Download presentation
Presentation is loading. Please wait.
Published byAusten May Modified over 6 years ago
1
Collaborative Results Restructuring Roundtable March 28, 2003
Massachusetts DTE DG Interconnection Collaborative Collaborative Results Restructuring Roundtable March 28, 2003
2
What Is An Interconnect (Nomenclature)?
The interface between Distributed Generation (DG) equipment, (the Facility) and the grid (the area Electrical Power System or EPS) Point of Common Coupling (PCC) EPS Radial Customer Facility EPS Customer Site (interconnecting facility) Network Customer EPS Load 1 Load 2 Load 3 DG (generating facility)
3
Collaborative Effort Has Resulted in the Creation of Four Processes
Simplest process Minimal or no costs expected Shortest time Still reasonably simple Strict limits Modest fees, longer time interval Standardized process Screens / Supplemental Review technical approach Moderate fees , longer time interval Similar to current process Essentially based on actual costs Potentially long time interval Simplified - Radial Simplified – Network Expedited – Radial Standard – Radial or Network
4
Simplified Radial Process
One sheet application and approval Only three technical screens Radial distribution systems only Limited to 10kW or less Inverter-based, UL1741 listed Minimal or no costs expected 15 business days max Customer Submits Application Network or Radial EPS? Complete Simplified Process >7.5% of circuit peak load? ≤10kW Qualified Inverter? Radial Yes To Network Process To Supplemental Review No To Expedited Screens
5
Simplified Network Process
One sheet application and approval Additional technical limits Spot network only Tighter capacity limit $100 or $300 fee 40 to 100 days max Area or Grid Network 1 Substation Circuit 2 3 Secondary Bus Loads Primary Feeders Transformer Network Protector Breaker Network Protector Fuse Switch Spot Network Customer NP
6
Expedited Radial Process
Is Facility Certified? Supplemental Review No Yes Pass Starting V Drop? Standardized application Five additional technical screens If passed, only a review of possible EPS modifications remains If not passed, Supplemental Review determines if application can remain in Expedited or go to Standard process Fee range from $300 to $3,750, possible EPS upgrades 40 or 60 days max No Yes Pass Fault Contrib? No Yes Pass Config. Screen? No Yes Pass Trans. Stability? No (If required) Company makes EPS Modifications Yes Suppl. Review Determine Req.? Company Sends Written Authorization EPS Modification Check Optional Witness Test Yes Customer Installs Facility No To Standard Process
7
Basis For Screens Circuit impact
Fault handling, fuse desensitizing & nuisance trip Short circuit handling Proper connection Single phase imbalance Circuit size versus DG size DG contribution to fault Short circuit interrupting capability limit Three-wire and four-wire circuit criteria Nameplate limits
8
Standard Review Process
Standardized application Initial review Impact study if required Facility study if required Fee range from $300 to actual costs (no limit) 125 or 150 days max (If required) Company makes EPS Modifications initial review optional scoping meeting Impact Study if required Facilities Study if required Company Sends Written Authorization Optional Witness Test Customer Installs Facility
9
Process In Report Customer submits complete application and application fee 1. Is the Point of Common Coupling on a Radial Distribution System? No Go to Figure 2 Customer opts for Standard Process Yes 2. Is the aggregate generating Facility capacity on the circuit less than 7.5% of circuit annual peak load? No Perform Supplemental Review Initiate Standard Process initial review Yes 3. Does the facility use a Qualified Inverter with a power rating of 10 kW or less? No Yes Does the facility pass all the following screens? 4. Is the Facility certified? 5. Is the Starting Voltage Drop Screen met? 6. Is the Fault Current Contribution Screen met? 7. Is the Service Configuration Screen met? 8. Is the Transient Stability Screen met? No Does Supplemental Review determine requirements? Yes Yes No System Modification Check Company provides cost estimate and schedule for Interconnection Study(ies) Customer accepts Company performs Impact and Facility (if required) Study Facility Processed for Simplified Interconnection Under DG Tariff Facility Processed for Expedited Interconnection Under DG Tariff Facility Processed for Standard Interconnection Under DG Tariff
10
Simplified Process For Networks
Is the Point of Common Coupling on a spot network? No Initiate Standard process Yes Does the facility use a Qualified Inverter? (UL1741) No Yes Is the Facility 10kW or less? No Yes Is the aggregate generating Facility capacity less than 1/15 of Customer’s minimum load? No Yes System Modification Check Yes Facility Processed for Simplified Interconnection Under DG Tariff
11
Minimum Technical Requirements Set By
IEEE P1547 – “Draft Standard for Distributed Resources Interconnected with Electric Power Systems”. Underwriters Laboratories Inc. Standard UL 1741, November 1, 2002 “Inverters, Converters and Charge Controllers for Use in Independent Power Systems IEEE , “IEEE Recommended Practice for Utility Interface of Photovoltaic (PV) Systems.”
