Download presentation
Presentation is loading. Please wait.
1
Solar Orbiter EUI Extreme UV Imager
SO Cleanliness Working Group #24 Stevenage 10 – 12 October 2017 Jean-Philippe Halain Udo Schühle (MPS)
2
Outline Summary of individual instrument status (including final bake-outs overview); open issues affecting cleanliness and contamination, including evaluation of the impacts of the current Airbus contamination predictions; status of action items (including evidence of closure, where applicable).
3
a) Summary of EUI project status
EUI flight model Three units delivered + harness
4
a) Summary of EUI project status
S/C activities CEB FM unit installed on S/C panel PRT installed S/C harness modified Electrical tests to be performed Harness To be installed
5
a) Summary of EUI project status
S/C activities OBS Delivered to ADS in May 2017 Pre-handover functional check OK, using FS CEB Panel flatness checked (< 0.05 mm) Handling jig fixation to OBS unit improved Kapton collar installed on entrance baffles Helicoils replaced by self-locking helicoils Thermal straps installed on OBS interfaces OBS mounted on platform Harness fixation on OBS back panel to be performed Alignment to be performed Electrical tests to be performed
6
Cleanliness status OBS cleanliness status (summary)
Cleanliness and Contamination Report RP-CSL-SOEUI-17053, Iss. 1, Rev. 2 ( ) MOC measured After assembly: < 0,2 g/cm² After TVAC / Bake-out: < 0,2 g/cm² At delivery: < 0,2 g/cm² PFO measured At delivery 149 ppm (over 101 days) Intermediate cleaning of internal cavity during assembly External surfaces cleaned before delivery Bake-out 70°C for 72 hours TQCM deviation of linearity (f”/f’) ~ 0,37% after 40 hours RGA major peak (water) at 8x10-7 mbar partial pressure
7
Cleanliness status OBS Assembly Airborne counter log: ISO 5 conditions
During the overall assembly time period an airborne counter was located next to the OBS unit.
8
Cleanliness status OBS assembly
MOC witness sample monitoring: < 0, g/cm² 10/01/2017 06/02/2017 06/03/2017 Witness samples located in the CSL cleanroom are monitored monthly, showing cumulative molecular levels.
9
Cleanliness status OBS TVAC
MOC witness sample monitoring: < 0, g/cm² 17/04/2017
10
Cleanliness status OBS bake-out
all sub-systems baked out before assembly TQCM Deviation of linearity (f”/f’) ~ 0,37% after 72 hours RGA monitoring all sub-systems have been baked out before assembly
11
Cleanliness status OBS at delivery PFO MOC 149 ppm over 101 days
Cleaned before delivery MOC << 40 ng/cm² The PFO witness sample that is following the OBS FM unit since its AIT start in January has been analysed. A total of 149 ppm over 101 days was collected, i.e ppm/day (much better than required in a ISO5 cleanroom). The OBS unit has however been cleaned many times along that period and the effective particulate cleanliness level is thus below the required 100 ppm on external hardware surface as specified in [RD 4] and in EID-A. The measured MOC level is much below the limit of [RD 4] and in EID-A, of 370 ng/cm².
12
Cleanliness status CEB cleanliness status PFO Bake-out
Build & test:10 ppm Vacuum bake-out: 6 ppm Packaging: 3 ppm EMC test: 200 ppm (before cleaning outgoing inspection) TVAC: 3 ppm Total: 220 ppm Bake-out 80°C for 90 hours, TQCM ≤1% outgassing deviation from linearity after 20 hours RGA major peaks above 40AMU < 8.0x10-10 mbar partial pressure
13
Project status CEB bake-out TQCM RGA
14
b) open issues affecting cleanliness
Contamination analysis SOL.S.ASTR.RP.00037: Table 5.4: molecular contamination during ground tests: The EUI EXT HW sensitive surfaces are inside the S/C cavity which should accumulate MOC at a predicted rate of 0.2 ng/day, while the table shows 1 ng/day.
15
c) status of action items
AI#22: Airbus-DS, ESA and instruments teams to review which materials may need to be tested. The solar array CDR is scheduled for June 2017. EUI exposed to UV are the Entrance Baffle and the Internal Doors surfaces. They are all made of aluminium. No test required. AI#24: Airbus DS plans to remove instruments covers during TV activities. Instruments teams to check compatibility of covers’ materials with thermal vacuum conditions if covers need to be maintained. EUI covers need to be removed before TV test. AI#26: Instruments teams to provide relevant information on frequency of measurements and handling of contamination witnesses at Airbus DS. EUI contamination witnesses have been removed and analysed. Further monitoring to be made by Airbus DS. Δ-CDR AI#1: ESA to ensure that each instrument PI will need to study the updated SOL.S.ASTR.RP and the impact of the spikes on their instruments and implement operational constraints in their instrument user manual. open
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.