Download presentation
Presentation is loading. Please wait.
Published bySharlene Anthony Modified over 6 years ago
1
Acterna Headquarters John M Sekel Germantown, Maryland
The Pennsylvania State University Architectural Engineering 2003 Senior Thesis Presentation Structural Emphasis
2
Presentation Overview
Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions and recommendations Structural Option John M Sekel
3
Existing building Project Team Owner: Milestone Industrial, LLC
Architect: Hickok, Warner, Fox Architects Structural Engineer: Structural Design Group MEP Engineer: Girard Engineering General Contractor: L.F. Jennings Structural Option John M Sekel
4
Existing Building General New corporate campus for Acterna Corporation
Site clearly visible off I-270 outside Washington, D.C. Six story, 187,500 sf office building 253’x126’ building footprint $10 million construction cost BOCA 1996 design code Structural Option John M Sekel
5
Existing Building Structural Floor framing Foundations
Composite beam and slab construction 50 ksi wide flange shapes 30’x25’ typical bays 3 ¼” lightweight concrete slab on 2” metal decking 2 – transfer girders over conference room on level 1 Foundations Spread footing foundations 4” first floor slab on grade Structural Option John M Sekel
6
Existing Building Structural Lateral Frames
2 – braced frames in each direction Structural Option John M Sekel
7
Existing Building Typical framing plan Structural Option John M Sekel
8
Existing Building Mechanical Electrical/Lighting
VAV boxes with electric duct heaters and reheat coils with VFD 2 – cfm VAV A/C units per floor 2 – 350 ton cooling towers Plate and frame heat exchanger Electrical/Lighting 277/480 volt, 3-phase, 4 wire system 4000 amp primary switchboard 2000 amp secondary switchboard 2’x4’ 277 volt florescent fixtures Structural Option John M Sekel
9
Presentation Overview
Existing Building Proposal Structural Re-design Construction Considerations Architecture Re-design Mechanical Considerations Conclusions Structural Option John M Sekel
10
Proposal Structural design goals
Eliminate intermediate column line outside of core Use long span steel from core to exterior Economize the structure Design for ease of construction Update to IBC 2000 code Structural Option John M Sekel
11
Proposal Architectural design goals
Reflect structural changes in the façade Open interior spaces, column free areas Add glazing to lessen “hole-punch” look Emphasize the drum shape Predominant architectural feature Structural Option John M Sekel
12
Proposal Construction goals Mechanical considerations
Reduce construction cost Reduce construction schedule time Design building for ease of construction Mechanical considerations Analyze impact of façade design on system Structural Option John M Sekel
13
Presentation Overview
Existing Building Proposal Structural Re-design Construction Considerations Architecture Re-design Mechanical Considerations Conclusions Structural Option John M Sekel
14
Structural depth Framing Re-design Overview
New bay size outside of core 30’x50’ 50 ksi wide flange shapes Most readily available shapes Possible options 3 ¼” lightweight concrete slab on 2” metal deck 2 hour fire rating Re-size frames for additional gravity load IBC 2000 lateral loads Structural Option John M Sekel
15
Use 50’ to maintain core size
Structural depth Economic steel design measures Redundant shapes Simple shear tab connections Efficient spacing and span direction Efficient bay size Original 1.5 * 25’ = 37.5’ Redesign 1.5 * 30’ = 45’ Use 50’ to maintain core size Structural Option John M Sekel
16
Structural Depth New framing plan Structural Option John M Sekel
17
Structural Depth New gravity member sizes Typical Girders
Original: W18 New Design: W24 Typical Beams Original: W14 Typical Interior Column Original: W12x65 New Design: W14x120 Typical Exterior Column Original: W10x54 New Design: W14x90 Deflection criteria controls (L/360) Structural Option John M Sekel
18
Structural Depth ƒn calculation Vibration Analysis ap/g calculation
0.18 √[g/(Δg+Δj)] 3.19 Hz Vibration Analysis Typical bay analyzed Wj=157.8 kips Δj=1.040” Wg=156.8 kips Δg’=0.191” Po=65 lb β=0.03 W=157.6 kips ap/g calculation [Po e^(-0.35ƒn)]/βW 0.45%g Structural Option John M Sekel
19
Structural Depth ap/g vs. fn chart Most accurate between 4 and 8 Hz
Combined mode frequency is 3.19 Hz Peak acceleration is 0.45% of g Meets acceptable criteria for office buildings 0.64% of g at 3.19 Hz Structural Option John M Sekel
20
Structural Depth New Braced Frame Sizes Foundations
Original frame layouts and geometries were maintained Frames 1 & 4: Inverted “V” Frames 2 & 3: Diagonal All web members are TS 10”x10”x5/16” Column sizes increased for higher gravity load Designed for member strength and drift Foundations Spread foundation system Size and depth increased due to greater load Structural Option John M Sekel
