The Ross Development Trust
SCIO founded in 2016 Aim to replace Ross Theatre and improve WPSG Accessible to all – A Place for People Currently working with CEC within a development agreement to allow fundraising and construction
2
Ross Fountain Restoration
Donated to city 145 years old Hasn’t worked since 2010 122 Pieces Restoration due for completion by Summer 2018
3
International Design Competition
125 submissions 7 shortlisted 1000 visitors to the Exhibition Technical review held 27 June 17 Independent Jury agree winning concept 11 July 17
4
Winning Concept American architect’s wHY Local partner - GRAS Flexible performance space 20% more green space Improved Access Public Favourite in Scotsman vote 96 million online reach
5
Where are we now? Potential donors have expressed caution regarding the future maintenance Reassurance needed from CEC to donors that their contributions will leave a legacy for the City Fundraising and design development temporarily suspended until we can give this assurance
6
Working with CEC to develop a Business Case (OBC)
3 facilitated workshops held in January to identify key areas of OBC Agree what can be offered for donor assurance Develop a sustainable maintenance model Reassurance to the public on access and usage Complete Business Case for review at Finance and Resources Committee in March
7
Next Steps Complete and approval given on OBC Resume Fundraising Further work on concept design development