Presentation is loading. Please wait.

Presentation is loading. Please wait.

Capital Expenditure Programme

Similar presentations


Presentation on theme: "Capital Expenditure Programme"— Presentation transcript:

1 Capital Expenditure Programme
16 October 2017 Presenter: Anthony Els Capital Expenditure Programme Tariff Consultation

2 SECTION CONTENT Demand growth forecast
2. Augmentation & Renewal plan to 2037 3. Capital budget

3 Supply Area Overview 2016/2017 average demand: 4084 Mℓ/d
3500+ km of pipeline: mostly > 600 mm 60 reservoirs: 20Mℓ to 650 Mℓ 600 Bulk meters ≥ 100mm

4 Potable Demand Snapshot 4 metros = 83% of demand

5 Potable Demand Potable water users Historical growth Municipalities
Mines Direct Users Historical growth AADD increase from 1000 Mℓ/d in 1965 to 4084 Mℓ/d in 2016/2017 Several decades of growth in the 3% to 6% per annum range AADD Growth from 2007 to 2017 averaged ~2.4% Currently at ~2%

6 Forecasting Demand in future
Domestic usage is ~71% of total Natural population growth, inward migration, AIDS, service backlogs, system losses Factors affecting demand growth Estimated population in 2010 – 11.7 million Projected population by 2030 – 14.7 million (Annual pop. growth rate is declining) Population demographic model Supply 83% of total demand to four metros: Johannesburg, Ekurhuleni, Tshwane, Emfuleni Metros forecast av. growth of 1.5% to 2% p.a. Questionnaire model (major customers)

7 Demand Growth Forecast
Current growth Currently at ~2% (was negative last year during restrictions) Projected growth After compiling and correlating data, a decline is seen in both ‘natural’ population growth and inward migration: Medium term growth of 1.80% p.a. By 2035 a growth rate of 1.25% p.a. Growth may level off by about 2070 (0%) Year 2020 2025 2030 2035 Average Potable Demand (Mℓ/d) 4700 5100 5500 5900

8 Identical growth gradient Possible future abstraction licence Scenario 1: growth as per Infrastructure Planning Projection (no WDM) Scenario 2: Demand progressively reduced 7.5% Historical Abstraction Current proposed abstraction licence Scenario 3: Demand quickly reduced By 15% for 5 – 8 years, before growing again (currently mainly due to 2016 restrictions: WDM only partially contributed to low 2016/2017 AADD)

9 Response to limited raw resources
Integrated Vaal River System (IVRS) Project 1600 Committee to establish common ground on usage and abstraction (RW, DWS, SALGA, COGTA) Water conservation. Measurement: RW statistical model Problem area indication RW sets up and monitors demand targets for RW users; Develops and implements appropriate protocols for: Medium term: compliance with abstraction limit of 1600 m³/annum set by DWS until 2025 (until Lesotho Highlands Ph II). Shorter term drought and emergency situations, using a phased approach Monthly target monitoring: Measurement shows that 3 months into the year, customers are cumulatively 5% over ttl. license target. There is currently no contractual enforcement….

10 Response to limited raw resources
Water Demand Management efforts (medium term) Municipal WDM focuses on municipal delivery infrastructure (closing gaps on unaccounted-for water). However: Acknowledgement of - and action on - high night flow areas required Abnormally high household leaks need fixing in homes. Municipalities are currently required to have WDM plans Rand Water have not yet seen a reduction in projected growth based purely on WDM efforts. Much better results were seen during restriction periods: Emergency actions; short term; when required: Phase 1: Notify municipalities to reduce minimum night flows (MNF) Phase 2: RW assists distressed RW bulk systems from other RW systems Phase 3: RW intervention: restrict top 25 meters by quantity (may change to top 25 meters, prioritized by least efficient recent water usage)

