Download presentation
Presentation is loading. Please wait.
Published byBuddy Arnold Modified over 6 years ago
1
Transmission Planning Attachment K Public Input Meeting
FERC Order 1000, Biennial Planning Cycle Quarter 3 Meeting September 13, 2018
2
Agenda Pacific Time Topic Presenter 9:00 – 9:05
Greetings and Introductions Jamie Austin 9:05 – 9:15 Explain the Planning Process Discuss status of the local planning process and any interim iterations of the draft Local Transmission Plan; 9:15 – 9:30 TPL Study Process Scott Beyer 9:30 – 9:40 Status of Ongoing Area Planning Studies Scott Beyer, Jake Barker 9:40 – 9:55 Five Year Studies PACW Area, Kickoff Studies: Coos Bay Study PACE Area, Kickoff Studies: Montpelier Study Adam Lint, Larry Frick Sachith Abayakoon 9:55 – 10:00 Q&A
3
The Planning Process Jamie Austin
4
3rd Quarter Deliverables Process
Discuss status of the local planning process and interim iterations of the draft Transmission System Plan: Technical Studies – for designing a reliable system Economic Studies - economic analysis to identify transmission congestion PacifiCorp has been Providing quarterly updates to Stakeholders on local transmission studies (5-yrs studies; reliability assessment studies) Current plan includes posting a draft TSP in Q4, 2018 Review of the Transmission System Plan Outline
5
Transmission System Plan Outline
INTRODUCTION FERC ORDER 890\1000, ATTACHMENT K, LOCAL TRANSMISSION PLANNING PROCESS DISCUSSION THAT TIES THIS WORK TO OUR EXISTING PLANNING LOCAL PLANNING OBJECTIVES OF THE TRANSMISSION SYSTEM PLAN SUB-REGIONAL & REGIONAL COORDINATION PLANNING PROCESS AND TIMELINE TRANSMISSION SYSTEM PLAN INPUTS AND COMPONENTS ASSUMPTIONS\DATABASES GENERAL DESCRIPTION OF PACIFICORP’S TRANSMISSION SYSTEM PacifiCorp East Balancing Area – Description PacifiCorp West Balancing Area – Description LOAD AND RESOURCE PROCESS RELIABILITY ASSESSMENT AREA PLANNING STUDIES 10-YEAR PLANNING HORIZON ECONOMIC STUDIES COST ALLOCATION
6
Economic Planning Studies Background
The Economic studies identify “significant and recurring” congestion. Stakeholders can submit study requests through the OASIS process. No study requests were submitted in Q1 Next chance to submit requests will be in Q5
7
PAC BIENNIAL TRANSMISISON PLANNING CYCLE 2018-2019
PacifiCorp 8 Quarter Process Time Line PAC BIENNIAL TRANSMISISON PLANNING CYCLE Quarter Date Technical Studies Economic Studies Activities Year Q1 Jan - Mar Data Collection Data Collection for Economic Studies Q2 Apr - Jun Reference Case Development Q3 Jul - Sep Technical Studies to determine System Adequacy Economic Studies to Identify Congestion Q4 Oct - Dec Draft Report on System Adequacy Draft Reporting Year Q5 Data Collection for Re-Study Re-Study Requests Economic Study Second Year Requests Q6 Draft Report Review Draft Re-Study Review Q7 Final Report and Review Q8 Final Transmission Plan approval
8
NERC TPL-001-4 Standard Overview Scott Beyer
9
Overview Areas Background NERC TPL-001-4 Standard
2018 TPL Plan and Status Update 2017 Planning Assessment Results Compliance Monitoring and Enforcement
10
Common Acronyms BES – Bulk Electric System
ERO – Electric Reliability Organization FERC – Federal Energy Regulatory Commission NERC – North American Electric Reliability Corporation WECC – Western Electricity Coordinating Council RE – Regional Entity TPL – Transmission Planning (Standards Family)
11
Why the need of Reliability Standards?
