The open pit production scheduling problem with metal uncertainty

Similar presentations


Presentation on theme: "The open pit production scheduling problem with metal uncertainty"— Presentation transcript:

1 The open pit production scheduling problem with metal uncertainty
Amina Lamghari, COSMO McGill Univ., Canada Jacques A. Ferland, Dept. Inf. Rech. Oper., Univ. de Montréal, Canada Roussos Dimitrakopoulos, COSMO McGill Univ., Canada

2

3 the economic value of extracting block i objective function

4

5 the economic value of extracting block i objective function

6 the economic value of extracting block i

7 the economic value of extracting block i

8

9

10

11

12

13

14

15 How to solve it? Hybrid solution approach (General idea):
Exact methods Good for solving limited-size problems Metaheuristic methods Can deal with large-scale problems Hybrid solution approach (General idea): Decompose the problem into sub-problems, each associated with a period The sub-problems are of reduced size, so an exact method can be used Combine the solutions of the sub-problems to get a solution of the original problem Improve this solution using a metaheuristic method