G R E A T L A K E S B U I L D E R S A Re-construction Company Specializing in Structural Remediation and Alterations
2
Beam and Column Replacement
3
Beam and Column Replacement
Client: Post Oak Property Management Location: Racine Ave., Chicago Building Type: 3-unit Apartment Building Problem: Deteriorated wood beams and columns with deflection in beams. Corrective Action: Shored joists in basement and removed existing wood beams and columns. Jacked up joists to level position. Replaced wood beams and columns with steel. Set columns in steel reinforced concrete footings.
4
Beam and Column Replacement
Shored joists Saw cut slab and installed steel reinforced concrete footings
5
Beam and Column Replacement
Before After
6
Beam and Column Replacement
After Before
7
Beam and Column Replacement
After Before