LCG experience in Integrating Grid Toolkits
Zdenek Sekera IT Division , CERN 16/11/2018 CHEP2003
2
zdenek.sekera@cern.ch CHEP2003
Outline What is LCG? LCG project goals With whom we work ? Basic LCG milestones What is LCG-0 ? What are the plans for LCG-1 ? What is the process to get to LCG-1 ? Conclusions Authors: Piera Bettini, Ian Bird, Flavia Donno, Maarten Litmaath, Di Qing, Louis Poncet, Andrea Sciaba, Zdenek Sekera, Marco Serra, David Smith 16/11/2018 CHEP2003
3
zdenek.sekera@cern.ch CHEP2003
What is LCG? LCG = LHC Computing Grid Creating the infrastructure for computing needs of LHC HEP experiments (Atlas, CMS, Alice, LHCb) All are worldwide collaborations, consequently the software has to work worldwide 16/11/2018 CHEP2003
4
zdenek.sekera@cern.ch CHEP2003
Project Goals Goal – Prepare and deploy the LHC computing environment to help the experiments to analyze the data coming from the detectors applications - tools, frameworks, environment, persistency computing system global grid service cluster automated fabric collaborating computer centres grid CERN-centric analysis global analysis environment central role of data challenges This is not another grid technology project – it is a grid deployment project 16/11/2018 CHEP2003
5
zdenek.sekera@cern.ch CHEP2003
LCG goals LCG goal is to bring physics world together by creating a user friendly, production quality environment for data processing and physics analysis. How? By integrating different grid toolkits or grid middleware into a homogenous package to guarantee the interoperability among different “ways of doing things”. LCG does NOT write grid middleware. We want physicist to use the same commands no matter where they work, in the USA, Europe, Asia. This makes them feel “at home” and surely their efficiency is much higher. 16/11/2018 CHEP2003
6
What is “production quality”?
It is all of the following in no particular order: availability 24 x 7 performance stability, robustness user friendliness maintainability user support 16/11/2018 CHEP2003
7
zdenek.sekera@cern.ch CHEP2003
Who are our partners? LCG is currently a “customer” of: iVDGL - VDT toolkit (including Globus & Condor toolkits) EDG - European DataGrid project EDT - European DataTag project (monitoring) Globus - underlying software GLUE schema – HICB (DataTag & iVDGL) product HICB = HEP Intergrid Coordination Board LCG can be considered a joint effort of all. It pulls together needed components from existing projects. We have to give credit to all developers in all these organizations for their effort in helping us to achieve the final LCG goal: to provide a well-defined user friendly environment. 16/11/2018 CHEP2003
8
zdenek.sekera@cern.ch CHEP2003
Basic LCG milestones LCG is focused on batch & experiments data challenges (phase 1) LCG release milestones: February - LCG-0 (deployment test, not publicly available) July - LCG-1 (production pilot) First publicly available LCG service November - LCG-1 (production system) Performance release needed for data challenges in 2004. We have a first set of integrated software and currently use it for deployment tests (LCG-0) 16/11/2018 CHEP2003
9
zdenek.sekera@cern.ch CHEP2003
LCG-0 WorldGrid demo last year (e.g Supercomputing 2002) demonstrated interoperability between VDT-EDG toolkits We went a step further by integrating VDT and EDG into a single package consisting of EDG VDT “Glue” schema It’s purpose is to setup infrastructure and release process rather than Grid functionality itself The important task is to determine the necessary work to be done by laboratories to get integrated 16/11/2018 CHEP2003
10
zdenek.sekera@cern.ch CHEP2003
LCG-0 deployment We are deploying it on tier 1 centers, goal is about 10 sites in the initial deployment Currently deployed by: CERN, RAL, CNAF, Taiwan being installed by: FNAL, U of Tokyo we expect a few more sites later 16/11/2018 CHEP2003
11
What did we learn with LCG-0
Release process is difficult: Many specific issues for different sites (how many service machines, what services on service machines, security issues) Packaging is an issue (USA x Europe, rpm x tar, pacman x LCFG) Installation is complicated, we cannot force ourselves on sites with our installation tools when they have already their own Configuration is major problem, it is far too complex Testing is a huge issue, we need to test different architectures, features, networking, interoperability 16/11/2018 CHEP2003
12
zdenek.sekera@cern.ch CHEP2003
Research? Deployment? If we want to/need to reconfigure service nodes, all neccessary changes are now propagated to configuration files manually. That cannot stay this way, we have to find much more automatic ways. Compare to Linux installation 3-4 years ago and today. We must probably go the same way of understanding what the real configuration issues are, only we would like to be much faster. The integration of worker nodes must be resolved by sites themselves, we will help. These issues (and more) make the difference between the research project ending with a demo and the product to be used for a production. 16/11/2018 CHEP2003
13
zdenek.sekera@cern.ch CHEP2003
What will be LCG-1? Expected to be: EDG VDT (Globus 2.2.4) We are just beginning LCG-1. We have a Certification & Testing testbed at CERN consisting of 40 machines we can configure as desired. Certification & Testing is a joint project (e.g. VDT is testing Globus and Condor). 16/11/2018 CHEP2003
14
LCG-1 Certification Testbed
U of Wisconsin 40 machines at CERN 16/11/2018 CHEP2003
15
zdenek.sekera@cern.ch CHEP2003
LCG-1 certification basic grid functionality connectivity grid services security resource brokering data management (replication, catalog) configurability error recovery real world applications site verification suite 16/11/2018 CHEP2003
16
Test and Validation process
Developers machines Build system Development Testbed ~15cpu Certification Testbed ~40cpu Production Unit Test Build Integration Certification Production WPs add unit tested code to CVS repository Run nightly build & auto. tests Individual WP tests Grid certification Certified public release for use by apps. Build system Integration Team Test Group Users Tagged package WPs Tagged release selected for certification Overall release tests Certified release selected for deployment Application Certification Fix problems Appl. Representatives Releases candidate Releases candidate Tagged Releases Certified Releases Office hours 24x7 Bugzilla anomalies reports 16/11/2018 CHEP2003
17
zdenek.sekera@cern.ch CHEP2003
Conclusions With LCG-0 we have proved it is possible to integrate different toolkits (VDT & EDG) into a single package that can be repeatable deployed. We have learned the difficult issues (installation, configuration, testing) that will require a special attention for LCG-1. The process how to get the first (July) LCG-1 release out has been setup and is operational. Incremental releases will be required to correct problems according to their priorities up to November LCG-1 release and possibly beyond. There is a difficult and long road ahead towards LCG-1 due to the complex software and aggressive schedule but we believe it can be managed with a systematic determined approach. It is a highly collaborative project so everybody has to contribute. 16/11/2018 CHEP2003