12
IEEE Std P1547 Key Clauses Voltage regulation
Integration with EPS grounding Synchronization Surge Withstand Response to EPS abnormal conditions Response to EPS faults EPS reclosing coordination Voltage detection and limits Frequency detection and limits Reconnection to EPS Limitation of Flicker Harmonics Unintentional islanding Design testing Commissioning testing
13
Additional Technical Requirements
For Facilities qualified for Simplified Process Must be “qualified” to UL 1741 Disconnect switch may be required For Facilities >10kW: Non-export functionality if not allowed to export Disconnect switch or comparable device Possible NPCC criteria For Facilities with rotating generators Interrupting Device (ID) Synchronizing Device (could be part of ID) Additional protection equipment requirements For large Facilities Transfer trip? High speed protection Communications channels Reactive capability (Note: Tariff also covers standby gensets that momentary parallel)
14
Simplified Spot Network
Fee Schedules Qualified Inverter ≤ 10 kW Qualified DG Any DG Simplified Expedited Standard Simplified Spot Network Application Fee (covers screens) $3/kW, minimum $300, maximum $2,500 ≤ 3kW $100, > 3kW $300 Supplemental Review or Additional Review (if applicable) N/a Up to 10 engineering hours at $125/hr ($1,250 maximum) Standard Interconnection Initial Review Included in application fee (if applicable) Impact and Facility Study (if required) Actual cost Facility Upgrades O and M TBD Witness Test Actual cost, up to $300 + travel time
15
Simplified Spot Network
Maximum Time Lines Qualified Inverter ≤ 10 kW Qualified DG Any DG Simplified Expedited Standard Simplified Spot Network Acknowledge Receipt of Application (3 days) Review Application for Completeness 10 days Complete Review of All Screens 25 days N/a Site review 30/90 days Complete Supplemental Review (if needed) 20 days Complete Standard Process Initial Review Send Follow-on Studies Cost/Agreement 5 days Complete Impact Study (if needed) 55 days Complete Facility Study (if needed) 30 days Send Executable Agreement Done 15 days Total Maximum Days 40/60 days 125/150 days 40/100 days Notice/ Witness Test <1 day with 10 day notice or by mutual agreement 1-2 days with 10 day notice or by mutual agreement By mutual agreement 1 day with 10 day notice or by mutual agreement
16
Application Process Prior Notice One Point of Contact
Application submittal Review Load flow and Voltage constraints Short Circuit and Protection review System Modification Review Agreement
17
Application Information
General (Single) or Specific Form? Simplified process (Inverter) Applicant contact information Location of generator Proof of UL1741 Others Application contact information Machine technical data Proposed drawings
18
Massachusetts Company Contacts
Boston Edison, Cambridge Electric, Com Electric (NStar Electric) Frank Gundal Tel: (781) Fitchburg Gas & Electric (Unitil) John Bonazoli P.E. Tel: (603) Massachusetts Electric Co. (National Grid) John J. Bzura, Ph.D., P.E., M.B.A. Tel: (508) Western Massachusetts Electric ( Northeast Utilities) Doug Clarke Tel:
19
Why is DG Different?
21
How Does DG Affect Distribution Companies?
Protection Generator Protection Coordination Reliability Effects Planning Procedures Peak Load Planning Firm Capacity
22
Interconnection Process Advantages
Standard Process Easier planning for customer More Efficient with time Less time Consuming Consistent Fees Known Costs to customer Known Process for customer
23
Challenges for Distribution Company
General Requirements Interpretations Analysis of compliance Testing Requirements New devices Time Lines Reports Interconnection agreement
24
Future Efforts Quarterly Collaborative Meetings
Interconnection updates Numbers of projects and applications Annual Documentation sharing Detailed process information Process Adjustments as needed
25
Upcoming Tariff Document
7 2 13 11 3 1 1.0 Introduction 2.0 Responsibility of the Parties 3.0 Process Overview 4.0 Interconnection Req. 5.0 General Operating Req. 6.0 Metering, Monitoring, and Communication 7.0 Responsibility For Costs of Interconnecting a Facility 8.0 Dispute Resolution Process 9.0 Confidentiality Statement 10.0 Insurance Req. 7 1 2 5 3 Exhibit A – Interconnection Service Agreement template Exhibit B – Third Party Owner Agreement Exhibit C – Simplified Application Exhibit D – Expedited/Standard Application Exhibit E – Supplemental Review Agreement Exhibit F – Impact Study Agreement Exhibit G – Facility Study Agreement Exhibit H – Qualifying Facilities Discussed already, from Collab. report, or new effort
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.