November 9, 1965: Northeast Blackout resulting in loss of power to 30 million people July 13-14, 1977: Blackout of New York City resulting in loss of power to 9 million people and widespread looting, arson and rioting July 2-3, 1996 & August 10, 1996: Western North American Blackouts impacting areas across Western Canada, Western United States and Northwest Mexico, resulting in loss of power to more than 7.5 million people August 14, 2003: Northeast/Midwest Blackout, including Ontario, Canada, resulting in loss of power to 50 million people (largest to date)
12
Actions taken after the 2003 Blackout?
2005: U.S. Energy Policy Act of 2005 creates the Electric Reliability Organization (ERO) 2006: Federal Energy Regulatory Commission (FERC) certified NERC as the ERO; Memorandum of Understanding (MOUs) with some Canadian Provinces 2007: North American Electric Reliability Council became the North American Electric Reliability Corporation (NERC); FERC issued Order 693 approving 83 of 107 proposed reliability standards; became mandatory and enforceable
13
What are the Reliability Standards?
Reliability Standards are the planning and operating rules that electric utilities follow to ensure the most reliable system possible Standards are developed by the industry using a inclusive process managed by the NERC Standards Committee Committee is facilitated by NERC staff and comprised of representatives from many electric industry sectors NERC has eight Regional Entities (RE’s) across the United States and Canada The RE’s are responsible for compliance monitoring and enforcement of the reliability standards PacifiCorp’s RE is the Western Electricity Coordinating Council (WECC)
14
Who develops the Reliability Standards?
FERC Approves/denies following full NERC process NERC Standard Action Request (SAR) Board of Trustees (BOT) approves/denies continent wide (NERC) and regional (WECC) standards Standard Drafting Teams (SDT) Industry involved approval process WECC Oversees regional enforcement of reliability standards Oversees the development of regional standards (more stringent than continent standards) BOT approves regional (WECC) standards Committee only approves Criterion FERC NERC WECC
15
Who are NERC’s Regional Entities?
WECC: Western Electricity Coordinating Council MRO: Midwest Reliability Organization SPP: Southwest Power Pool TRE: Texas Regional Entity NPCC: Northeast Power Coordinating Council RFC: ReliabilityFirst Corporation SERC: SERC Reliability Corporation FRCC: Florida Reliability Coordinating Council
16
Development of NERC TPL-001-4 Standard
NERC standard TPL refers to Transmission System Planning Performance requirements – became fully effective and enforceable on January 1, 2016 The TPL standard revision officially replaced the four individual standards previously in place – i.e., TPL , TPL-002-0b, TPL-003-0b and TPL a TPL was for performance under normal conditions (Category A) TPL-002-0b was for loss of a single BES element (Category B) TPL-003-0b was for loss of two or more BES elements (Category C) TPL-004-0a was for loss of two or more BES elements (Category D or Extreme Events) Overall, the new standard was expanded over the previous standards with increased performance criteria and requirements – it has 65 requirements and sub- requirements
17
TPL-001-004 Standard Requirements
R1 – Each Transmission Planner and Planning Coordinator shall maintain system models within its respective area for performing the studies needed to complete its Planning Assessment… R2 – Each Transmission Planner and Planning Coordinator shall prepare an annual Planning Assessment of its portion of the BES… R3 – For the Steady-State portion of the Planning Assessment, each Transmission Planner and Planning Coordinator shall perform studies for the Near-Term and Long-Term Transmission Planning Horizons… R4 – For the Stability portion of the Planning Assessment, each Transmission Planner and Planning Coordinator shall perform the Contingency analysis listed in Table 1… R5 – Each Transmission Planner and Planning Coordinator shall have criteria for acceptable Steady-State voltage limits, post-Contingency voltage deviations, and transient voltage response for its system… R6 – Each Transmission Planner and Planning Coordinator shall define and document, within their Planning Assessment, the criteria or methodology used in the analysis to identify System instability… R7 – Each Planning Coordinator, in conjunction with each of its Transmission Planners, shall determine and identify each entity’s individual and joint responsibilities for performing the required studies… R8 – Each Transmission Planner and Planning Coordinator shall distribute its Planning Assessment results to adjacent Planning Coordinators and adjacent Transmission Planners… Each Requirement has multiple Sub-Requirements – 57 in total
