1 Clean Coal Initiative at the Summit Anthracite Facility
Schuylkill County Proposed Site at Summit Anthracite Mine Wilkes University October 29, 2007 1

2 Agenda US Coal Reserves Partners Technology Site Project Options
Impact (Economic & Environmental) Progress Questions 2

3 US Coal Reserves

4 US Coal Reserves

5 Select History of Gasification Projects
140 Power, Methanol 1,000 1 Germany SVZ 92,080 138 50/80 Fuel Gas 350/500 2 GB British Gas1 100 Town Gas 940 6 Ruhrgas AG1 90 820 5 65 580 4 170 Electric Power 1,560 Steag AG1 Ammonia 1,080 PR China CNTIC 830 SNG 16,000 14 USA Great Plains 2,680 Liquid Fuels 30,000 40 RSA Sasol III Sasol II 1,200 Syngas/Chemicals USA* EPIC MWe Main Products Coal Input (tpd) Gasifiers Country Client *Over EPIC designed gasifiers operate in China. At least 50 run on Anthracite!

6 Typical Gasifier Operations: Much CLEANER Than burning coal
EPIC AirBlown 6

7 Coal Gasification Process
7

8 Future NEPA Project: Map I
Mine Site 8

9 Future NEPA Project: Map II
9

10 Future NEPA Project Options
Option #1: 140 MW Clean Power Project $300 Million investment $68 Million annual revenue 450k tons anthracite required annually Option #2: 60MMSCFD SNG Project $550 Million investment $120 Million annual revenue 1 Million tons anthracite required annually 10

11 Future NEPA 60MMSCFD Coal to SNG Project
Optional Chemicals BGL 11

12 Mass Balance - SNG 12

13 Future NEPA 140 MW Coal to Power Project
GE 7E A EPIC SUMMIT MINE EXPORT 13

14 Mass Balance - Coal to Electricity
14

15 Economic Impact on the Community
Investment in Schuylkill County $400 mm Construction Jobs $50K $10 mm Cluster Jobs $50K $3.5 mm Permanent Jobs $50K $7.5 mm Property Tax Base: $400 mm Annual Revenue: $100 mm $XX mm 15

16 Progress 140 MW Clean Power Project 60MMSCFD SNG Project
Binding Term Sheet for plant and technology Turnkey EPC commitments Mass - Balance Report Successful coal tests, prelim emission report 60MMSCFD SNG Project 16

17 Discussion / Questions
17