11 Knock-on effects of restricting growth
Actively reducing demand growth reduces income stream Fixed costs remain = a less efficient operating model Slower growth requires reactively slowing the augmentation programme as follows: Long lead time large projects currently underway would be completed Several future projects identified for deferral. However: Some augmentation projects are required to facilitate renewal. These projects cannot be slowed. In 95% of renewal project cases, deferral is not an option: renewal completion dates are based on condition, not demand growth Cutting capital spending has consequences: if growth resumes, it takes time to get capital projects back on track

12 SECTION CONTENT Demand growth forecast
2. Augmentation & Renewal plan to 2037 3. Capital budget

13 Supply systems for Planning
Note: Primary = Raw Water + Vereeniging + Zuikerbosch Rand Water Eikenhof Supply System Zwartkopjes Supply System Palmiet Supply System Mapleton Supply System Booster Systems Primary Systems Vereeniging Purification System Zuikerbosch Purification System Raw Water Supply System

14 Supply systems City of Tshwane Palmiet system Eikenhof system
Mapleton system Zwartkopjes system Primary systems Vaal Dam

15 Corporate Systems Booster Primary 200km

16 Required Augmentation
Augmenting for 2015 to 2030 cycle Projected growth in peak day demand = 1600 Mℓ/d over 15 years Growth split between four booster systems Northern Jhb Tshwane Madibeng Central Jhb Southern areas Eastern Tshwane Ekurhuleni Mpumalanga North west Jhb West Rand Rustenburg Zwartkopjes system 300 Mℓ/d growth Palmiet system 600 Mℓ/d growth Eikenhof system 400 Mℓ/d growth Primary (refurb) Mapleton system 300 Mℓ/d growth Primary Primary systems 1600 Mℓ/d growth Primary

17 Peak demand by pumping station
Design capacity Projected peak day demands (Mℓ/d) Yellow = WDM change (indicative) 2020 (2025) 2025 (2030) 2030 (2035) 2035 (2040) Primary Systems Zuikerbosch 3810 4300 4800 5300 5800 Vereeniging 1200 1300 Booster systems Palmiet 1875 2000 2190 2380 2570 Mapleton 960 990 1080 1180 1270 Eikenhof 1800 1470 1610 1750 1880 Zwartkopjes 800 760 780 840 880

18 Augmentation & Renewal Planning
Augmentation: Increase capacity to meet future demands 20 year view of projects based on long term view of demands Renewal: Asset management approach Operate and maintain asset; Monitor asset condition; Refurbish and extend life of existing asset when appropriate; Replace when economical and if condition merits it Integration of augmentation and renewal Renewal and augmentation can facilitate each other (e.g. pipelines) Integrated at plant, site and system level

19 Asset Portfolios Buildings and property Civil structures Pipelines
Mechanical Electrical Process Automation

20 Asset Replacement Value
Buildings Civil Pipelines Electrical Mechanical Process Automation All Assets Raw Water 74 1,619 2,083 1,403 29 5,208 Vereeniging 1,254 881 1,997 172 1,508 3,122 12 8,946 Zuikerbosch 1,972 4,158 264 1,707 7,016 20 15,137 Eikenhof 275 1,572 17,241 128 1,258 239 4 20,717 Zwartkopjes 1,499 847 8,850 126 892 242 3 12,459 Palmiet 204 2,867 19,635 105 1,020 220 2 24,053 Mapleton 164 1,165 13,283 81 856 151 15,703 Total 5,442 13,109 63,089 876 8,644 11,019 44 102,223

21 Infrastructure Augmentation
Providing for 2015 to 2030 augmentation cycle Augment primary capacity, with associated major pipelines and booster pumping capacity Package of linked major projects for backbone infrastructure 2009 Additional Water Supply (AWS) Scheme Anchor project for the 2009 AWS Scheme Purifies and pumps into the network additional 1200 Mℓ/d after completion of phase 2 Station 5 at Zuikerbosch

