1
National LambdaRail Update Dave Jent NLR Layer 2/3 Service Center Indiana University
July 18, 2005
2
National LambdaRail Update
Installation update Phase 2 Layer 1 Layer 2 deployment Layer 3 deployment Other Credits
3
National LambdaRail Update
SEA 8 8 POR 8 8 BOI SYR 8 4 4 4 STA 4 NYC OGD 4 8 4 PIT 4 8 DEN KAN 8 8 8 CHI CLE CLE 8 SVL 4 8 8 8 8 SLC 8 4 4 8 8 8 4 WDC 4 8 LAX RAT RAL 4 8 LAX 8 4 PHO 4 ALB TUL 4 4 8 4 8 ATL 4 DAL 4 ELP 4 4 4 PEN 4 JAC 8 4 4 4 4 4 4 Level3 fiber WilTel fiber 4 4 SAA BAT 4 4 HOU Cisco terminal Cisco OADM Cisco terminal Cisco OADM 8 4
4
National LambdaRail Update
Phase II Layer I Deployment SYR 4 4 4 NYC OGD 4 4 DEN CLE 4 SLC KAN 4 4 4 WDC 4 LAX RAT 4 4 PHO 4 ALB TUL 4 4 4 4 DAL 4 4 ELP 4 4 PEN 4 JAC 4 4 4 4 4 4 Level3 fiber WilTel fiber 4 4 SAA BAT 4 4 HOU Cisco terminal Cisco OADM Cisco terminal Cisco OADM 8 4
5
National LambdaRail Update
Phase I PoP Layout CRS-1 6509 15808 15500 East West Metro and Regional Optical Networks NLR demarc DWDM 1GE 10GE or OC192
6
National LambdaRail Update
Phase II PoP Layout CRS-1 6509 15454 15500 East West Metro and Regional Optical Networks NLR demarc DWDM 1GE 10GE or OC192
7
Install Completion Date Test Start Date Test Completion Date
Provider Segment OLA Sites OADM / Regen Sites Terminal Sites Install Start Date Install Completion Date Test Start Date Test Completion Date Interconnect Ready Date Targeted Equipment Ship Date WilTel KC to Dallas 11 1 2 06/28/05 07/12/05 07/27/05 08/04/05 4/5/2005 5/2/2005 Dallas to Houston 6 07/11/05 07/19/05 n/a Houston to Baton Rouge 07/26/05 08/22/05 08/25/05 5/23/2005 Level 3 NYC to DC 7 07/28/05 08/05/05 08/31/05 09/03/05 NYC to Syracuse 9 08/16/05 09/08/05 09/16/05 Syracuse to Cleveland 10 08/26/05 3/15/2005 6/13/2005 WilTel/Level 3 Baton Rouge to Pensacola 08/29/05 09/07/05 10/21/05 10/29/05 TBD Pensacola to Jacksonville 8 09/17/05 6/6/2005
8
* ** Provider Segment OLA Sites OADM / Regen Sites Terminal Sites
Install Start Date Install Completion Date Test Start Date Test Completion Date Interconnect Ready Date Targeted Equipment Ship Date Level 3 & WilTel Ogden to Salt Lake City 1 * ** TBD 5/9/2005 WilTel Houston to San Antonio 5 2 06/23/05 06/30/05 08/09/05 08/17/05 n/a 5/2/2005 San Antonio to El Paso 14 07/05/05 07/20/05 El Paso to Phoenix 10 07/19/05 07/30/05 10/07/05 10/15/05 5/30/2005 Phoenix to LA 11 07/29/05 08/12/05 Level 3 El Paso to Albuquerque 4 08/20/05 09/22/05 09/28/05 4/5/2005 6/13/2005 Albuquerque to Denver 7 08/22/05 09/07/05 5/6/2005
9
National LambdaRail Update
Layer 2 Network Design SEA CHI NYC PIT DEN SVL KAN CLE WDC RAL LAX PHO ALB TUL ATL ELP JAC BAT HOU 10GE wave 10GE managed wave Cisco 6509 switch
10
Layer 2 Completed and connected via 10GE:
Sunnyvale Denver Kansas City Chicago Cleveland Pittsburg Washington DC Raleigh Jacksonville installation this week, Seattle next week Atlanta scheduled for the week of August 1 Tulsa scheduled for the week of August 8, Los Angles scheduled for the week of August 15. Houston and EL Paso scheduled for the week of August 22. Baton Rouge scheduled for the week of August 29. New York City scheduled for the week of Sept 5. Albuquerque scheduled for he week of OC 4. FE's ==== FE"s are in from SNVA to PIT. JAC goes in next week. Atlanta is currently scheduled for the week of August 1. That could push back by up to 2 weeks. WDC is scheduled for the week of Aug 8.
11
National LambdaRail Update
Layer 3 Network SEA CHI NYC DEN PIT WDC LAX RAL PHO TUL ALB ATL BAT JAC HOU Cisco CRS-1 router 10GE wave 10GE managed wave
12
10GE circuit between DEN & CHI up.
Layer 3 Denver is complete Chicago is complete 10GE circuit between DEN & CHI up. Seattle scheduled for the week of JUL 25th *Atlanta scheduled for the week of August 1. *Pending schedule adjustment Say something about the UCAR connection to the router, this is the first connection.
13
WDC is scheduled for the week of Aug 8.
Layer 3 WDC is scheduled for the week of Aug 8. LAX is scheduled for the week of AUG 15. HOU is scheduled for the week of AUG 22. NYC is scheduled for the week of Sept 5. DC, LA, HOU, NYC are dependent on the Wiltel schedule.
14
Other Tom has Layer 1 pricing
NLR Board is working setting prices for L2 and L3 Anticipate some information soon Group B report impact, not, yet Layer 2/3 and Service Desk have renewed contracts for support of the network and users.
15
Credits (IU) Caren Litvanyi, Lead Technical Engineer, L2/3
Jon-Paul Herron, Project Manager Grover Browning, Deployment Manager Steve Peck and staff, Service Desk Manager Caroline Carver Jay Duncan Andrew Lee Chris (smokin’ hot) Robb Brent Sweeny Luke Fowler Chris Small Steve Kerby
16
Credits (CENIC) Sherilyn Evans Director of Technical Services
Cindy Abercrombie NOC Manager Chris Costa Darrell Newcomb Heather Sherman
17
Credits (MCNC) Mark Johnson Bonnie Phillips John Moore Tommy Jacobson
18
N L R For more information… Contact Tom West twest@nlr.net
NLR puts the control, the power and the promise of experimental Contact Tom West NLR: putting the control, the power and the promise of experimental network infrastructure in the hands of our nation’s scientists and researchers. light the future N L R