Presentation is loading. Please wait.

Presentation is loading. Please wait.

“Earned Schedule and Earned Value Management” The trend mentioned in PMBOK Guide 6 -th edition Presented by Mikayel Nshanyan, PMP®

Similar presentations


Presentation on theme: "“Earned Schedule and Earned Value Management” The trend mentioned in PMBOK Guide 6 -th edition Presented by Mikayel Nshanyan, PMP®"— Presentation transcript:

1 “Earned Schedule and Earned Value Management” The trend mentioned in PMBOK Guide 6 -th edition
Presented by Mikayel Nshanyan, PMP®

2 Structural Changes in PMBOK Guide 6 –th Edition
TRENDS AND EMERGING PRACTICE IN PROJECT COST MANAGEMENT “Within the practice of Project Cost Management, trends include the expansion of earned value management (EVM) to include the concept of earned schedule (ES)”. PMBOK Guide 6 –th Edition, 2017, Ch. 7, p. 233

3 $ Contract Budget Base Time Scope - WBS Management Reserve Schedule
Performance Measurement Baseline Budget $25K $12K $55K $37K $45K $14K Time

4 Earned Value Management is needed because...
In a single integrated system, Earned Value Management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management. It provides an “early warning” signal for prompt corrective action Still time to recover Timely request for additional resources.

5 Historical Background of EVM
Cost/Schedule Control Systems Criteria (C/SCSC), 1967; US Department of Defense (DoD) EVM System (EVMS), 1998; ANSI /EIA PMBOK Guide 2 –nd, 3 –rd, 4 –th, 5 –th, 6 – th Editions; PMI® Practice Standard for Eearned Value Management, 2005, 2011; PMI® Including EVM in PMP Certification Exam Program since 2000; PMI®

6 Use of EVM EVM is now used in projects and programs world-wide.
Primary users include the US, Europe, UK, Canada, Australia, China and Japan. EVM is a requirement of many US agencies, including the Department of Defence (DoD), NASA, the Department of Energy (DoE), the Intelligence Community, the Department of Homeland Security (DHS), the Federal Aviation Administration (FAA), the Department of Transportation (DoT), the Department of Health and Human Services (HHS) and others. EVM is applicable not only to waterfall but also to agile projects.

7 Benefits of EVM usage There are significant benefits to the contractor and to the customer. Contractor benefits include increased visibility and control to quickly and proactively respond to issues, which makes it easier to meet project schedule, cost and technical objectives. Custormer benefits include confidence in the contractor`s abiity to manage the project, identify problems early and provide objective, rather than subjective, contract cost and schedule status.

8 Basic Terms in EVM PV – Planned Value Planned cost of the total amount of work scheduled to be performed to date. AC – Actual Cost Cost actually incurred to accomplish the work that has been done to date. EV – Earned Value The planned (not actual) cost of work that has been done to date.

9 Some Derived Metrics Cost Variance (CV): CV = EV – AC
Schedule Variance (SV):  SV = EV – PV Cost Performance Index (CPI): CPI = EV / AC Schedule Performance Index (SPI):  SPI = EV / PV

10 Earned Value Metrics Method to measure project performance against scope, schedule and cost baseline (performance measurement baseline) Interpretation of basic EVM performance measures Performance Measures Schedule SV > 0; SPI > 1 SV = 0; SPI = 1 SV < 0; SPI < 1 Cost CV > 0; CPI > 1 Ahead of schedule, Under budget On schedule, Under the budget Behind schedule, CV = 0; CPI = 1 On budget CV < 0; CPI < 1 Over budget

11 EVM - Graphical Representation
Time Cost Schedule Variance (SV) Variance (CV) ACTUAL PLAN EARNED VALUE Estimate at Completion Budget at Completion Projection of Schedule: delay at completion Projection of cost: variance at completion (VAC) Status date BAC EAC AC EV PV Project is over budget and behind schedule

12 Project Performance Variances
Cost × Ahead schedule: SV > 0 × × EV AC Under budget (saving): CV > 0 PV Status date Time

13 Project Performance Variances
Behinde schedule (delay): SV < 0 Cost × × PV AC Under budget (saving): CV > 0 EV Time Status date

