SAB 3122 CONSTRUCTION TECHNOLOGY AND ESTIMATING CONCRETE AND REINFORCEMENT Dr. Chai Chang Saar.

Similar presentations


Presentation on theme: "SAB 3122 CONSTRUCTION TECHNOLOGY AND ESTIMATING CONCRETE AND REINFORCEMENT Dr. Chai Chang Saar."— Presentation transcript:

1 SAB 3122 CONSTRUCTION TECHNOLOGY AND ESTIMATING CONCRETE AND REINFORCEMENT
Dr. Chai Chang Saar

2 CONCRETE WORKS 3 MAIN ITEM concrete reinforcement bar formwork
11/23/2018

3 Concrete Mixing on Site using Cement, Sand & Aggregate
11/23/2018

4 MATERIAL 1) CONCRETE Material
Material from mixture of cement : sand : aggregate & water Example: 1: 2 : 4 (Concrete Grade 20), 1:3:6 (Concrete Grade 10) Cement Aggregate Sand 11/23/2018 Concrete Mixing on Site using Cement, Sand & Aggregate

5 MATERIAL Shrinkage - Shrinkage when pour up
Wastage - Wastage when placing, mixture Consolidated -Consolidated when compacted Consolidation compacts fresh concrete to mold it within the forms and around embedded items and reinforcement and to eliminate stone pockets, honeycomb, and entrapped air. 11/23/2018 Concrete Mixing on Site using Cement, Sand & Aggregate

6 LABOUR There are 3 types for concrete mixing on site using cement, sand & aggregate: 1) Mixing, hoisting & placing by hand Average output to mix the concrete 2.00hr/m3 concrete 2) Mixing by plant with hoisting & placing by hand 3) Mixing, hoisting & placing by plant 11/23/2018 Concrete Mixing on Site using Cement, Sand & Aggregate

7 LABOUR Hoisting & placing by hand (Table 1)
11/23/2018 Concrete Mixing on Site using Cement, Sand & Aggregate

8 MIXING, HOISTING & PLACING BY HAND
Build up rate for 1m3 reinforced in-situ concrete Grade 25 ( 1:1½:3) in isolated column by hand. Assumption Concrete Grade 25= 1:1½: 3 Cement = RM 13.00/bag (1m3=28 bag) Sand = RM 16.50/m3 Aggregate= RM 35.00/m3 Mixing =2hr/m3 Hoist and placing = 8hr/m3 General worker =RM40/day Allow 25% of shrinkage, wastage & consolidated Allow 20% profit and overhead (Applicable to all build up rate) 11/23/2018 Concrete Mixing on Site using Cement, Sand & Aggregate

9 MIXING BY PLANT, HOISTING & PLACING BY HAND
Machinery/plant Mixing by concrete mixer (Table 2) Size of mixer Workers needed Output/hr (m3 Diesel/hour (litre) Lubricator/hour (litre) 5/3½ 1 operator 1 general 1.25 1.10 0.04 7/5 3 general 2.25 1.60 0.06 10/7 4 general 3.25 1.80 0.07 14/10 4.50 2.10 0.08 18/12 6 general 5.50 2.40 0.10 11/23/2018 Concrete Mixing on Site using Cement, Sand & Aggregate

10 MIXING BY PLANT, HOISTING & PLACING BY HAND
Build up rate for 1m3 of reinforced in-situ concrete Grade 25 (1:1½:3) in isolated column. Assumption: Concrete mixer 7/5 Life-cycle = 4 year Purchase value = RM 15,000.00 Scrap value = RM 2,000.00 Interest = 10%/year Maintenance = 10% Mobilization = 5% Diesel = RM 1.90/litre Lubricator = RM 20.00/litre Average working day = 200day/year Operator = RM 50.00/day General Workers = RM 40.00/day To build up the cost for 1m3 concrete, shall include: Material cost Cost of concrete mixer and labours Cost for hoisting and placing by hand 11/23/2018 Concrete Mixing on Site using Cement, Sand & Aggregate