22 The Primary systems Augmenting for 2015 to 2030 cycle
Projected growth in peak day demand = 1600 Mℓ/d over 15 years Growth split between four booster systems Palmiet system 600 Mℓ/d growth Mapleton system 300 Mℓ/d growth Eikenhof system 400 Mℓ/d growth Zwartkopjes system 300 Mℓ/d growth Primary systems 1600 Mℓ/d growth North west Jhb West Rand Rustenburg Central Jhb Southern areas Northern Jhb Tshwane Madibeng Eastern Tshwane Ekurhuleni Mpumalanga Primary Primary (refurb)

23 The Primary systems Overview Growth in demand
Increase of 1600 Mℓ/d from 2015 to 2030 Key augmentation projects Station 5 at Zuikerbosch “anchor project” (1200 Mℓ/d in two phases) BG3 (complete). BG4, Canal 2 & Forebay in future B19 raw water pipeline from Lethabo to Vg (nearing completion) Lethabo pipe header upgrade Panfontein Drying Beds Phase 2 Key renewal projects Vg Engine Room 4 upgrade 250 Ml/d Sedimentation Tank at Vg Vg Chlorine plant 2 Zb Filter House 1 renewal Zb Chlorine Plant 4 renewal

24 Primary Systems – 1600 Mℓ/d growth from 2015 to 2030
Additional Purification Plant – 1200 Mℓ/d capacity Additional raw water pipelines and purification plant upgrades Vg Sed Tank R250 million over next 5 years (renewal) B19 raw water pipeline R10 million budget for 2016/17 Station 5 at Zuikerbosch 1200 Mℓ/d capacity in two phases R1 910 million budget over 5 yrs: aug Panfontein Drying Beds R490 million over next 5 years (augment)

25 The Palmiet system Augmenting for 2015 to 2030 cycle
Projected growth in peak day demand = 600 Mℓ/d over 15 years Mapleton system 300 Mℓ/d growth Eikenhof system 400 Mℓ/d growth Zwartkopjes system 300 Mℓ/d growth North west Jhb West Rand Rustenburg Central Jhb Southern areas Northern Jhb Tshwane Madibeng Eastern Tshwane Ekurhuleni Mpumalanga Primary Primary (refurb) Palmiet system 600 Mℓ/d growth Primary systems 1600 Mℓ/d growth

26 The Palmiet system Overview Main customers Growth in demand
Eastern and Northern Johannesburg Central, Western and Northern Tshwane Western Ekurhuleni Growth in demand Increase of 600 Mℓ/d from 2015 to 2030 Key augmentation projects Zuikerbosch to Palmiet B17 pipeline (in commissioning) Engine Room 3b at Palmiet pumping station Germiston to Lombardy O6 pipeline Klipfontein to Brakfontein H39 pipeline Brakfontein-Lyttleton Heights H43 (and H14 pipeline) Kensington to Yeoville pumping station Key renewal projects O2 Pipeline and O1/G25 Palmiet Engine Room 1 upgrade B6 refurbishment

27 Zuikerbosch Purification & Pumping Station
Palmiet System – 600 Mℓ/d growth from 2015 to 2030 Additional Engine Room – 600 Mℓ/d capacity Total of 150 km of pipe between 600 mm and 2100 mm diameter H43 Brakfontein – Lyttleton R724 million in next 5 years (aug) O6 Germiston to Lombardy R460 million in next 5 years (aug) H39 Phase 2: Dale Road to Modderfontein R350 million in next 5 years (aug) Kensington – Yeoville system R400 million in next 5 years (aug) B6 Renewal: R240 million over 5 years (renewal) Engine Room 3b at Palmiet 600 Mℓ/d operational capacity (aug) R 10 million in 2018 (commission) G37/H37 B17 (commission in 2017) Zuikerbosch Purification & Pumping Station

28 The Mapleton system Augmenting for 2015 to 2030 cycle
Projected growth in peak day demand = 300 Mℓ/d over 15 years Eikenhof system 400 Mℓ/d growth Zwartkopjes system 300 Mℓ/d growth North west Jhb West Rand Rustenburg Central Jhb Southern areas Northern Jhb Tshwane Madibeng Eastern Tshwane Ekurhuleni Mpumalanga Primary Primary (refurb) Palmiet system 600 Mℓ/d growth Mapleton system 300 Mℓ/d growth Primary systems 1600 Mℓ/d growth

