ELCITA Update March 2016.

Similar presentations


Presentation on theme: "ELCITA Update March 2016."— Presentation transcript:

1 ELCITA Update March 2016

2 Estate Management Skywalk E – Toilets
M/s mayaPRAXIS had a presentation on the preliminary feasibility study on Skywalk system for Electronics city phase 1. E – Toilets 12 e-toilets operational, 3 installed and 1 e-toilets installation work in progress. Estate survey Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries 95 % completed. Soft copy of base map drawing of Phase 1 has been submitted for ELCITA review.

3 Estate Management Permanent Works - Under Progress WIPRO Neeladri Road
Cdot Dmart Road

4 Bhavani Industries Road
Estate Management Permanent Works - Under Progress Quasitum Road Bhavani Industries Road

5 Tessolve Edizi Tools Road
Estate Management Road Works - Under Progress WIPRO Neeladri Road Tessolve Edizi Tools Road

6 Drain work adjacent to KSSIDC Compound wall
Estate Management Maintenance – Under Progress Drain work adjacent to RajKamal Industries Drain work adjacent to KSSIDC Compound wall

7 Drain from 300KLD STP to Outside
Estate Management Maintenance – Under Progress WMM Road from MSME Building to Exit Gate Drain from 300KLD STP to Outside

8 Canara Bank Jn to Fire Station Road Drain
Estate Management Maintenance – Under Progress Cyient Road Drain Canara Bank Jn to Fire Station Road Drain

9 Estate Management Maintenance – Under progress
Construction of Compound Wall at Wipro Gate No 5 Construction of Compound Wall at Wipro Gate No 12 A

10 Estate Management Maintenance - Under Progress
HP Road Widening Work - Completed Construction of Compound wall next to Shriram properties

11 Estate Management Sustainability Works – Completed
Supply & Erection of Shed for Organic waste processing plant at KIADB Land – Ecity Phase 2

12 Estate Management Permanent Works – Completed
Construction of 300KLD Conventional STP in ELCIA Park Completed Trail run in progress

13 Estate Management RWH works – Under Progress
33 Rainwater Harvesting Pit Completed & 5 more in progress at Various locations

14 Tender Under Evaluation
Estate Management Tender Under Evaluation Providing and laying of Asphalting using 60/70 grade bitumen along Velankani & HP Avenue Road Café Corner & JP IT Park Road Bhavani Industries & Quasitum Road Providing and laying Concrete Pavements along Doddanagamangala Village Road

15 Estate Management Contracts Awarded
Providing and laying of Asphalting using 60/70 grade bitumen from C-DOT to D-Mart Road Junction Fire Station to Canara bank Road

16 Estate Management Contracts on Anvil
Providing and laying of Asphalting using 60/70 grade bitumen from Hp Avenue - RHS Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP. Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2

17 Thank You