R. Graciani for LHCb Mumbay, Feb 2006
LHCb Plans for SC4 R. Graciani for LHCb Mumbay, Feb 2006
2
LHCb Plans for SC4 (Mumbay, Feb 2006)
Overview The LHCb Computing Model Storage Classes LHCb DC06 LHCb SC4 Aim Preparation SC4 Outlook LHCb Plans for SC4 (Mumbay, Feb 2006)
3
LHCb Plans for SC4 (Mumbay, Feb 2006)
LHCb Computing Model LHCb Plans for SC4 (Mumbay, Feb 2006)
4
LHCb Computing Model (I)
RAW data distribution: Tier-0 -> Tier-1’s Stored on MSS for resilience Data Tier-1’s + Tier-0 First pass: RAW still on MSS disk cache Second pass: RAW retrieved from MSS Note 50% of re-processing at Online Farm. Produce rDST, stored on MSS LHCb Plans for SC4 (Mumbay, Feb 2006)
5
LHCb Computing Model (II)
Stripping (filtering, streaming, skimming…) First pass: rDST and RAW still on MSS cache Later pass: rDST and RAW from MSS Produces DST for analysis: distributed to ALL Tier-1’s+CAF+few large Tier-2 MSS at producer site Disk replicas at ALL Sites Analysis of DST: DST from disk Produces User data (N-tuples, ETC, mini-DST…) LHCb Plans for SC4 (Mumbay, Feb 2006)
6
LHCb Computing Model (III)
Simulation temporary storage at Tier-2 (“volatile” disk) rDST transferred to associated Tier-1 (including CERN) from then on, similar to real data Tier-1’s DST distributed to CAF + 1 additional Tier-1 MSS + disk Available on disk Other activities: alignment, calibration, detector studies,… LHCb Plans for SC4 (Mumbay, Feb 2006)
7
Data|Storage Classes (I)
Single|Double copy, MSS, + disk cache RAW (Tier-1 + Tier-0), rDST (at Tier-1 production site) Production access for reprocessing Multiple copies, permanently on disk DST (CAF+Tier-1s+few large Tier-2s) More than one version of all DSTs (at least 2 latest) Efficient access needed from WNs (IO bound analysis) LHCb Plans for SC4 (Mumbay, Feb 2006)
8
Data|Storage Classes (II)
Single copy user files, on disk, reliability needed mini-DSTs, Ntuples (AOD)… created outside control from the VO-manager possibly small files (down to 10’s of MBytes) needs high reliability or MSS backup permanently available on disk (quota!) Ancillary files DIRAC sandboxes (disk-only) Production logfiles (disk-only): web access required LHCb Plans for SC4 (Mumbay, Feb 2006)
9
LHCb DC06 “Test of LHCb Computing Model using LCG Production Services”
Distribution of RAW data Reconstruction + Stripping DST redistribution User Analysis MC Production Use of Condition DB (Alignment + Calibration) LHCb Plans for SC4 (Mumbay, Feb 2006)
10
LHCb Plans for SC4 (Mumbay, Feb 2006)
SC4 Aim for LHCb Test Data Processing part of CM Use 200 M MC RAW events: Distribute Reconstruct Stripped and Re-distribute Simultaneous activities: MC production User Analysis LHCb Plans for SC4 (Mumbay, Feb 2006)
11
LHCb Plans for SC4 (Mumbay, Feb 2006)
Preparation for SC4 Event generation, detector simulation & digitization 100M B-physics + 100M min bias events: 3.7 MSI2k · month required (~2-3 months) 125 TB on MSS at Tier-0 (keep MC True) Timing: Start productions mid March, Full capacity end March LHCb Plans for SC4 (Mumbay, Feb 2006)
12
LHCb Plans for SC4 (Mumbay, Feb 2006)
LHCb SC4 (I) Timing: Start June Duration 2 months Distribution of RAW data Tier0 MSS SRM Tier1’s MSS SRM 2 TB/day out of CERN 125 TB on Tier1’s LHCb Plans for SC4 (Mumbay, Feb 2006)
13
LHCb Plans for SC4 (Mumbay, Feb 2006)
LHCb SC4 (II) Reconstruction/stripping 270 kSi2k · month 60 TB on Tier1’s (full DST) 1k Job/day (following the data) Jobs duration 2 hour 90 % Jobs (Rec): Input 3.6 GB Output 2 GB 10% Jobs (Strip): Input 20 GB Output 0.5 GB DST Distribution 2.2 TB on Disk / Tier1 + CAF (selected DST+RAW) LHCb Plans for SC4 (Mumbay, Feb 2006)
14
LHCb Plans for SC4 (Mumbay, Feb 2006)
DIRAC Tools & LCG DIRAC Transfer Tier-0 + Tier-1’s FTS + SRM DIRAC Production Tools Production Manager console Transformation Agents DIRAC WMS LFC + RB + CE Applications: GFAL: Posix I/O via LFN LHCb Plans for SC4 (Mumbay, Feb 2006)
15
LHCb Plans for SC4 (Mumbay, Feb 2006)
To be Tested after SC4 Data Management: SRM v2 gridFTP 2 FPS Workload Management: gLite RB ? gLite CE ? VOMS Integration with MW Applications Xrootd LHCb Plans for SC4 (Mumbay, Feb 2006)
16
LHCb Plans for SC4 (Mumbay, Feb 2006)
Outlook DC06: Data processing test (SC4) MC Production User Analysis Check of LHCb Computing Model LCG Production Services not in place LHCb Plans for SC4 (Mumbay, Feb 2006)