29 The Mapleton system Overview Main customers Growth in demand
Central and eastern Tshwane Eastern Ekurhuleni Growth in demand Increase of 300 Mℓ/d from 2015 to 2030 Key augmentation projects Zuikerbosch – Slangfontein B16 pipeline Engine Room 3 at Mapleton pumping station S4 Van Dyk Park to Vlakfontein pipeline Vlakfontein Reservoir 200Mℓ Bronberg Reservoir 100Mℓ R5 Vlakfontein to Mamelodi pipeline Key renewal projects Mapleton disinfection plant M1 pipeline replacement

30 The Mapleton system Mapleton System 100Mℓ Bronberg Reservoir
R124 million over next 4 yrs (aug) R5 Vlakfontein, Mamelodi R432 million over next 4 yrs (aug) 200Mℓ Vlakfontein Reservoir R330 million over next 5 yrs (aug) S4 Van Dyk Park - Rynfield R468 million over next 5 yrs (aug) 210Mℓ Brakpan Reservoir R134 million over next 5 yrs (aug) M1, M6 replacement R237 million over next 5 yrs (renew) N1 Selcourt - Wildebeestfontein R300 million over next 5 yrs (renew) B16 Zuikerbosch - Slangfontein R570 million over next 5 yrs (aug) Engine Room 3 at Mapleton R660 million over next 5 yrs B16 Zuikerbosch – Slangfontein system

31 The Eikenhof system Augmenting for 2015 to 2030 cycle
Projected growth in peak day demand = 400 Mℓ/d over 15 years Zwartkopjes system 300 Mℓ/d growth North west Jhb West Rand Rustenburg Central Jhb Southern areas Northern Jhb Tshwane Madibeng Eastern Tshwane Ekurhuleni Mpumalanga Primary Primary (refurb) Palmiet system 600 Mℓ/d growth Mapleton system 300 Mℓ/d growth Eikenhof system 400 Mℓ/d growth Primary systems 1600 Mℓ/d growth

32 The Eikenhof system Overview
Main customers (includes significant mining use) Western Johannesburg and Soweto Far West Rand Rustenburg Growth in demand Increase of 400 Mℓ/d from 2015 to 2030 Key augmentation projects F34 Waterval to Weltevreden pipeline F49 Krugersdorp to Randfontein pipeline Meredale reservoir 1 x 210Mℓ Additional Meredale reservoir storage (2 x 100Mℓ) Key renewal projects Replace Eikenhof disinfection plant Replace F18 pipe at Witpoortjie Reservoir Replace pipework from Moroka to Zuurbekom

33 The Zwartkopjes system
Augmenting for 2015 to 2030 cycle Projected growth in peak day demand = 300 Mℓ/d over 15 years Northern Jhb Tshwane Madibeng Central Jhb Southern areas Eastern Tshwane Ekurhuleni Mpumalanga North west Jhb West Rand Rustenburg Zwartkopjes system 300 Mℓ/d growth Palmiet system 600 Mℓ/d growth Eikenhof system 400 Mℓ/d growth Primary (refurb) Mapleton system 300 Mℓ/d growth Primary Primary systems 1600 Mℓ/d growth Primary

34 The Zwartkopjes system
Overview Main customers Northern Emfuleni and Southern Johannesburg Central Johannesburg (largely developed, low growth expected) Benoni Growth in demand Increase of 300 Mℓ/d from 2015 to 2030 Key augmentation projects Amanzimtoti pumping station upgrade T5 Orange Farm to Ennerdale pipeline Daleside additional 40 Mℓ reservoir Arcon Park to Langerand A13 pipeline duplication Key renewal projects Replace Vg-Daleside A6 and A8 pipelines Lay new Zb-Daleside pipe to allow refurbishment of B1 and B2

