Presentation is loading. Please wait.

Presentation is loading. Please wait.

CHPE308 Engineering Economy Estimation of Manufacturing Costs

Similar presentations


Presentation on theme: "CHPE308 Engineering Economy Estimation of Manufacturing Costs"— Presentation transcript:

1 CHPE308 Engineering Economy Estimation of Manufacturing Costs

2 Estimation of Manufacturing Costs

3 Direct Costs

4 Fixed Costs

5 General Expenses Administration Costs Distribution and Selling Costs
Research and Development

6

7

8 Manufacturing Costs

9 How Do We Get…..

10

11

12 Manufacturing Costs with depreciation as 10% FCI (8.1) (8.2) COM without Depreciation

13

14

15 Cost of Operating Labor
NOL = the number of operators per shift P = particulate processing steps Nnp = non-particulate processing steps – compression, heating/cooling, mixing, separation, and reaction Important note – Above equation based on data from chemical plants and refineries where number of particle processing steps is low. For units with more than 2 solids processing steps ignore middle term and add 1 operator per solids step

16 Example 8.2: Estimate the operating labor requirement and costs for the
Toluene hydrodealkylation facility shown in fig 1.3 and 1.5

17 Example 8.2 solution Pumps & Vessels are Not counted in evaluating Nnp

18 Example 8.2 solution

19 Example 8.2 solution 2 $ 741,000/yr

20 Cost of Raw Materials, Utilities, and Waste Treatment

21

22 Stream Factor not kmol/hour

23 Utilities – Fuel and Electricity

24 Cost of Fuel – Utility costs
This graph clearly shows the recent trend in petroleum based fuels. This data is prior to the $140 per barrel surge that occurred in 2008 so the costs for natural gas and fuel oil are even higher. Not the relatively stable cost of coal.

25

26 Utilities - Steam

27

28

29

30

31

32 Refer to textbook, pages 248-249, for solution
(Utility: HPS) (Utility: Cooling Water) (Utility: Natural gas, heating value = GJ/m3, heater thermal efficiency=90%) (Utility: Electricity) (use table 8.5 to find theoretical steam requirements) (Utility: Electricity) Refer to textbook, pages , for solution

33

34

35

36 On the Utilities Summary of CAPCOST, each piece of equipment that may use a utility is flagged. For drives (compressor) and pumps, the electrical load is calculated. For fired heaters and exchangers the utilities must be specified. For example the exchanger above is using mps at a rate of 10,000 MJ/h. This data is input and the yearly utility cost is calculated. Note – for utilitiy generators such as a waste heat boiler use a negative duty (negative cost = revenue)

37 Likewise, other equipment are added and the annual utility costs is calculated. Note that in the users section of the CAPCOST program, the user may specify the efficiencies of the different equipment and the cost of different utilities as shown on the following slide

38 Unit costs for utilities
All these values may be changed by the user to customize a process User specified equipment efficiencies Cost of labor


Download ppt "CHPE308 Engineering Economy Estimation of Manufacturing Costs"

Similar presentations


Ads by Google