Hopewell Valley Regional School District
Referendum Project Update July 17, 2017
2
District-wide Clocks/PA/Messaging System
Cabling is nearly completed at all schools. Devices are being installed at Central HS.
3
Toll Gate School- Gym HVAC Upgrades
Mechanical unit curbs awaiting installation on the roof. Equipment is ready to be installed after curbs are placed.
4
Toll Gate School- Gym HVAC Upgrades
Existing mechanical units have been removed. The wall areas will be restored and wall pads will be reinstalled.
5
Central High School Roof Replacement
Roofing work in progress on July 17 (400 wing).
6
Central High School Roof Replacement
Roofing work is well underway. The red hatched areas indicate roofing areas in progress. Hopewell ES roof replacement will start after Central HS is completed.
7
Central High School Additions/Renovations To Date
1 Three project meetings have been held with contractor to discuss schedule and coordination. Township fire officials have participated in these meetings. 2 On site work completed: Utility mark-outs, office trailer, storage trailers, preliminary survey work, site coordination. 3 Project paperwork: Contracts, bonds, shop drawings, permit applications. 4 Project will ramp up this week: Fencing, trailers and start of site demolition.
8
Central High School Look-Ahead
Bid Protest Resolved (Withdrawn) July 12, 2017 Site Mobilization- Fencing and Preparations July 18, 2017 – July 21, 2017 Start site removals- trees, patio, etc. (Site access changes) July 20, 2017 See Detailed Schedule for more information Hand-Out