Thabo Maisela Acting ED Housing
2
Synopsis Financial Performance: City wide
SUMMARY CONDITIONAL GRANT CAPITAL SPENDING Description No. of Projects Budget 2017/18 Year to Date Expenditure 2017/18 C/G Amount Adjustment Approved Adjusted Spending to Mar 2018 R'000 % Spent 30 June % Allocated R'000 Allocation R000 Budget R'000 to Revised Budget 2017 F/Cast Forecast 79 ( ) R 48.5% 100% Urban Settlement Development Grant
3
Synopsis Financial Performance: Housing
SUMMARY CONDITIONAL GRANT CAPITAL SPENDING Description No. of Projects Budget 2017/18 Year to Date Expenditure 2017/18 C/G Amount Adjustment Approved Adjusted Spending to May R'000 % Spent 30 June % Allocated R'000 Allocation R000 Budget R'000 to Revised Budget 2017 F/Cast Forecast 31 R 58 % 68 % Urban Settlement Development Grant
4
Issues raised at the Portfolio Committee
Concerns of the Portfolio Committee Lack of working relations between the City and Province and Coffee between CoJ and Province proposed Severe Storm Report to be submitted Capacity within the department to be strengthened No procurement plan Resolution On better working relations with Province Meeting held between MEC and EM to discuss challenges in the South of Johannesburg Meeting resolved on forming a joint task team Issues of Power of Attorney resolved Discussion with DDG Ongoing discussions with Province Agreements with SHRA and HDA Hail Storm Acting ED only informed on Friday of the need to submit this report. Housing Capacity Skills audit to be done Structure to be reviewed against delivery programs and mayoral priorities (pro poor; inner city; site and service and high densities in strategic areas) The review will be used to determine which positions will be prioritized for filling
5
Impediment on USDG performance ( Challenges in 2017/18 FY)
Late start on procurement for 2017/18 projects Poor Contract Management (including preparation of contracts and service level agreements) Implementation Community unrest 30% on SSME Poor General Management lack of project management Lack of Project Pipeline Lack of Project readiness Human factors
6
Intervention: Mitigation on USDG low expenditure (Non Performance)
Procurement Department will be following MFMA regulation 32 to procure consultants form JPC panel of consultants Copy of Copy of Housing Annexure B Detail Capex (3).xlsm Acquisition Plan to be reviewed and finalised Resolution of Minmec : National to provide capacity to the City of Joburg to assist in improving USDG expenditure Poor Contract Management Tighten controls on contract management Training and development Improving Implementation to unlock Expenditure AED has signed all reports to EAC South Hills Malibongwe Ridge Fleurhof Diepsloot Riverside Pipeline Regulation 32 projects Southren Farms Zandspruit
7
South of Joburg : Input of 01 June Meeting
Task Team consisting of: Province MEC Senior official City of Joburg Mayor of the City Joburg MMC housing Senior Officials Brief of the Task Team Will focus of on projects in the south of Joburg through site and service Land resonlution.pptx Key Decision Following discussion between Mayor and MEC City will provide Power of Attorney on city owned sections of land implementation protocol
8
Summary Of Estimated Project Yield For Johannesburg South
Area Project Yield Eldorado Park 2 703 Ennerdale/Finetown 23 466 Lenasia/Lawley/Kliprivieroog/Unaville 11 772 Orange Farm/Dark City of Poortie 30 192 Slovo Park (Nancefield) 47 588 Total
9
Thank you
10
EXPENDITURE ON HOUSES CONSTRUCTED – 2017/18
Project Budget Spending Variance Projected Expenditure to June 2018 % expenditure Riverside 82% Fleurhof 25% South Hills 87% Elias Motsoaledi 26% Kliptown 10% Golden Triangle 47% Lufhereng 100%