14 Project Performance Variances
Behinde schedule (delay): SV < 0 Cost PV × × × AC EV Over budget (overspending): CV < 0 Time Status date

15 Project Performance Variances
Cost Over budget (overspending): CV < 0 × × × AC EV Ahead schedule: SV > 0 PV Time Status date

16 Project Cost Forecusting in EVM
Variances are atypical: EAC = AC + ( BAC - EV ) Past estimating assumptions are not valid: EAC = AC + ETC Variances will be present in the future and time is the constrain: EAC = AC + ( BAC - EV ) / (CPI cum * SPI cum ) Project will be continued on the same rate of spending: EAC = BAC/ CPI cum

17 Example Month PV, $K PV Cum ,$K EV, $K EV Cum ,$K SV cum ,$K SPI cum.
1 100 90 - 10 0.90 2 200 85 175 - 25 0.86 3 300 80 255 - 45 0.85 4 400 75 330 - 70 0.83 5 500 405 - 95 0.81 6 600 70 475 - 125 0.79 7 - 545 - 55 0.91 8 55 1.00

18 SPI at the End of the Project
Project’s status: actually project finished 2 months late EVM calculation: final SPI = 1.00; final SV = $ 0 1.2 1.1 1.0 1 2 3 4 5 6 Time 7 8 0.9 0.8 0.7 2 months Planned finish Actual finish

19 Limitations of Basic EVM
Exact measurements of Earned Value (Physical work completed) may not be accurate There may be problems with critical activities hiden in Cumulative Earned Value (EV cum) EVM is not applicable for controlling and forecasting of project schedule at the last stage (after 70% of work completion), especially for late projects: SV = 0, SPI = 1 even for delayed projects, which is not correct.

20 Earned Schedule History
Developed by Wolt Lipke in Included as an appendix in PMI Practice Standard for EVM, 2 -nd Edition, 2011 Referred as an extension to EVM in PMI PMBOK Guide 6 –th Edition, 2017

21 Schedule Metrics in Cost Units
Cost, $K PV = $300K EV = $200K SV ($) = EV – PV = - $100K SPI ($) = EV / PV = 0.67 600 500 400 PV 300 SV ($) 200 100 EV Jan Feb Mar Time Status day

22 Schedule Metrics in Time Units
Cost, $K Planned Duration (D) 600 500 400 PV 300 200 100 EV Jan Feb Mar Apr May Jun Time Status day Earned Schedule (ES) Actual Time (AT)

23 Schedule Metrics in Time Units
Earned Schedule (ES) is the time when the current earned value was planned to be accomplished, in other words, ES is the time at which PV supposed to be equal to the current EV. Actual Time (AT) is the time passed from the project start. Planned Duration (PD) is the planned duration of the project SV(t) = ES – AT = 2m – 3m = - 1m SPI(t) = ES / AT = 2m / 3m = 0.67

24 Schedule Metrics in Time Units
Cost, $K Planned Duration (PD) = 6 months 600 500 PV 400 EV 300 200 100 Jan Feb Mar Apr May Jun Jul Aug Time Earned Schedule (ES) = 6 months Actual Time (AT) = 8 months

25 Schedule Performance Checking the End of Project
EV = $600K PV = BAC = $600K SV($) = EV – PV = 0 SPI($) = EV / PV = 1 ES = 6 months PS = ES = 6 months SV(t) = ES – AT = 6 – 8 = - 2 months SPI(t) = ES / AT = 6 / 8 = 0.75 At the end of the project, SV(t) and SPI(t) remain good indicators of project status, while SV($) and SPI($) end up at 0 and 1, respectively, regardles 2 months delay of project completion.

