Quarterly Transportation Report 4th Quarter 2011 October 11, 2011
Thomas Blaser – Director Department of Transportation
2
Transportation Headlines
Road Opening Prince William Parkway (Hoadly Road - Old Bridge Road) Project complete and open to traffic Project completed on schedule August 31, 2011
3
University Boulevard PPTA (Prince William Parkway to Sudley Manor Drive)
Accomplishments Hornbaker Road design has been completed and approved by VDOT University Boulevard design has been submitted for approval Issues R-O-W negotiations with adjacent developments Timeline Some construction to begin late this Fall with majority starting in Spring 2012 Construction to be substantially complete by end of November 2013
4
University Boulevard PPTA (Prince William Parkway to Sudley Manor Drive)
5
Route 1 – Joplin to Bradys Hill
Accomplishments Utility relocation is complete Installation of storm drain is 97% complete, sanitary sewer and waterline are 100% complete Box culvert crossing Route 1 is approx. 35% complete Earthwork activities on south-bound lane of Route 1 for Phase I have been completed Phase II construction grading work is complete Traffic is switched for Phase II on northbound lane to install new sections of box culvert Issues Temporary lane closures during non rush hours Timeline Construction scheduled completion June of 2012
6
Route 28 (Linton Hall Road to Fitzwater Drive)
Accomplishments Design has initiated with survey work underway First design coordination meeting for realigned Vint Hill Rd. held in March 2011 Public Hearing Plan submitted to VDOT for review Issues Project construction phasing to expedite completion Project Funding Impacts to septic fields Timeline Citizen information meeting tonight at 7:00 pm at Nokesville Elementary Public Hearing planned for January 2012 Anticipated Final Plans for VDOT review – February 2012 Construction Advertisement for Phase I (Linton Hall Road to Realigned Vint Hill Road) anticipated for August 2012
7
Route 28 (Linton Hall Road to Fitzwater Drive)
8
Fuller Rd./Fuller Heights Rd. (Quantico Marine Corps Base Entrance)
Accomplishments Environmental Categorical Exclusion (CE) document approved by VDOT and FHWA Public hearing on project was held on May 18, 2011 Utility Field Inspection (UFI) meeting was held on April 18, 2011 BOCS approved project design on July 26, 2011 County has submitted package to VDOT for design approval Coordination meeting held with Marine Corps Base Quantico (MCBQ) on August 16, 2011 Issues Maintenance of traffic during construction Possible design waivers R-O-W and easement request from MCBQ Timeline Drainage and floodplain comments to be sent to VDOT in October 2011 R-O-W authorization from VDOT anticipated by December 2011
9
Fuller Rd./Fuller Heights Rd. (Quantico Marine Corps Base Entrance)
10
Telegraph Road Commuter Lot
Accomplishments Final plans for Phase I (Commuter Lot) have been approved by VDOT Final design for Phase II (Telegraph Road) initiated and submitted to VDOT for review $7.2 M in funding from the State available for project construction of both phases Issues Right-of-Way Acquisition for and additional lane requirements for Telegraph Road Improvements Coordinate with adjacent developers Timeline Construction advertisement for lot – mid-October 2011 Construction for the lot anticipated to begin – late Fall 2011 Final R-O-W plan approval for road improvements – November 2011 Construction advertisement for road improvements – Late Spring 2012
11
Telegraph Road Commuter Lot
12
Preliminary design is in progress Issues Utility Relocation Timeline
Old Bridge Road Pedestrian Improvements (Mohican Road to Dillingham Square) Accomplishments Preliminary design is in progress Issues Utility Relocation Timeline Design anticipated to be completed by mid-December 2011 Construction is anticipated to start March 2012
13
Old Bridge Road (Springwoods Drive Turn Lane)
Accomplishments Design plans were approved by VDOT on May 12, 2011 for construction Issues None Timeline Construction by County forces started on July 1, 2011 and is complete This is the final report
14
Prince William Parkway (Old Bridge Road to Minnieville Road)
Accomplishments Plans completed by AMT and design-build documents for RFP being prepared for advertisement NEPA environmental documentation anticipated to be Categorical Exclusion (CE) Issues Improvements to Parkway/Hillendale Intersection Timeline Advertise RFP for design-build – December 2011
15
Rollins Ford Road Accomplishments Issues Timeline
Traffic signal design and transition design plans approved by VDOT Construction on transition and conversion of two lane section to four lane section between Estate Manor Drive and Linton Hall Road underway Signal plans approved, IFB for construction is in review Issues Coordination with Park during roadway construction Timeline Construction of signal and transition to be completed late fall, 2011 Design completion for Rollins Ford Road extension anticipated by Summer 2012
16
Route 1 – Dale Blvd. to Featherstone Rd.
Accomplishments Three unsolicited design-build proposals received for the project Issues None Timeline Evaluation of unsolicited design-build proposals – November 2011 Possible award of design-build contract – February 2012
17
Minnieville Road – Spriggs Rd. to Rte. 234
Accomplishments Three unsolicited design-build proposals received for the project Issues None Timeline Evaluation of unsolicited design-build proposals – November 2011 Award of design-build contract – February 2012
18
Mountain Road Improvements (Revenue Sharing/TRIP) (Bear Hollow Trail to Jackson Hollow Road)
Accomplishments Bid document is completed R-O-W and easements offers have been sent out Issues R-O-W negotiations Utility relocation Timeline Final comment resolution meeting with VDOT to scheduled in October 2011 Completion of R-O-W acquisition anticipated for Fall 2011 Utility relocation completion anticipated for Spring 2012 Construction advertisement scheduled for Spring 2012 at conclusion of utility relocations
19
Mountain Road Improvements (Revenue Sharing/TRIP) (Bear Hollow Trail to Jackson Hollow Road)
20
Logmill Road Improvements
Accomplishments Surveying is completed Preliminary plan design is in progress Project kick-off meeting with VDOT and JMT held in September 2011 Issues None Timeline Project Day meeting is scheduled for November 2011 100% Plan submission scheduled for December 2011 Advertisement for construction – Spring 2012 Construction completion anticipated for November 2012
21
Accomplishments Issues Timeline
Fuller Heights Rd. Sidewalk – Bethlehem Church Rd. to Potomac Crest Dr. (TRIP) Accomplishments Majority of R-O-W acquisition is completed Construction by County forces is in progress Issues Coordination during construction of sewer line with project Timeline Construction completion is anticipated by May 2012
22
Hoadly Road Trail – Spriggs Road to Dale Boulevard (TRIP)
Accomplishments Surveying is completed Preliminary plan design is in progress Issues Asphalt trail type/ R-O-W constraints Possible design waiver Timeline Preliminary plan submission to VDOT anticipated for November 2011
23
Wermuth Way (TRIP) Accomplishments Issues Timeline
Plats have been completed by AMT R-O-W Acquisition is in progress Issues None Timeline R-O-W Acquisition anticipated to be completed by November 2011
24
Glenkirk Road Sidewalk
Accomplishments County request to administer project approved by VDOT Issues Advertisement of RFP for design using Federal funds Timeline Initiate design services in November 2011 Advertise for construction in Fall 2012
25
Mine Road @ Van Buren Road Intersection Improvements
Accomplishments County request to administer project approved by VDOT Issues Advertisement of RFP for design using Federal funds Timeline Timeline is currently under development
26
Panther Pride Drive Sidewalk
Accomplishments County request to administer project approved by VDOT Issues Advertisement of RFP for design using Federal funds Timeline Timeline is currently under development