Boris Sursky LEED AP BD + C

3 The e-Roofing Permitting System is the WINNER of the prestigious NATIONAL ROOFING CONTRACTORS ASSOCIATION 2003 GOLD CIRCLE AWARD for service to industry.

4 The e-Roofing Permitting System is the WINNER of the 2004 NATIONAL ASSOCIATIONS OF COUNTIES AWARD FOR INTEGRATING PROCESSES AND SERVICE: ROOFING/STORM PANEL PERMITTING AND SERVICES SYSTEM

5 The e-Roofing Permitting System provides progressive and improved customer service through the use of advanced technology.

6 The e-Roofing Permitting System is an revolutionary permitting application process, with tens of thousands of Roofing permits issued since 2004.

7 The e-Roofing Permitting System was put to the test after Hurricane Wilma which occurred in 2005, when over 12,000 e-Roofing permits were issued in a 12 month period using this system.

8

9 CLICK HERE

10 CLICK HERE

11 CLICK HERE

12 CLICK HERE

13 CLICK HERE

14 CLICK HERE

15 ENTER TRADESMAN NUMBER

16 Contact Contractor’s Section for assistance with Tradesman Number.

17

18 CREATE USER PROFILE

19 CLICK HERE

20

21

22

23 CLICK HERE

24 Enter: Roofing (CCC) Contractor License Number

25

26 2 units required for duplexes

27 Use total ft² “NOT 2 Roofing Squares”
CLICK HERE

28

29 Select Low Slope Manufacturer

30

31 Do Not Use Fractions

32

33

34

35

36

37 Minimum 2/12” ROOF SLOPE required for shingles

38 ROOF MEAN HEIGHTS CAN NOT EXCEDE 33 FT.

39 Note: Prescriptive fastener spacing

40 Note: Online Review was not
approved. This happens after 2 code related rejections An example of a code related rejection, would be an incorrect roof slope or roof mean height.

41

42

43

44 All Dispositions required to be approved prior to paying for permit

45 Note: Provide a completed Owner’s Notification Form at the jobsite to be collected by the inspector and submitted to Micro-Film as part of the permit record.

46

47 Print completed roofing application forms for jobsite inspections

48 ePermitting NO NO’s Use total ft² on permit application, do not use roofing squares (1=100 s.f.) No Florida Product Approvals allowed, only use current Miami-Dade County Product Approvals with the ePermitting System

49 ePermitting NO NO’s Do not use fractions when inputting data, use only decimal numbers Use correct slope for specific roof system types, for example a minimum 4/12 slope is required for mechanically attached tiles

50 ePermitting NO NO’s NO CHANGES CAN BE MADE TO the “ePermitting System generated Uniform Permit forms. Changes to system generated forms require a permit revision.

51 DO NOT SHARE YOUR PASSWORD TO ACCESS THE “ePermitting” SYSTEM
ePermitting NO NO’s DO NOT SHARE YOUR PASSWORD TO ACCESS THE “ePermitting” SYSTEM WITH ANY ONE YOU DO NOT TRUST! PERMITS CAN BE OBTAINED WITHOUT YOUR KNOWLEDGE!

52 REQUIRED DOCUMENTS FOR JOB SITE INSPECTION
A completed Section 1524 Owner’s Notification Form to be collected by Inspector and placed in Micro-Film

53 REQUIRED DOCUMENTS FOR JOB SITE INSPECTION
Completed Section A & B page including a roof plan diagram. Total roof area to be field verified by inspector & shall match paid permit fees. The completed roof plan diagram shall included dimensions, roof sections, levels and roof types.

54 REQUIRED DOCUMENTS FOR JOB SITE INSPECTION
Printed copy of the “ePermitting” system generated Uniform Roof Permit Form for the types of roof systems to be installed. Category 92 Low Slope BUR Category 95 Shingles Category 107 Tile

55 REQUIRED DOCUMENTS FOR JOB SITE INSPECTION
One copy of the Miami-Dade NOA Product Approval for the proposed roof system(s) to be installed

56 REQUIRED DOCUMENTS FOR JOB SITE INSPECTION
Low Slope BUR NOA Approval including Cover Page, System Page(s), Limitation Page(s) Class “A” Fire Directory Listing for the Low Slope BUR

57 REQUIRED DOCUMENTS FOR JOB SITE INSPECTION
Tile NOA Product Approval Tile Underlayment NOA Product Approval Tile Adhesive or Mortar NOA Product Approval

58 “ePermitting” Improvements CATEGORY 107 TILE ROOF SYSTEMS

59 New Tile Underlayment Selections
Prescriptive 30/90 hot mopped Modified Bitumen hot mopped with a required NOA Product Approval for tile underlayment Self Adhered Modified Bitumen with a required NOA Product Approval for tile underlayment

60

61 Select Tile Mechanical Attachment Method

62 Select Mortar Attachment Type

63 Select Adhesive Attachment Type

64 Adhesive Type Selected, Note Exposure Category Selected
EXPOSURE CATEGORY D IS TYPICALLY OCEAN LINE

65 Select Roof Deck Type

66 Select Base Sheet Type

67 Prescriptive Tile Underlayment Selected

68 Modified Bitumen Hot Mopped Tile Underlayment

69 Self Adhered (S/A) Underlayment

70 I Agree Statement

71 SAMPLE NOA LIMITATIONS

72 SAMPLE NOA LIMITATIONS

73 SAMPLE NOA LIMITATIONS

74 SAMPLE NOA LIMITATIONS

75 Tile Roof System Shall comply with RAS 118, 119, 120
CLICK HERE

76 Self Adhered Underlayment Selected
Note: Yes “I AGREE” STATEMENT SELECTED

77 Note: Attachment Method

78 Note: That the calculated attachment
resistance in P3 is greater than attachment resistance found in the NOA

79 Note: Attachment Method

80 Note: That the calculated attachment
resistance for all roof zones are LESS than the attachment resistance found in the Tile NOA.

81 Submit Review if Application is Complete
CLICK HERE

82 Approved Application