Presentation is loading. Please wait.

Presentation is loading. Please wait.

Reliability Assessment Committee Reliability Workshop Priorities

Similar presentations


Presentation on theme: "Reliability Assessment Committee Reliability Workshop Priorities"— Presentation transcript:

1 Reliability Assessment Committee Reliability Workshop Priorities
Dave Angell, RAC Chair Western Electricity Coordinating Council

2 Western Electricity Coordinating Council
Approach Priority Topic Details Potential Action Zen approach Knowing the question is the first step to knowing the answer. Western Electricity Coordinating Council

3 Near-Term Priorities -> RAC
Improve inverter-based resources modeling in WECC base cases Evaluate changing resource mix impacts Clarify the roles, responsibilities and relationships between WECC Regional Planning Groups Transmission Planners Other stakeholders The answers from the Reliability Workshop are the near-term priorities Western Electricity Coordinating Council

4 Renewable Energy Models
WECC Approved Dynamic Model Library Version January 2018 GE PSLF Status Comments reec_a approved 3/19/14 Renewable energy electrical control model for Wind type 3/4 and Photovoltaic reec_b Renewable energy electrical control model for Photovoltaic WECC Approved Dynamic Model Library From EPRI Model User Guide - The collaborative community of stakeholders has worked under the Western Electricity Coordinating Council’s (WECC) Renewable Energy Modeling Task Force (REMTF). Thus, at the culmination of the work, the models were WECC approved and have found their way into several of the major commercial software platforms, namely, Siemens PTI PSS®E, GE PSLFTM, PowerWorld Simulator and PowerTech Labs simulations tools Western Electricity Coordinating Council

5 Western Electricity Coordinating Council
Blue Cut Fire Event Western Electricity Coordinating Council

6 Western Electricity Coordinating Council
Canyon 2 Fire Event Western Electricity Coordinating Council

7 Western Electricity Coordinating Council
reec_a Complex Western Electricity Coordinating Council

8 Western Electricity Coordinating Council
reec_b Simpler Western Electricity Coordinating Council

9 Action Update WECC Approved Dynamic Model Library GE PSLF Status
Comments reec_a approved 3/19/14 Renewable energy electrical control model for Wind type 3/4 and Photovoltaic reec_b Renewable energy electrical control model for Photovoltaic Where different variants of the same model exist, the preferred version for submittal to WECC is highlighted in green. Western Electricity Coordinating Council

10 Changing Resource Mix Impacts
Existing transmission path ratings Remedial Action Scheme effectiveness/fault-duty Resource adequacy and the effectiveness of traditional methods for determining resource adequacy The transmission and distribution system interface due to DER Essential Reliability Services specific to the Western Interconnection Western Electricity Coordinating Council

11 Transmission Path Ratings
Western Electricity Coordinating Council

12 Western Electricity Coordinating Council
Flow Limited Paths Transmission Paths may be limited by the amount of available resources rather than reliability considerations Studies and analyses performed to determine the Accepted Rating of a transfer path must use realistic simulations A transmission Path's Accepted Rating will not be lowered because its maximum achievable flow is reduced due to system changes made by others System owners that make such changes shall be responsible for mitigating any adverse impacts on the other system(s) Western Electricity Coordinating Council

13 Remedial Action Scheme Effectiveness
Colstrip Remedial Action Scheme (RAS) Acceleration Trend Relay (ATR) The generators advance during a short circuit on the power system. The ATR measures how fast the generators are advancing and trips unit(s) if to remain stable. When these units are replaced with wind, the ATR will not be available and a new RAS will need to be developed. Western Electricity Coordinating Council

14 Path Ratings & RAS - Action
Under Review and Revision Western Electricity Coordinating Council

15 Determining Resource Adequacy
13.5% 14% 39% 27% Information from the WECC 2017 Reliability Report – 2016 data Total Capacity 267,000 MW Assess vulnerabilities from fuel availability Need ability to analyze more resource variability Western Electricity Coordinating Council

16 Resource Adequacy – Light Load
System Peak July 27th at 5:00 PM System Minimum May 8th at 5:00 AM Western Electricity Coordinating Council

17 Light Load in California
Cal Independent System Operator Western Electricity Coordinating Council

18 Resource Adequacy – Load Variability
California Energy Commission data from November 2017 Western Electricity Coordinating Council

19 Resource Adequacy - Action
Expand resource adequacy measures probabilistic approaches that reflect resource and load variability and reliability characteristics Include non-peak system conditions Western Electricity Coordinating Council

20 DER and the T & D Interface
Distributed Energy Resources energy contribution in 2017 by state Western Electricity Coordinating Council

21 DER and the T & D Interface - Action
Ensure there is sufficient detail on DER capability and performance to determine BPS impact Identify the type and periodicity of information needed from DER to improve load forecasting and generator modeling Account for the uncertainty introduced by integration of variable generation and essential reliability services Western Electricity Coordinating Council

22 Western Interconnection Essential Reliability Services
Western Electricity Coordinating Council

23 Essential Reliability Services - Action
All new resources should have the capability to support voltage and frequency - FERC Forecasting, visibility, and participation of DERs as an active part of the electric grid – Utility Planners and WECC Western Electricity Coordinating Council

24 Western Electricity Coordinating Council
Clarify the Three Rs Planning Regions Responsibility WECC Role Stake-holder Relationship Western Electricity Coordinating Council

25 Questions Dave Angell dangell@idahopower.com (208) 388-2701
Here is what you should expect to see in December A three-year work plan Western Electricity Coordinating Council


Download ppt "Reliability Assessment Committee Reliability Workshop Priorities"

Similar presentations


Ads by Google