8-layer PC Board, 2 Ball-Grid Array FPGA’s, 718 Components/Board
DMB Production Boards 8-layer PC Board, 2 Ball-Grid Array FPGA’s, 718 Components/Board S. Durkin, J. Gilmore J. Gu, USCMS-EMU Meeting, Oct. 29, 2004
2
DMB Production Boards 220 boards delivered and tested
60 boards required repair 20 Dead Burr-Brown 16 bit ADCs 20 XiLinx eprom bit-errors Bad Chip Lots Board are being boxed and stored until needed at Ohio State S. Durkin, J. Gilmore J. Gu, USCMS-EMU Meeting, Oct. 29, 2004
3
DDU2004 Prototype VME FPGA DMB Input FPGAs 4 Input FIFOs GBE FIFO
XILINX Virtex2-500 DMB Input FPGAs 2 XILINX Virtex2Pro-20 4 Input FIFOs 512 KB each GBE FIFO 1024 KB 9U VME board, 220 mm depth FMM output port 15 Optical fiber inputs (just 1 for now) Gbit Ethernet Output To Local DAQ SLINK Mezzanine board connector DDU Control FPGA XILINX Virtex2Pro-7 S. Durkin, J. Gilmore J. Gu, USCMS-EMU Meeting, Oct. 29, 2004
4
DDU 2004 Design FPGA FPGA MGT-HSC FPGA FPGA FMM/Slow Control VME
BUSY READY L1 Throttle Data Errors Loss of Synch FPGA FPGA VME Slow-control and JTAG FIFO MGT-HSC Fiber links from 15 DMBs FPGA DCC/DAQ Multi-Gigabit Transmission via High-Speed Connector to backplane FIFO FPGA TTC control via backplane S-Link (for SP use) Transceivers Gigabit Ethernet To Local DAQ S. Durkin, J. Gilmore J. Gu, USCMS-EMU Meeting, Oct. 29, 2004
5
DDU Performance Beamtest results Conclusions
Multiple DMB readout to DAQ Good performance via DCC/S-Link and gigabit Ethernet spy path Error-free operation at high rates Passed all tests up to 6-times LHC expected data rate DDU buffer size is more than sufficient for LHC Status/error monitoring All checks performed as expected, verified in offline software Verified consistent fast monitoring path performance Detected event and bunch counter inconsistencies Caused by non-uniform implementation of EMU board resets Conclusions The DDU passed all tests with no problems Ready for ESR S. Durkin, J. Gilmore J. Gu, USCMS-EMU Meeting, Oct. 29, 2004
6
DCC Status: DCC Beam Tests
Fully stuffed DCC was used for Sept/Oct. CERN Beam test It corrected several mistakes (clock driver from LVDS to PECL, Bus_LVDS buffers) in rev1. This board works It distributes the TTC control signals. The L1A number and BX number sync with DDU in the FED crate, and sync with DMBs in the peripheral crates. It reads data from DDU and sends data through SLINK to computer. With the ‘FakeDDU’, in addition to DDU, the DCC sends data at >240MB/s to the computer, which jammed the SLINK receiver. VME SLINK S_FIFO In_fpga spy in_fifo TTCrx M_fpga DDU C_bus S. Durkin, J. Gilmore J. Gu, USCMS-EMU Meeting, Oct. 29, 2004
7
DCC Status: Some issues
Issues with the board: On the DDR fifo, there are internal cross talk from D22 to D21 line. Get around: do not use D21, we only need 33 bits out of 40bits on the FIFO. The DDR fifo works at 125MHz reading speed, but the manufacture downgraded its rating to 100MHz. Solution: Even 100MHz (800MB/s) is good enough for our application (Slink ~200MB/s) At the CERN beam test, we do not have a readout system fast enough to handle the 200MB/s data, required by SLINK, this is not a real problem. S. Durkin, J. Gilmore J. Gu, USCMS-EMU Meeting, Oct. 29, 2004
8
DDU /DCC Conclusion DDU/DCC/Controller ESR
November 12, 2004 CMS Electronics Week Production will begin after passing Review S. Durkin, J. Gilmore J. Gu, USCMS-EMU Meeting, Oct. 29, 2004