Contra Costa Community College District
7th Annual UC/CSU/CCC Sustainability Conference Contra Costa Community College District LMC CCC DVC BC WC SRC Best Practices New Construction/Major Rehab-Lighting Design Retrofit Sustainable Operations–Renewables/Innovative Energy Generation
2
CCCCD Established December 1948 Three Colleges Two Centers One Site
Contra Costa College, San Pablo Diablo Valley College, Pleasant Hill Los Medanos College, Pittsburg Two Centers Brentwood Center San Ramon Center One Site Walnut Creek
3
Stats Students: 38,180 (Fall 07) FTES: 13,634 (Fall 07)
Employees: 2,080 (Fall 07) Improvements: 312 Acres, 99 Buildings, 2,455 Rooms, 1,550,00 square feet Utility Budget: Over $4,500,000/year
4
Energy Initiatives Comprehensive District-wide Energy Analysis and Energy Services Agreement Solar Photovoltaic Generation Systems 3.2MW Total Across 3 Campuses Lighting Retrofit in All District/College Buildings Motor Controllers High Voltage System Component Upgrades $35M Design-Build Partnership with Chevron Energy Systems and Parsons-Brinkerhoff Return on Investment: 13 years
5
Lighting Retrofit Replaced lamps and ballasts on over 22,100 fixtures
Project Cost: $1,960,000 Rebate: $243,000 Net Cost: $1,717,000 Estimated Annual Energy Savings: 1,994,000kWh Estimated Annual Cost Savings: $288,000 Simple ROI: 6 years
6
Solar Photovoltaic Generation Systems
3.2MW at 3 locations in 2 phases Project Cost: $32,200,000 Rebates: $8,400,000 Net Cost: $23,800,000 Estimated Annual Energy Savings: 3,964,000 kWh Calculated ROI: 16.5 years
7
Combined Project Power Reductions
Solar Panels On-line End of December
8
Combined Project Power Reductions
Solar Panels On-line End of December
9
Combined Project Power Reductions
Solar Panels On-line End of December
10
Questions?