ACTIVITY 1: TRAVELING SALESMAN PROBLEM Sandys grandmother lives in an old one- story house. There are many connecting doors between the rooms. One day, Sandy wanted to find a route that would take her though each door exactly once. Help Sandy find a route.
2
TSP SOLUTION If a room has an odd number of doors, you must either begin in that room or end in that room
3
This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012
4
EXPAND THE CIRCUIT Steve just added a visit to Columbus, Ohio. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012
5
THE NEAREST-NEIGHBOR ALGORITHM I.Choose a node as your starting point II.From the starting node, travel to the node for which the fare is the cheapest. We call this node the nearest neighbor. If there is a tie, choose one arbitrarily. III.Repeat the process, one node at a time, traveling to nodes that have not yet been visited. Continue this process until all nodes have been visited. IV.Complete the Hamiltonian circuit by returning to the starting point. V.Calculate the cost of the circuit. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012
6
THE NEAREST-NEIGHBOR ALGORITHM This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012 What is the cost of the route? What is the new route? $531.00; WPCoCSAW
7
THE NEAREST-NEIGHBOR ALGORITHM Why does using the nearest-neighbor algorithm make more sense than using the brute-force method in this case? Will the nearest-neighbor algorithm always give a good route? Why or why not? This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012
8
REPETITIVE NEAREST-NEIGHBOR ALGORITHM I.Select any node as a starting point. Apply the nearest-neighbor algorithm from that node. II.Calculate the cost of that circuit. III.Repeat the process using each of the other nodes as the starting point. IV.Choose the best Hamiltonian circuit. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012
9
REPETITIVE NEAREST-NEIGHBOR : SOLUTION 1.Start at P: PWACSCoP = 74+76+104+65+110+79= $508 2.WACSCoPW; its cost is the same, $508. A circuit goes into and out of each city. Therefore, the starting point within a given circuit has not effect on the total cost. 3.Start at C: CSWPCoAC = 65+105+74+79+121+104 =$548 4.Start at A: AWPCoCSA = 76+74+79+88+65+149 = $531 5.Start at S: SCCoPWAS = 65+88+79+74+76+149 = $531 6.Start at Co: CoPWACSCo = 79+74+76+104+65+110 = $508. This is identical to the circuit found by starting the nearest –neighbor algorithm at Pittsburgh. The cheapest circuit found by starting the algorithm at either Pittsburgh or Columbus translates to WACSCoPW and costs $508. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012
10
ACTIVITY #2 Instructions: Using the poster board and the pins, place the different characteristics under the correct method This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012
11
SOLUTION This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 6 : 6/25/2012
12
LINEAR PROGRAMMING This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
13
ALGEBRA Variable x or y It can also be x1 and x2 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
14
LINEAR EQUATION x+2y=16 x=0 y=8 x=2 y=7 x=6 y=5 x=14 y=1 x=16 y=0 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
15
SERIES OF LINEAR EQUATIONS x+2y=16 x+ y=12 x+2y-2y=16-2y x=16-2y (16-2y)+y=12 16-2y+y=12 16-y=12 16-y+y=12+y This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
16
SERIES OF LINEAR EQUATIONS x+2y=16 x+ y=12 16=12+y 16-12=16+y-12 4=y x+2(4)=16 x+8=16 x+8-8=16-8 x=8 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
17
SERIES OF LINEAR EQUATIONS x+2y=16 x + y=12 x=8 y=4 (8)+2(4)=16 8+8=16 16=16 (8)+ (4)=12 12=12 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
18
INEQUALITY x + y<12 x=0y=0 x=0y=1 x=1y=0 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
19
GRAPH LINEAR EQUATION y-2x=1 x=0y=1 x=1y=3 x=2y=5 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
20
GRAPH INEQUALITY y<x y=1x=0,-1,-2,-3….. y=0x=-1,-2,-3,-4….. y=5x=4,3,2,1….. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
21
LINEAR PROGRAMMING For many manufactures the ability to maximize profits is limited, or constrained by their machine, production line, and assembly line capacity, as well as by the size of their workforce. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
22
LINEAR PROGRAMMING Linear programming assists managers in making complex product-mix decisions in the presence of constraints. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
23
LINEAR PROGRAMMING The founder of linear programming was American operations researcher George Dantzing. The first problem solved was a minimum-cost diet problem that involved the solution of 9 equations with 77 decision variables. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
24
LINEAR PROGRAMMING Dantzing, working with The National Bureau of Standards, supervised the solution of the diet problem, which took 120 person-days using hand-operated desk calculators. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
25
MCDONALD'S FRANCHISES This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
26
MCDONALD'S FRANCHISES This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
27
MCDONALD'S FRANCHISES This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