11 MIXING, HOISTING & PLACING BY PLANT
Build up rate for 1m3 reinforced in-situ concrete Grade 25 (1:1½:3) in isolated beams – m3 Assumption: Crane 15 tonne (rental) = RM /day (inclusive operator & fuel) Crane output for placing = 15m3/day 5 general worker for hoisting & placing Material cost/m3 (as previous) = RM Mixing cost by mixer/m3 (as previous) = RM Cost for hoisting & placing by crane 11/23/2018 Concrete Mixing on Site using Cement, Sand & Aggregate

12 Ready Mixed Concrete 11/23/2018

13 READY MIXED CONCRETE Ready mixed concrete
Concrete is ready mixed in the factory and will send to site by supplier 11/23/2018 Ready Mixed Concrete

14 READY MIXED CONCRETE Build up rate for 1m3 ready mixed reinforced concrete Grade 25 in isolated beams Assumption: Rental crane 15 tonne = RM /day (inclusive operator & fuel) Crane output to placing = 15m3/day 5 general worker to hoist & placing Ready mix concrete = RM /m3 (inclusive delivery to site) Allow 5% concrete wastage 11/23/2018

15 Reinforcement 11/23/2018

16 Tying bar for 1 tonne (kg)
RE-BAR MATERIAL Add 5% wastage for re-bar Allowance for rebar wire Table 3 Diameter (mm) Tying bar for 1 tonne (kg) 6-12 10 16-25 6 32-50 5 11/23/2018

17 RE-BAR LABOUR Output general worker 1.50 hr for 1 tonne bar
Output for cutting, bending (Table 4) Output for placing (Table 5) 11/23/2018

18 RE-BAR Build up rate for 1 kg of 16mm diameter High Tensile reinforcement in straight and bent bars in foundation Assumption: Cost for 16mm dia = RM 1,800/tonne Cost for tying bar = RM 3.50/kg General Workers = RM per day Cutting, bending & placing = RM per day 11/23/2018

19 FABRIC REINFORCEMENT MATERIAL Allow 5 % wastage
Allow 10% for tying bar Allow 10% for lapping 11/23/2018

20 FABRIC REINFORCEMENT LABOUR Output for general worker 0.15hr/m2
Output for cutting, bending, placing Location Barbender-hr/m2 Bed, floor, roof 0.20 Foundation 0.25 wall 0.33 Staircase 0.50 11/23/2018

21 FABRIC REINFORCEMENT Build up rate for1m2 fabric reinforcement BRC A6 in suspended floor slab Assumption Fabric reinforcement per pcs = RM 70.00 1 pcs of fabric reinforcement = 6.00m x 2.20m General Workers = RM per day Cutting, bending & placing = RM per day 11/23/2018

22 Formwork 11/23/2018

23 MATERIAL Can be used more than once:
-Slab and wall can be up to 6 times usage -Foundation, beam and column normally only for 4 times usage Nail is inclusive in the built up rate, 0.35kg/m2 10% of formwork wastage Strutting for formwork 11/23/2018

24 STRUTTING Strutting Location Strutting (m3) Side of column 0.02
Sides of fdnt & wall 0.04 Sides & soffit of beam 0.05 Sides & soffit of slab 0.06 11/23/2018

25 LABOUR Determine sawn formwork or wrought/wrot formwork
Add 25% for wrought formwork Output to prepare, placing and take out 11/23/2018

26 FORMWORK Build up rate for 1m2 Sawn formwork to soffit of suspended floor slab. Assumption: 12mm thick board with 2.40m x 1.20m = RM 35.00/piece Timber = RM 900/tonne (1 tonne = 1.40m3) Nail = RM 4.50/kg 11/23/2018 11/23/2018

27 THE END 11/23/2018


Download ppt "SAB 3122 CONSTRUCTION TECHNOLOGY AND ESTIMATING CONCRETE AND REINFORCEMENT Dr. Chai Chang Saar."