18
Example sub-requirements of TPL-001-4
Spare Equipment Strategy R2.1.5 requires an annual study of impacts for the loss of major equipment, such as power transformers, that do not have a spare unit available and have a lead time of one year or more – studies shall be performed for the P0, P1 and P2 categories shown in Table 1 with the identified equipment out of service Short Circuit Analysis R2.3 requires a short circuit analysis to be conducted annually within the Near-Term Transmission Planning Horizon to determine if circuit breakers have interrupting capability for faults they would be expected to interrupt R2.8 requires a Corrective Action Plan to address circuit breakers subject to short circuit interrupting duty levels that exceed their equipment rating Non-consequential Load Loss R2.7.2 cites that if situations arise that are beyond the control of the Transmission Planer or Planning Coordinator that prevent implementation of a Corrective Action Plan in the required timeframe, it is permitted to utilize Non-Consequential Load Loss and curtailment of firm Transmission Service (≤ 75 MW) to correct the situation that would normally not be permitted in Table 1 – this grace period is in place for five years from the date the standard was approved in 2015 Protection System Studies (R3.3.1) R3.3.1 requires simulating the removal of all elements that the protection system and other automatic controls are expected to disconnect for each Contingency without operator intervention – includes RAS and other protection systems with automatic control
19
PacifiCorp’s TPL Study Schedule and Status
TPL Study Status Study Plan draft completed April 24, 2018 Study Methodology draft completed May 31, 2018 10 Base Cases completed for Steady-State analysis in June 2018 – four for PACE and six for PACW PACW Bases Cases – 2019 summer peak, winter peak, 2020 light spring, 2023 summer peak, winter peak, and 2028 summer peak (Long-Term) PACE Base Cases – 2019 summer peak, 2020 light spring, 2023 summer peak and 2028 summer peak (Long-Term) 2 Base Cases for PACE and PACW to perform Stability Analysis – 2023 summer peak, 2020 light spring Simulations are currently being run for Steady-State base cases Stability analysis will be performed based upon the results of the Steady-State simulations Short-circuit study is completed Analysis for extreme events, sensitivity studies and loss of major equipment without spares will proceed at the conclusion of the Steady-State analysis Study team is targeting November 2018 to deliver preliminary reports for PACE and PACW
20
Compliance Monitoring and Enforcement
WECC, with delegated authority from NERC, is the Regional Entity responsible for compliance monitoring and enforcement for the Western Region of the United States WECC provides the environment for development of reliability criteria, occasional regional variances, and coordination of the operating and planning activities of its members NERC is the driving force for developing new standards through its process of an Open Call for Standard Drafting to get team members from its Regional Entities memberships – FERC reviews and approves new and modified NERC Standards WECC provides audit oversight for compliance with NERC Standards for Critical Infrastructure Protection and Operations and Planning Standards NERC has a three year auditing cycle for its TPL Standards – the next audit of PacifiCorp’s TPL compliance is scheduled for 2019
21
NERC TPL-001-4 Standard Overview
Questions?
22
Local Area Studies Update - PACW Scott Beyer
23
Time-line 5-yr studies - West
Study Area State Existing Study Completion Date Update Study Status Comments Crescent City CA Feb-17 Grants Pass OR Dec-15 Hood River Nov-15 Pendleton/Hermiston/Enterprise May-17 Walla Walla/Wallula WA Dec-09 85% Roseburg Sep-10 40% Portland Mar-11 Dalreed/Arlington/Sherman County 100% Completed May 2018 Klamath Falls May-11 Lakeview/Alturas Coos Bay Aug-11 Attachment K Kick-Off September 2018 North Oregon Coast Sep-17 Yakima Dec-11 95% Medford Sep-12 Willamette Valley Dec-12 Junction City/Cottage Grove Central Oregon Mar-13 Yreka Dec-14
24
Attachment-K Q3 Public Meeting Coos Bay Area Transmission Planning Study Kickoff Area Planner: Adam Lint Presented by Larry Frick September 13, 2018 Choose from three different title slide designs by selecting “New Slide.” These slides are suitable for business and community presentations.