21
Presentation Overview
Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions Structural Option John M Sekel
22
Construction Breadth Cost Comparison
RS Means cost estimate for both systems Cost includes material, labor and equipment Item Original Design New Design Difference Structural Steel $1,182,852 $1,263,433 $80,581 Fire Proofing $145,957 $118,316 $28,641 Foundations $182,790 $159,800 $22,990 Total $1,511,599 $1,541,549 $28,950 Structural Option John M Sekel
23
6 ½ weeks superstructure
Construction Breadth Schedule Comparison Fewer beams to place Typical floor original: 222 members Typical floor redesign: 127 members Fewer columns and foundations 16 columns removed in redesign 30% reduction in structure construction time Original Design 20 days foundations 9 weeks superstructure Redesign 14 days foundations 6 ½ weeks superstructure Structural Option John M Sekel
24
Presentation Overview
Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions Structural Option John M Sekel
25
Architectural Breadth
Reflect change in floor framing Square box-like windows Long, continuous windows Structural Option John M Sekel
26
Architectural Breadth
Increase glazing Emphasize the drum Vertically spanning glass Structural Option John M Sekel
27
Architectural Breadth
Structural Option John M Sekel
28
Architectural Breadth
Structural Option John M Sekel
29
Architectural Breadth
Structural Option John M Sekel
30
Architectural Breadth
Structural Option John M Sekel
31
Presentation Overview
Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions Structural Option John M Sekel
32
Mechanical Breadth Increase in cooling load
Greater glazing area on facade Carrier hourly analysis program analysis Additional 1.5 tons of cooling required per floor Original system capacity is 92 tons per floor 1.6% increase Most likely will not need to resize equipment Further analysis required Structural Option John M Sekel
33
Presentation Overview
Existing Building Proposal Structural Redesign Construction Considerations Architecture Redesign Mechanical Considerations Conclusions Structural Option John M Sekel
34
Conclusions Insignificant cost difference by implementing new system
Shorter construction time Faster cost return Improvement to building architecture Greater tenant flexibility with interior spaces Good selling point for owner More notable exterior façade Final Recommendation: Use re-designed structural system Structural Option John M Sekel
35
Thank You Structural Design Group LF Jennings AE Faculty and staff
Mike Weiss LF Jennings Kevin Malpass AE Faculty and staff Prof. Parfitt, Dr. Geschwinder, Dr. Hanagan AE classmates Chris Flynn, Tim Nolan My parents and roommates for their encouragement and support Structural Option John M Sekel
36
Questions? ? ? ? ? ? Structural Option John M Sekel
37
Structural Depth Building Height Comparison Structural Option
John M Sekel
38
Structural Depth Plenum heights 11 ¾” increase per floor
5’-10 ½” total building height increase Structural Option John M Sekel
39
Structural depth Plenum comparison Typical In-Bay Framing Member
Deepest Member at Duct Crossing Required Plenum Depth Original Design W14x22 [17] 1” W18 46 ¾” New Design W24x55 [48] 1 ¼” W30 58 ½” Structural Option John M Sekel
40
Structural Depth Deflections and camber Structural Option John M Sekel
41
Structural Depth Connections Structural Option John M Sekel
42
Structural Depth Drift Frame Drift Ratio #1 1.77” 1/583 #2 1.49” 1/693
#3 1.44” 1/717 #4 2.43” 1/425 Structural Option John M Sekel
43
Structural Depth Drift Frame #1 Frame #2 Frame #3 Frame #4 Level Drift
Ratio 2 0.290” 1/662 0.219” 1/877 0.226” 1/850 0.371” 1/518 3 0.288” 1/583 0.268” 1/627 0.270” 1/622 0.386” 1/435 4 0.299” 1/562 0.265” 1/634 0.260” 1/646 0.414” 1/406 5 0.295” 1/570 0.254” 1/661 0.244” 1/689 0.415” 1/405 6 0.292” 1/575 0.240” 1/700 0.224” 1/750 0.411” 1/409 R 0.302” 1/616 0.238” 1/782 0.212” 0.430” 1/433 Structural Option John M Sekel
44
Construction Breadth Working crews
RS Means assumes a steel crew of the following: (2) Steel foremen (5) Steel workers (1) Welder (1) Welding machine (1) Oiler operator (1) Crane operator (1) 90 ton crane The daily operating cost for this crew is $ Structural Option John M Sekel
45
Construction Breadth Crane reach 60 ton crane 4 ton pick at 60’
W21X182 frame column Structural Option John M Sekel
46
Construction Breadth Project delivery system Structural Option
John M Sekel
47
Construction Breadth Linear footage comparison
Original structure: 43,300 feet Redesigned structure: 32,700 feet Additional cost is hidden in fabrication and materials Structural Option John M Sekel
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.