SLB Synchronization in H4 Beam (LIP - Lisbon)
55 () 60 62 () 56 54 63 64 59 58 TT SPS beam intensity histogram SLB bunch crossing occupancy histogram Validated!
2
Trigger in MTCC Major success!
25 million events at a trigger rate of ~ 200 Hz Mixture of DT, CSC, RBC, RPC-TB, HCAL-RCT trigs. Trigger requirements easily configurable Stable operation Stable run uptime > 1 hr many runs > 500K L1A. All subsystems synchronized Tracker, ECAL, HCAL*, RPC*, DT*, CSC* Readout & Trigger* Trig. throttling worked Even when trigger problems or noise > 1 kHz Impressive teamwork!
3
Results from MTCC Phase 2
HCAL-RCT Trigger in time w/DT Drift Tube Trigger vs. Calorimeter Trigger time in 25 ns bunch crossings (coincidence = 0 bx)
4
Selected MTTC Muon Trigger Results: Extrapolation of DT to CSC
Validated! & Relative CSC DT timing checked
5
Event display of DT & RPC
6
Trigger Installation in USC55
Regional Calorimeter Trigger: 18 crates RCT Crates installed in 10 Racks 10 crates have all tested cards installed 6 Global Cal. Trig. Crates also installed Cables connected to ECAL, HCAL, GCT Most other trigger systems have crates & cards installed Integration “pattern tests” underway
7
Global Calorimeter Trigger: First Phase Trigger installed in USC55
3 Jets Leafs Wheel Concentrator Wheel 3 Jets Leafs e/ Leafs Source Card Source Card Leaf Card Source Card Source Card Concentrator Card GTI Source Card Source Card Leaf Card Source Card Source Card 18/63 Source cards 1/8 Leaf cards 0/2 Wheel cards Proto/1 Concentrator Source Card Source Card 31 Source Cards 32 Source Cards