35 Balancing and Emergency Storage
Reservoir storage 20 year plan includes additional 1300 Mℓ reservoir storage 40% to 50% in Eikenhof system to boost emergency storage Water quality – total volume, through flow, circulation Availability of appropriate sites Projects “Lower” Meredale reservoirs (and associated pipework) Daleside 40Mℓ reservoir Vlakfontein 210Mℓ reservoir Bronberg 100Mℓ reservoir Hartebeesthoek additional reservoir Brakpan 210Mℓ reservoir

36 SECTION CONTENT Demand growth forecast
2. Augmentation & renewal plan to 2037 3. Capital budget

37 2018 2037 Raw Augmentation Vg Zb Eik Red projects: timing can be altered to suit WDM success Zks Palmiet Mapleton

38 Infrastructure renewal
2018 2037 Raw Vg Infrastructure renewal Zb Eik Zks Pal Mapleton

39 Capital budget for 2017/18 Annual budget 2017/18
Augmentation projects – R1.79 billion â Renewal projects – R1.23 billion á Overall: R3.02 billion á Annual budget 2017/18 Forecast average demand growth of 1.8% to 2020, (1.75%->2025, 1.6% -> 2030, 1.2% -> 2035) Roughly equates to a need for ~R1.6 bn p.a. 2018 planned is R1.2 bn (R1.5 bn for 2019) Appropriate Augmentation spend RW should be spending 1% - 2% p.a. of replacement value on renewals This equates to R0.8 – R1.6 billion p.a. Planned for 2018 is R1.23bn/a (1.16%). 2019: R1.5bn (1.4%) Appropriate Renewal spend

40 Replacement value (RM) 2018 renewal allocation (Rm)
Renewal spending Asset category Replacement value (RM) Design life (yrs) 2018 renewal allocation (Rm) Pipelines 63 090 65+ 432 Civil 13 110 50 to 100 248 Mechanical 8 644 30+ 58 Process 11 020 15 to 20+ 150 Buildings 5 442 80+ 51 Electrical 876 20 to 30+ 111 Automation 44 5 to 10+ 137 Total 1 187 (1.16%)

41 New projects entering scoping in 2017
Item System Project Description Indicative ttl cost Rm 1 Primary Stabilization of embankment at Intake 1 – refurbish 65 2 Pipe A18 replace portions of pipe 60 3 Laboratory Extension at Vg 64 4 Palmiet Pipe O6 augmentation (Phase 2) Germiston to Lombardy East 710 5 Pipe B6 refurbishment (Phase 1) 310 6 Pipe G25 slip lining/refurbishment 105 7 Mapleton Reservoir new 80Mℓ at Selcourt 112 8 Pipe L10 New Era to Modder East replacement 126 9 Pipes M2/M5 Servaas stasie to Heidelberg ptns refurbish/replace 117 10 Pipes K2/K7 Kleinfontein to Modder East replacement 97 11 Pipes K3/K6 Apex to Government Areas replacement 12 Eikenhof Pipes D1, E4, E6 replacement between Zuurbekom and Libanon Pumping Station. 325 13 Pipes F6, F11, F13 Roodepoort P.S to Krugersdorp Res. 260

42 5-year Capital Expenditure (2018 - 2022)
forecast of R19.8 billion for continuing business System Augmentation (Rm) Renewal (Rm) Total Eikenhof 1 088 á 2 432 á Mapleton 3 395 á 1 014 á 4 409 á Palmiet 2 198 á 714 á 2 912 á Primary systems 3 145 â 1 627 á 4 772 â Zwartkopjes 1 073 á 2 085 á Other & All/spread 258 2 607 2 865 8 450 á á Percent of total Aug: (57%â) Renewal: (42%á) 100%

43 Capital Expenditure: Augmentation + Renewal forecast

44 Thank You…


Download ppt "Capital Expenditure Programme"

Similar presentations


Ads by Google