28
MCDONALD'S FRANCHISES This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
29
HIGH STEP SPORTS SHOE The High Step Shoe Corporation wants to maximize its profits. Airheads=$10 Groundeds=$8.50 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
30
HIGH STEP SPORTS SHOE In developing a production plan, managers will often be constrained by limited resources such as number of workers, availability of raw materials, maximum demand for a product, and so forth Quantities that can change (vary) and that managers are able to control are called decision variables. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
31
DECISION VARIABLE What are the decision variables that the managers at High Step Sports Shoe must consider? The main decision variable to consider are the number of Airheads (A) and Groundeds (G) to produce each week This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
32
OBJECTIVE FUNCTION The goal is to make the most money, or to maximize profits. P=10A + 8.5G This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
33
CONSTRAINTS The steps in manufacturing the shoes include cutting the materials on a machine and having workers assemble the pieces into a pair of shoes. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
34
CONSTRAINTS There are 6 machines that are used to cut materials. Each pair of Airheads requires 3 minutes of cutting time, while each pair of Groundeds requires 2 minutes. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
35
CONSTRAINTS There are 850 workers who assemble the shoes. It takes a single worker 7 hours to assemble a pair of Airheads and 8 hours to assemble a pair of Groundeds. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
36
CONSTRAINTS The assembly plan operates 40-hours per 5-day work week. Also, each cutting machine is operated only 50 minutes per hour to allow for routine maintenance. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
37
HIGH STEP SPORTS SHOE How many minutes of work can 6 machines do in 40-hour work week? Now use the decision variables to write an inequality to represent a constraint that is based on the limited time the cutting machines operate each week. 6 X 50 X 40 = 12000 minutes 3A + 2G < 12000 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
38
HIGH STEP SPORTS SHOE How many hours of work can 850 assembly workers do in a week? Write an inequality to model a constraint based upon the limited number of worker hours available for shoe assembly each week. 850 X 40 = 34000 hours 7A + 8G < 34000 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
39
HIGH STEP SPORTS SHOE Could the number of pairs of shoes of each style that are produced each week ever be negative? Could it be zero? Why or why not? Then, are there more constraints? Which? This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
40
HIGH STEP SPORTS SHOE Graphing the system of inequalities shows the feasible region of the graph. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
41
HIGH STEP SPORTS SHOE What does each pair of coordinates represent? Which of the six intersection points satisfy all the constraints? What does the shaded region of the graph represent? This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
42
HIGH STEP SPORTS SHOE Of all the feasible points, one will give the maximum profit. The process of determining this best solution is called optimization, and the solution itself is called optimal solution. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
43
HIGH STEP SPORTS SHOE How many feasible points are there? Pick three points in the interior of the feasible region. List the corresponding values of A and G in a table like this one, and evaluate the profit P for each point selected. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
44
HIGH STEP SPORTS SHOE Compare your answers with those of other students, and see which point has the most profit. Now test each feasible corner point. Enter these values of A, G, and P in another table This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
45
HIGH STEP SPORTS SHOE Which point from either table yields the largest profit? What do the coordinates of this point represent? This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
46
HIGH STEP SPORTS SHOE This problem is an example of the corner principle. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
47
Model production in a furniture facture Suppose a company produces only tables and chairs A table is made of 2 large and 2 small pieces A chair is made of 1 large and 2 small pieces Profit: Table - $16 ; Chair - $10 Determine product mix that maximizes the companys profits using the available resources ACTIVITY #3: LEGO FURNITURE This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
48
ACTIVITY #3: SOLUTION This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
49
THE MEAT INDUSTRY IN NEW ZEALAND This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
50
THE MEAT INDUSTRY IN NEW ZEALAND This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
51
THE MEAT INDUSTRY IN NEW ZEALAND This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
52
