Presentation is loading. Please wait.

Presentation is loading. Please wait.

Planning Quality control - Manufacturing logbook Photos Conclusions

Similar presentations


Presentation on theme: "Planning Quality control - Manufacturing logbook Photos Conclusions"— Presentation transcript:

1 Planning Quality control - Manufacturing logbook Photos Conclusions
2 PROTOTYPES FOR SPS - OUTLINE Planning Quality control - Manufacturing logbook Photos Conclusions Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

2 2 PROTOTYPES FOR SPS -MANUFACTURING
Planning – production – installation Very detailed planning established at the start of the manufacturing drawings Including ALL operations - on a daily basis TOTAL: 123 days until installation :00h This included: Design, stores, workshop, brazing, metrology, lab for thermal measurements, assembly, pressure test, vacuum test, electro beam-welding, bakeout equipment, calibration, test of moving mechanism Space requirements in SPS, safety - radiation installation logistics, transport ON TIME within less than 5 days Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

3 2 PROTOTYPES FOR SPS MANUFACTURING
Quality control - Manufacturing logbook Record non-conformities Record dimensional measurements Record reference measurements for final alignment in SPS Time of operations for estimation of series production - will serve as an example for industry Photos Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

4 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

5 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

6 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

7 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

8 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

9 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

10 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

11 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

12 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

13 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

14 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
CONCLUSIONS The mechanical design remains close to the LEP collimators BUT high beam energy requires carbon and very efficient cooling - new jaws design Extensive thermo-mechanical analyses predict that the requested 25 μm should be possible but not proven yet… prototype manufactured on standard machines Temperature measurements confirm thermal calculations Prototype design finished, series design started Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

15 A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME
CONCLUSIONS – next steps Manufacture of three prototypes according to schedule, two for the SPS – one for tests Installation date in sight Market survey for series production launched Many different versions ( TCP, TCS, TCT, TCLI, TCLP, TCHS, TCDI ) with different angles “Standardisation” of different types of collimators will require considerable design effort ( one motor, two motors, plug-in, spares ) Special types with two beams in the same tank need still to be studied in detail Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME

16 KEEP THE MOMENTUM GOING Re-enforce the design team
FINAL REMARKS Next “Milestone” drawings for tender of part of the series end of August lot of work still ahead! KEEP THE MOMENTUM GOING Re-enforce the design team TO MEET THE DEADLINE OF THE FINANCE COMMITTEE BY THE END OF THE YEAR Collimator revue A. Bertarelli - S. Calatroni - M. Mayer - R. Perret TS/MME


Download ppt "Planning Quality control - Manufacturing logbook Photos Conclusions"

Similar presentations


Ads by Google