New Mexico Secretary of State
Critical System Hardware Replacement Implementation Certification Presentation should be high level, highlighting points agency wants to emphasize from their full business case. Presentation should be no longer than 10 slides- Template uses 7, 3 are “at large” and can cover additional topics, or add to existing as needed. Notes on all slides are provided as general guidance and should be used only as applicable (ie. Not all items may apply to all projects) Agency should use presentation to make the argument why THIS project is the most worthy of C2 funds Why this need is the most critical and urgent Why this C2 spend request returns the most value to taxpayers/state Why Agency is the most ready to succeed with the C2 investment being made. Include Business Owner and Executive Sponsor Rehearse so things are well coordinated Be clear & concise Adhere to allocated time (Total 20 mins, 10 – 12 mins for Presentation, 5-8 mins for Q&A) Committee will have your Business Cases, so don’t repeat all info, simply reference it Blezoo Varghese, Acting Chief Information Officer
2
Business Need Aging physical infrastructure on critical application systems reaching manufacturer’s end of life (EOL). Risk of unsupported equipment failure that can result in prolonged system downtime and or data loss. High risk of prolonged interruption of core SOS services increases the longer we wait to replace it. Inability to recover swiftly from hardware failures resulting in unplanned and prolonged downtime and data loss; New system applications, including SERVIS and NMBFS, are quickly outgrowing the current storage, performance, and redundancy capacity of the current hardware platform; Unmet statutory requirements for a failover site for SERVIS; and Increased security risks – designation of election systems as critical infrastructure highlights the debilitating impact an outage or compromise of an election system.
3
Project Description Replace critical server, storage and network equipment reaching end of life Hardware refresh will allow SOS to reduce risk of prolonged system downtime and data loss Increase storage and redundancy for mission critical applications and process
4
Software Defined Storage
Proposed Solution Details: HyperConverged VxRail™ Infrastructure Summary Compute 9 appliances of VxRail E-Series 2x Intel Xeon Gold GHz (12 Core) 256GB per node Software Defined Storage VSAN (Includes Deduplication and Compression) Network 20 x 10Gbps SFP+ Ports for PROD 16 x 10Gbps SFP+ Ports for DR Management VxRail Mgmt Prod VXRail (5U) 2 x Intel Xeon Gold Ghz 12 Cores 120 Cores per Cluster 256 GB RDIMM 1.2 TB per Cluster x 800 GB SSD & 6 3 . 84 TB SAS SSD 48 66 TB Usable Per Cluster 5 x VxRail E Series 1 U Appliance VxRail Configuration Summary ( PROD ) 4 x 10GB SFP+ ports Storage Summary Cluster QTY SSD Capacity Per Node HDD Capacity Per Node Total Usable Capacity PROD 5 102.7TB (RAW) NA 46.1TB DR 4 82.1TB (RAW) 34.4TB Total 9 80.5TB SW Licensing License QTY Provided By VMware vSphere Enterprise Plus Edition (per CPU socket) 18 Customer VMware vSAN included Support 5 Years ProSupport Mission Critical Support (Prod) 5 Years ProSupport Next Business Day Support (DR) DR VXRail (4U) 2 x Intel Xeon Gold GHz 12 Core 96 Cores per Cluster 256 GB RDIMM 1TB per Cluster x 800 GB SSD & 6 3 . 84 TB SAS SSD 34 4 TB Usable Per Cluster x VxRail E Series 1 U Appliance VxRail Configuration Summary ( DR ) 10GB SFP+ Ports Services Quantity Delivered By Notes Deployment and Implementation ProDeploy Plus Onsite Implementation Services 9 Dell EMC 5 Nodes in PROD 4 Nodes in DR Included two separated locations 30 Days Post Deployment Assistant 1 Data Migration (VM) 25 VMs Solution Architect Services Hours 8 Hours Including 4 hours of Project Management hours. Training and Education HCI Training Credit Valid 1 year 1 Seat
5
Proposed Solution Details: Networking and Data Protection
Two S5048-ON Air Flow controllable 48 ports of 1/10/25 Gbps 6 ports of 40 Gbps Running in HA mode Virtual Line Trunking (VLT) Data Protection: Data Domain 3300 16TB Useable PROD 16TB Useable DR Solution includes: DD Boost/Replication software with encryption Professional Services and Maintenance 3 or 5 years of Pro Support software support included ANM Basic implementation and installation services included
6
High Level Proposed Architecture Overview
7
Finalized Procurement Infrastructure changes Networking verifications
Project Timeline Equipment refresh 2018 1st 2018 2nd 2019 3rd 2019 3rd 2019 4th Quarter Quarter Quarter Quarter Quarter Planning Finalized Procurement Infrastructure changes Networking verifications Migration and cutover Discovery, Planning, Vendor meetings and presentations. Quote from final vendor Submit latest quotes to purchasing weeks lead time from purchase to delivery Move rack at OSO Grande to DoIT space at OSO. Equipment Stand up at DoIT and OSO datacenters. Verify layer 2 circuit between OSO and DoIT datacenters. VPN tunnels between NACP rack and DoIT rack, and NCAP rack and OSO rack. Identify low/no use servers to migrate, test and verify. Migration of Production servers will not take place until election certification and all testing is complete . Critical Hardware Systems Replacement – New Mexico Secretary Of State
8
Project Appropriation
FY18-19 C-2 Special Appropriation $825,000 Approved Capital Outlay (C2599 Chapter 80 Section 30) IV&V waiver approved on 7/10/2018
9
Questions?