Minuteman Vocational Technical Regional High School Progress

Similar presentations


Presentation on theme: "Minuteman Vocational Technical Regional High School Progress"— Presentation transcript:

1 Minuteman Vocational Technical Regional High School Progress
February 12th, 2018 – March 19th, 2018

2 March 15th View of Area A & B - Interior
Excavation & backfill of underground plumbing elements in progress.

3 March 15th View of Area G – Facing North-West
Steel Erection and Decking & Detailing Complete.

4 March 15th View of Area G – Second Floor
Construction of edge form and installation of reinforcing in preparation for concrete slab on deck placement.

5 March 15th View of Area E – Facing West
Concrete Foundations Complete. Building foundations completed on March 6th. Area C Steel Erection in progress in the background.

6 February 26th View of Area E South – Facing North
Decking & Detailing activities in progress. March 15th View of Area E South – Facing South Decking & Detailing activities in progress.

7 March 15th View of Area F – Facing West
Steel Erection Complete. Decking & Detailing Substantially Complete.

8 February 26th View of Area C – Facing East
Steel Erection in Lower Level of Theater in progress. Forming of electrical duct back in progress.

9 March 6th View of Area C – Facing East
Steel Erection in progress with the setting of steel columns. March 15th View of Area C South – Facing East Steel Erection in progress with upper framing being set.

10 March 16th View of Area C – Facing South
Steel Erection of theater low roof in progress. Two crane pick required due to size and weight of roof beams.

11 Excavation & Foundation Progress 3/19/18.
Building Foundations were completed on 3/6/18

12 Steel Erection Progress
3/19/18

13 March Construction Schedule Look Ahead:
Area A+B Continue excavation & backfill for underslab utilities. Commence roof parapet framing and wood blocking. Installation of Roof Drain bodies. Place concrete slab on deck on Level 2. Area G Installation of Roof Drain bodies Commence roof and exterior framing. Area E – Lower Continue decking & detailing of steel. Area C Continue/Complete steel erection Commence decking & detailing of steel