Melanie Garrick Barry Mullins Nihar Patel Jason Young
Group 5 – ECE 4006: Week 16 Melanie Garrick Barry Mullins Nihar Patel Jason Young 11/18/2018
2
Semester Summary Started off clueless
Got hope after testing the practice board Worked on OLB Designed the transceiver and did the layout Tested and debugged It works!!! 11/18/2018
3
From laser driver specs
Optical Link Budget From graph From Standard From Standard From schematics From laser driver specs 11/18/2018
4
Optical Link Budget 11/18/2018
5
Schematics 11/18/2018
6
Design Layout 11/18/2018
7
Test Results – Baseline Rx
PRBS7 11/18/2018
8
Test Results – Baseline Tx
PRBS7 11/18/2018
9
Test Results – Loopback
PRBS7 11/18/2018
10
Test Results – Attenuated Tx
PRBS7 – 5dB PRBS7 – 10dB 11/18/2018
11
Test Results – Attenuated Rx
PRBS7 – 5dB PRBS7 – 10dB 11/18/2018
12
Test Results – Att. Loopback
PRBS7 – 5dB Unshielded PRBS7 – 5dB Shielded 11/18/2018
13
Test Results – Att. Loopback
D21.5 – 10dB Shielded 11/18/2018
14
Test Results – Alignment Rx
PRBS7 11/18/2018
15
Test Results – Algn. Loopback
PRBS7 11/18/2018
16
Test Results – Algn. Tolerance
PRBS7 In x-direction ~ 0.5 μm tolerance Thanks to Group 2 for letting us borrow your PD! In y-direction ~ 0.75 μm tolerance In z-direction ~ 2 μm tolerance 11/18/2018
17
Monetary Budget 11/18/2018
18
Bill of Materials 11/18/2018
19
Final Gantt Chart 11/18/2018
20
Results Summary Baseline Rx, Tx, and Loopback successful
Attenuation testing successful after discovery of fiber voodoo PRBS7 Loopback works for 5 dB, while D21.5 works until 10 dB attenuation Alignment testing cut short due to limited lab time 11/18/2018
21
Anticipated Progress for Week 17
HUH !! What progress ?? We done 11/18/2018