Download presentation
Presentation is loading. Please wait.
1
ELC 347 project management
Day 21
2
Agenda Integrative Project Assignment 7 Posted
Part 4 corrected, feedback sent, both teams need revision and clarification Part 5 Due Nov 24 (page 342) Any of the first five sections can be resubmitted for rescoring prior to finals week. The recorded score will the average of the original score and the score on the resubmitted section. Assignment 7 Posted Due Nov. 24 Today will discuss Critical Chain Project Scheduling
3
Schedule for rest of semester
Nov 17 Chap 11 Nov 20 Group work Nov 24 Quiz 3 Through Chap 11 IP part 5 Due Assignment 7 due Dec 1 Project ‘s 5 & 6 Dec 4 Group Work Assignment 8 due Dec 8 Chap 12 IP Part 6 due Dec 11 Chap 13 & 14 Dec 10 AM Quiz 4 Through chap 14 IP Project’s due © 2007 Prentice-Hall, Inc
4
Critical Chain Project Scheduling
Chapter 11 © 2007 Pearson Education
6
BAE Systems
7
Theory of Constraints & Critical Chain Project Scheduling
A constraint limits system output. The Goal – Goldratt TOC Methodology Identify the constraint Exploit the constraint Subordinate the system Elevate the constraint Repeat the process
8
Dropping a marble Top left Top right Bottom left Center
9
Dr J Edwards Deming
10
Variation Common Cause Inherent in the system Special Cause
Due to a special circumstance Managers should Understand the difference between the two Not adjust the process if variation is common cause Not include special cause variation in risk simulation Not aggregate discrete project risks
12
CCPM and the Causes of Project Delay
How safety is added to project activities Individual activities overestimated Project manager safety margin Anticipating expected cuts from management time 25% 50% 80% 90% Gaussian Distribution
13
Wasting Extra Safety Margin
The Student Syndrome Immediate deadlines Padded estimates High demand Failure to pass along positive variation Other tasks Overestimation penalty Perfectionism Multitasking Path Merging
15
Critical Chain Solutions
Central Limit Theorem V∑ = n * V , SD2 = V, Standard deviation of the sum is less than the sum of the standard deviations! Aggregating risk leads to reduced risk
16
Activity durations estimated at 50% level
Buffer reapplied at project level Goldratt rule of thumb (50%) Newbold formula (2σ) Feeder buffers for non-critical paths
19
CCPM Original 50% Probability Activity Duration A 10 5 B 6 2 C 14 7 D
E 8 3 F 12 Total 52 24 New estimate = 23 + (52-24)/2 = 37
20
CCPM Changes Due dates & milestones eliminated
Realistic estimates – 50% level not 90% “No blame” culture Subcontractor deliveries & work scheduled ES Non critical activities scheduled LS Factor the effects of resource contention Critical chain usually not the critical path Solve resource conflicts with minimal disruption
23
Critical Chain Solutions
Bob Feeder Buffer ProjectBuffer Buffers protect constraints and prevent delays
25
Critical Chain Project Portfolios
Drum – system-wide constraint that sets the beat for the firm’s throughput Drum – person, department, policy, resource Capacity constraint buffer – safety margin between projects Drum buffer – extra safety before the constraint
26
Applying CCPM to Project Portfolios
Identify the drum Exploit the drum Prepare a schedule for each project Determine priority for the drum Create the drum schedule Subordinate the project schedules (next slide) Elevate the capacity of the drum Go back to step 2
27
Subordinating Project Schedules
Schedule projects based on drum Designate critical chain Insert capacity constraint buffers Resolve any conflicts Insert drum buffers so the constraint is not starved
29
CCPM Critiques No milestones used
Not significantly different from PERT Unproven at the portfolio level Anecdotal support only Incomplete solution Overestimation of activity duration padding Cultural changes unattainable
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.