TRIM LOSS AT THE CUTTING TIMES Products such as paper, sheet metal, and photographic film are manufactured in very wide rolls that need to be cut into sets of smaller strips to meet specific product needs. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
53
TRIM LOSS AT THE CUTTING TIMES The Cutting Times is a small local newspaper with its own printing press. The paper receives large 48-inch-wide rolls of newsprint, which must to be cut into 25-inch-wide rolls for the ordinary pages in the paper and 21-inch-wide rolls for smaller inserts This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
54
TRIM LOSS AT THE CUTTING TIMES Lets draw some models of each possible cutting pattern. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
55
TRIM LOSS AT THE CUTTING TIMES For the Sunday edition of the Times right before Thanksgiving, the Times needs twenty 25-inch rolls for the ordinary part of the edition and fifty 21-inch rolls for the extra advertising inserts. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
56
TRIM LOSS AT THE CUTTING TIMES When the times decides how many of each pattern to cut, what should be considered? How can the newspaper control the amount of waste? Why would the newspaper want to control the amount of waste? This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
57
DECISION VARIABLES Let x= the number of large rolls cut into two 21-inch rolls Let y= the number of large rolls cut into one 25-inch and one 21-inch roll This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
58
DECISION VARIABLES Now write a function representing the amount of waste, w, in terms of the decision variables x and y. Min w= 6x + 2y This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
59
CONSTRAINTS When a large roll is cut into two 21-inch rolls, how many 25-inch rolls and how many 21-inch rolls are produced? When a large roll is cut into one 25-inch roll and one 21-inch roll, how many 25- inch roll and how many 21-inch roll are produced? This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
60
CONSTRAINTS If 5 rolls are cut using the first pattern and 10 rolls are cut using the second pattern, how many 21-inch rolls and how many 25-inch rolls are produced? Ten 25-inch rolls and twenty 21-inch rolls This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
61
CONSTRAINTS If x rolls are cut using the first pattern and y rolls are cut using the second pattern. How many 25-inch rolls and how many 21-inch rolls will be produced? y= the number of 25-inch rolls 2x + y= the number of 21-inch rolls This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
62
CONSTRAINTS Now lets use the cut paper requirements to write two inequalities based on the number of 25-inch and 21-inch rolls that must be produced, in terms of x and y. 25-inch rolls requirement: y> 20 21-inch rolls requirement: 2x + y > 50 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
63
THE FEASIBLE REGION One of the decision variables is restricting the other decision variable, which one and why? y, and because the 25-inch rolls are produced using only one of the two patterns This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
64
THE OPTIMAL SOLUTION Choose two points in the feasible region and use the objective function to calculate the amount of waste (w 1 and w 2 ) produced for the points you selected. This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
65
THE OPTIMAL SOLUTION At what point do we have the minimum amount of waste? What does this point mean in terms of the original problem? This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
66
ACTIVITY #4: CUTTING STOCK Solve the given problem in teams of 4 One member of each team will be chosen to solve the problem on the board This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
67
ACTIVITY #4: SOLUTION A health care corporation wants to cut large 55-inch wide beams of gauze into 5- inch and 4-inch widths. List all of the possible cutting patterns. 5 Strips4 StripsWaste 1100 1011 922 833 750 661 572 483 3 0 2111 1122 0133 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
68
ACTIVITY #4: SOLUTION A health care corporation wants to cut large 55-inch wide beams of gauze into 5- inch and 4-inch widths. What variable names could be assigned to represent the number of beams of gauze cut using each of the patterns? Use the first 12 letters of the alphabet. A better solution would be the use of subscripts. i.e. x1,x2,x3…x10,x11,x12. The company also wants to cut some of the 5-inch rolls of gauze into 3/4-inch rolls to be used in the manufacture of adhesive strips and 3-inch rolls to be used in the manufacture of square gauze pads. The company needs 120 thousand 3/4-inch rolls and ten thousand 3-inch rolls. How should the 5-inch rolls be cut to minimize waste? Both patterns minimize the waste, however, only the first pattern can give both cuts. ¾(.75)3Waste 111.25 210.50 302.75 402.00 501.25 600.50 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012
69
ACTIVITY #4: SOLUTION Decision variables: Let x = the number of 5 strips cut into 6 ¾ rolls Let y = the number of 5 strips cut into 2 ¾ and 1 3 roll Objective Function: Minimize w = 6x + 2y Constraints: subject to 2x + y 120,000 y 10,000 This opportunity if funded by the United States Department of Education. Award # 2010-38422-19963 - DAY 7 : 6/26/2012