1
X-ray Pump-Probe Instrument
David Fritz XPP Instrument Scientist June 9, 2009
2
XPP Update from previous FAC Component Status
Outline Overview XPP Update from previous FAC Component Status Design Procurement and Fabrication Early commissioning?
3
XPP Instrument Overview
Page 3
4
Update from Fall FAC Received advanced procurement approval December 18, 2009 for: Sample Goniometer Detector Mover Final Instrument Design Review successfully held Feb 24, 2009 Procurement authorization for everything except OPA, multipass amplifier Baseline change request processed to include large offset monochromator system for XPP Procurement documents were reviewed at the XCS advanced procurement review April 24, 2009 and the documents are being updated
5
Laser Tables and Enclosure
5’ x 12’ 5’ x 6’ Completed design of laser containment system and optical table layouts Design review November 14, 2008 Laser tables are fabricated and are in storage in the control room. Anchor holes are drilled and tables are ready to be installed once granite is installed Enclosure PO placed April 20, 2009
6
X-ray Optics Tables Completed final design of X-ray optics tables
Final design review January 26, 2009 Granite PO placed April 14, 2009 Expected to be delivered in July w/ rails installed Anchor holes for the earthquake restraints already drilled
7
Sample Goniometer Received advanced procurement authorization Dec. 18, 2008 Goniometer PO awarded to Huber April 1, 2009 Expected to be delivered in April 1, 2010 Vendor site visit scheduled for July 17, 2009
8
Detector Mover Received advanced procurement authorization Dec. 18, 2008 Robot basing design study completed in January, 2009 Robot PO awarded March 31, 2009 Expected to be delivered this week Robot support design review held May 22, 2009 Detailed fabrication drawings in process Robot software PO in process
9
Hutch Facilities Work benches and storage cabinets received and installed Tools and tool boxes PO placed March 24, 2009 Expected to be delivered and installed in August Raised floor PO in process (req submitted March 10) Cable trays are here
10
RFP issues for 20 Ghz Oscilloscope
Laser Equipment RFP issues for 20 Ghz Oscilloscope Various optics and optomechanics PO’s in process Much more to be procured over the next 6 months Hopefully procurement authorization will be given for OPA and multipass amplifier shortly so req’s can be placed
11
Updated Schedule XPP Advanced Procurement Review – November 2008 FY08
Preliminary Design Reviews X-ray Optics Support Tables – August 2008 Detector Mover Support – May 2009 XPP Advanced Procurement Review – November 2008 Final Instrument Design Review – February 2009 Final Design Reviews Optical Table Layout\Containment – November 2008 X-ray Optics Support Tables – January 2009 CD-3 - July 2009 Award PO Sample Goniometer – April 2009 Hutch Facilities – June 2009 Detector Mover – March 2009 X-ray Optics Support Tables – April 2009 Laser Containment System – April 2009 Optical Tables – April 2009 Detector Mover Support – July 2009 Receive Optical Tables – May 2009 Hutch Facilities – August 2009 X-ray Optics Support Tables – July 2009 Laser Containment System – July 2009 Detector Mover – June 2009 Sample Goniometer – April 2010 Detector Mover Support – September 2009 Ready for User Run – July 2010
12
X-ray support tables are expected to be installed in July
Early Commissioning? X-ray support tables are expected to be installed in July Vacuum transport can/will be installed in the summer as well Prototype X-ray diagnostics will be ready in the fall Would be extremely beneficial to receive some early “machine time” to test prototype diagnostics, optics, materials, etc… 4-8 hours per week??? This would significantly reduce the risk and commissioning time allocated to the dedicated XPP instrument commissioning Page 12