25
Sub-Transmission Planning Studies
Pacific Power study plan Service Area is divided into 17 study areas The studies are designed to predict the future electrical system requirements about 5-7 years out. The goal is to update each about every 36 months. This is intended as an agenda slide template. Choose from different slide layouts by selecting “New Slide.”
26
Pacific Power Study Areas
This is intended as an agenda slide template. Choose from different slide layouts by selecting “New Slide.”
27
Inputs to a Planning Study
New load requests (L&R) Customer transmission & substation data Generation increases and operations plans Potential system modification data Two restrictions to public access Maintaining confidential customer information Maintaining FERC & WECC codes of conduct This is intended as an agenda slide template. Choose from different slide layouts by selecting “New Slide.”
28
Coos Bay Area Topology Main Grid Sources
230 kV Alvey-Fairview Dixonville-Fairview Common Corridor Fairview-Isthmus 115 kV Tahkenitch-Fairview Coos-Curry system downstream via BPA Rogue and BPA Bandon
29
Coos Bay Area Topology Northern Portion
kV Isthmus source Distribution substations Coos River South Dunes Lockhart Empire State Street Jordan Point Normal open points At Empire facing State Street, switch 2C14 At Lockhart facing Red Dike Tap, breaker 2C6 Both SCADA controlled Normal Open Points
30
Coos Bay Area Topology Southern Portion
Pacific Power subs Coquille Myrtle Point Norway Tie Bandon (Pac. portion) Foreign subs Fairview Norway CCEC subs
31
Coos Bay Area Loads (Pacific Power)
Based on most recent load projections Summer ~ 94 MW Winter ~ 150 MW Overall growth rate 0.2% Winter limited Overall load factor 51% This is intended as an agenda slide template. Choose from different slide layouts by selecting “New Slide.”
32
Coos Bay Area Transmission Planning Study
Expected completion 2019 Q2 Questions or Input requests? This is intended as an agenda slide template. Choose from different slide layouts by selecting “New Slide.”
33
Local Area Studies Update – PACE Jake Barker
34
Time-line 5-yrs studies – East
Study Area State Last Studied Update Ogden UT Aug-14 65% Complete Utah (Southwest) Dec-14 90% Complete Pavant Feb-15 95% Complete Goshen ID Jun-15 Powder River WY Nov-15 Completed Montpelier Feb-16 Utah Valley Apr-16 Honeyville/Malad May-16 Grace Jul-16 Smithfield Price Utah (Southeast) Jun-16 Vernal Nov-16 Sigurd Feb-17 Presented Q5 North Salt Lake Wyoming (Southern) Mar-17 Salt Lake Valley May-17 Presented Q6 Tooele Jun-17 Wyoming (West) Oct-17 Presented Q8 Park City/Midway Big Horn Nov-17 Nebo Apr-18 Presented Q2
35
Montpelier, Idaho Study
Sachith Abayakoon Montpelier, Idaho Study
36
MONTPELIER, IDAHO AREA STUDY
Primary Sources Ovid – kV 138 kV source from Oneida Reactive Support to the Area Sage – kV 69 kV source from Naughton Generation Serves 46 kV Loads 15 area substations in three different states: Idaho, Utah and Wyoming. The total area is approximately 1,900 square miles. Includes Bear Lake recreational area. Sachith Abayakoon
37
Load Growth Area Loading Growth
Summer of 2017 area loading was at 29 MW Winter of area loading was at 22 MW Growth Average area growth has been about 2.1% Are there any questions?
38
Powder River, Wyoming Study
Sachith Abayakoon Powder River, Wyoming Study No changes to previous study identified.
39
Attachment K 2018-19 Biennial Planning Cycle Q4 Public Meeting
December, 2018 PacifiCorp
40
Q & A Session Contact Information – Link to PacifiCorp OASIS: For Attachment K related comments\questions, address your requests to:
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.