26 Schedule Fraction Calculation
Cost, $K 600 500 PV 400 300 EV EV 200 100 Jan Feb Mar Apr May Jun Time Status day Earned Schedule (ES) Actual Time (AT)

27 Schedule Fraction Calculation
Cost PVMar EV q × × EV PVFeb p p 1 PV x / 1 = p / q x = p / q p = EV - PVFeb q = PVMar - PVFeb x = (EV - PVFeb) / (PVMar - PVFeb) EV X = ? Jan Feb Mar Apr Time Earned Schedule (ES)

28 Schedule Fraction Calculation
Cost PV k = 1 EV q × × EV PV k p p 1 PV x = p / q p = EV – PV k q = PV k + 1 – PV k x = (EV – PV k) / (PV k +1 – PV k) EV X = ? Jan Feb Mar Apr Time ES = K + (EV - PVk) / (PVk+1 - PVk) Earned Schedule (ES)

29 Schedule Fraction Calculation
Cost EV st. day = $250K PVMar = $300K PVFeb = $200K PV k = 1 300 EV q EV × × PV k p p 200 1 PV ES = K + (EV - PVF) / (PVM - PVF) = = 2 m + (250 – 200) / (300 – 200) m = = months EV X = ? Jan Feb Mar Apr Time Earned Schedule (ES)

30 Project Duration Forecasting
Estimated Duration At Completion (EDAC) is defined as EDAT = AT + (PD – ESCum) / PF where PF is a Performance Factor

31 Comparison of EV and ES equations
Status Earned Value (EV) Earned Schedule (ES) Schedule Variance SV$ = EV – PV SVt = ES – AT Schedule Performance Indicator SPI$ = EV / PV SPIt = ES /AT Ramaining Work BAC - EV PD – ES Estimate At Complete EAC$ = BAC / CPI EAC$ = AC + (BAC – EV) / CPI EACt = PD / SPIt EACt = AT + (PD – ES) / SPIt To Complete Performance Index TCPI = (BAC – EV) / (BAC – AC) TCPI = (BAC – EV) / (EAC – AC) TSPI = (PD – ES) / PD – AT) TSPI = (PD – ES) / ED – AT)

32 SPI at the End of the Project
SPI(t) Project status: Project finished 2 months late Final SPI(t) = 0.75 Final SV(t) = - 2 months 1.2 2 months 1.1 1.0 Time 0.9 0.8 0.7 Planned finish Actual finish

33 Late Finished Project’s CV and SV

34 Late Finished Project’s CPI and SPI

35 Earned Duration Management A Novel Trends in Schedule Controlling
Earned Duration Management is a new approach to project schedule and duration performance management and measurements. (Khamooshi & Golafshani, 2014) EVM and Earned Schedule use cost as base to measure schedule performance to control duration of the project. While there is a correlation between schedule, cost, quality and scope of a project, using cost to control duration has proven to be misleading. In contrast to Earned Value and Earned Schedule the Earned Duration Management (EDM) has decoupled schedule and cost performance measures.

36 Earned Duration Management
Its foundation lies in the exclusive usage of time-based data for the generation of physical progress indicators. Thus, schedule performance indicators become free from any dependency on planned cost values, and therefore, are no longer influenced by them.

37 Similarity between ED and ES calculation
$ TRD Curve PV Curve TED Curve Total Duration × × EV Curve EV TED Time ES ED

38 Summary of EDM and EVM/ES metrics
Acronym Description Equation EVM ED Earned Duration ES Earned Schedule AD Actual Duration AT Actual Time TED Total Earned Duration EV Earned Values TPD Total Planned Duration PV Planned Value TAD Total Actual Duration AC Actual Cost ES(t) / AD DPI Duration Performance Index SPIt Schedule Performance Index (ES) EDI Earned Duration Index TED / TPD SPI Schedule Performance Index EV / PV TDV Total Duration Variance TED - TPD SV Schedule Variance EV - PV

39 Summary of EDM and EVM/ES metrics
Acronym Description Equation EVM ED Earned Duration ES Earned Schedule AD Actual Duration AT Actual Time TED Total Earned Duration EV Earned Values TPD Total Planned Duration PV Planned Value TAD Total Actual Duration AC Actual Cost DPI Duration Performance Index ED(t) / AD SPIt Schedule Performance Index (ES) ES(t) / AD EDI Earned Duration Index TED / TPD SPI Schedule Performance Index EV / PV TDV Total Duration Variance TED - TPD SV Schedule Variance EV - PV


Download ppt "“Earned Schedule and Earned Value Management” The trend mentioned in PMBOK Guide 6 -th edition Presented by Mikayel Nshanyan, PMP®"

Similar presentations


Ads by Google