Presentation is loading. Please wait.

Presentation is loading. Please wait.

© 2013 American College of Cardiology

Similar presentations


Presentation on theme: "© 2013 American College of Cardiology"— Presentation transcript:

1 © 2013 American College of Cardiology
Quality Improvement in Action: Using the FOCUS-PDSA Method to Conduct a QI Project November 22, 2003 © 2013 American College of Cardiology

2 © 2013 American College of Cardiology
Learning Objectives After viewing this presentation, you will be able to: State each step of the FOCUS-PDSA method Draft a QI project plan Build a QI project team Conduct a QI project step-by-step © 2013 American College of Cardiology

3 Getting started can feel like…
Who’s in charge? Are we there yet? Haven’t we done this before? By going step-by-step, you can make sense of your QI project © 2013 American College of Cardiology

4 © 2013 American College of Cardiology
FOCUS-PDSA Method Find a problem Organize a team Clarify the problem Understand the problem Select an intervention © 2013 American College of Cardiology

5 Commonly Used QI Tools*
Stakeholder analysis Brainstorming Dot voting Prioritization matrix Flow chart Root cause analysis * Refer to the “QI Tool Box” for details © 2013 American College of Cardiology

6 Step 1. Find a Process to Improve
Assemble QI project team Identify potential problems Identify primary stakeholders Select specific problems to improve Draft a problem statement Develop a project charter © 2013 American College of Cardiology

7 © 2013 American College of Cardiology
Step 2. Organize a Team Form project team Select a team leader and facilitator Conduct kick-off meeting Helpful hint: Make sure your team includes a representative of everyone affected by your QI problem © 2013 American College of Cardiology

8 Step 3. Clarify Current Knowledge of the Process
Develop understanding of situation Establish measurement process Collect data Helpful hint: Use a flow chart to document what is actually going on © 2013 American College of Cardiology

9 Step 4. Understand Process Variation
Graphically present data Identify patterns of variation Identify sources of variation Helpful hint: Use a fishbone diagram or another root cause analysis tool to figure out the cause(s) of the problem © 2013 American College of Cardiology

10 Step 5. Select the Intervention
Identify potential interventions Prioritize potential interventions Helpful hint: Your team should brainstorm all the possible solutions to your QI problem and vote to pick one © 2013 American College of Cardiology

11 FOCUS-PDSA Method Plan Act Study Do
Implement the intervention and determine its success © 2013 American College of Cardiology 11

12 Step 6. Plan How to Implement
Develop clear objectives Develop implementation plan Make a prediction about the impact Determine data and assess impact Plan the test cycle Seek buy-in from key stakeholders © 2013 American College of Cardiology

13 Step 7. Do – Implement the Plan
Test your intervention Document what happens Begin analysis of test data Helpful hint: Test your intervention on a small scale with a few providers or patients...make it simple! © 2013 American College of Cardiology

14 © 2013 American College of Cardiology
Step 8. Study the Results Analyze data Compare the results to your predictions Reflect on what happened Determine if modifications are needed Helpful hint: Look for the unintended consequences to your intervention © 2013 American College of Cardiology

15 Step 9. Act – Continue or Change
Apply the lessons learned Change the project or implement again as-is Prepare a plan for the next test Helpful hint: A lesson learned may be that you need to change your implementation plan or just start over © 2013 American College of Cardiology


Download ppt "© 2013 American College of Cardiology"

Similar presentations


Ads by Google