Bond Update October 16, 2017
2
Bid Packages - Phase 2 BP #7 – Edison / Indian Woods / Keewahdin Elementary School Remodeling Design In Process Bid November 1, 2017 Construct Spring/Summer/Fall 2018
3
Bid Package #7 – Edison ES
PHNHS – New Acrylic resurfacing that will also address the water drainage issues. New fencing and walk around the perimeter of the tennis courts will be incorporated. PHHS – New Acrylic resurfacing. Changing the footprint of the tennis courts by moving them to add more circulation space around the courts for spectators and coaches. New fencing that meets the high school athletic associations requirements. New ADA accessible swing gates along the south side that is next to the parking to prevent people from walking through. Existing Walk on the East side (to the running track) will remain.
4
Edison ES – Teacher Collab. Space
5
Edison ES – Staff Complex
6
Edison ES – Learning Commons
7
Edison ES – Learning Commons
8
Edison ES – Learning Commons
9
Edison ES – Kindergarten Classrooms
10
Bid Package #7 – Indian Woods ES
PHNHS – New Acrylic resurfacing that will also address the water drainage issues. New fencing and walk around the perimeter of the tennis courts will be incorporated. PHHS – New Acrylic resurfacing. Changing the footprint of the tennis courts by moving them to add more circulation space around the courts for spectators and coaches. New fencing that meets the high school athletic associations requirements. New ADA accessible swing gates along the south side that is next to the parking to prevent people from walking through. Existing Walk on the East side (to the running track) will remain.
11
Indian Woods ES – Secure Vestibule and Welcome Center
12
Indian Woods ES – Learning Commons
13
Indian Woods ES – Learning Commons
14
Indian Woods ES – Learning Commons
15
Indian Woods ES – Kindergarten Classrooms
16
Indian Woods ES – Teacher Collab. Space
17
Bid Package #7 – Keewahdin ES
PHNHS – New Acrylic resurfacing that will also address the water drainage issues. New fencing and walk around the perimeter of the tennis courts will be incorporated. PHHS – New Acrylic resurfacing. Changing the footprint of the tennis courts by moving them to add more circulation space around the courts for spectators and coaches. New fencing that meets the high school athletic associations requirements. New ADA accessible swing gates along the south side that is next to the parking to prevent people from walking through. Existing Walk on the East side (to the running track) will remain.
18
Keewahdin ES – Learning Commons
19
Keewahdin ES – Learning Commons
20
Keewahdin ES – Learning Commons
21
Keewahdin ES – Kindergarten Classrooms
22
Keewahdin ES – Teacher Collab. Space
23