Presentation is loading. Please wait.

Presentation is loading. Please wait.

IGG Agenda – 18th September 2008

Similar presentations


Presentation on theme: "IGG Agenda – 18th September 2008"— Presentation transcript:

1 IGG Agenda – 18th September 2008
Minutes from last IGG meeting Review of Action Items CER Update – 11.05 Gemserv update – 11.15 Market Operations Update – 11.25 Address Data Standards Update Retail Market Design Service Update Market Design Update Next Steps – 1

2 Minutes from IGG meeting – 14th August 2008

3 IGG Action Items Closed IGG Actions IGG Actions carried forward:
Updated IGG Action List issued in advance of meeting 30 Actions closed since last IGG meeting: IGG Actions carried forward: Owner August 14th Sept 18th Suppliers 7 2 RMDS 19 15 MRSO 1 ESBN 4 3 CER Total 35 23 3

4 CER Update 4

5 Gemserv Update 5

6 Market Operations Update
6

7 Retail Market Design Service Update
C. Madden, RMDS 7

8 RMDS Update Agenda Recalculation of Estimates
Updating of Site Addresses 8

9 RMDS Update Recalculation of Estimates
The changes to SAP to provide for Change Request CR221 were released to Production on September 16th. An was released outlining the details of the functionality delivered and/or deferred items 9

10 ESB Networks – Amending Site Address
Historically (June 2008) all address changes were accepted. This has led to: Duplicate addresses The Meter Reader unable to find a meter at a site address Acceptance of amended site addresses is now strictly controlled by the Bureau The following are some of the procedures used for verifying the site address: Find out if the site address already exists Is the site a one off or part of a development Research the address (New Connections) Determine if outside verification is required (Planning Authority) Carry out a site visit Access to main switching Board (Management Company) Access to the Customers premises (Customers Electrician) Is the address Commercial or Domestic 10

11 Supplier Impacts As a result of the new procedures the following has happened: Rejection rates have increased considerably Suppliers don’t know why their addresses are being rejected as there are not enough Reject Reason codes Multiple requests to amend the same site have been received Multi metering sites and Housing Estates are most problematic 11

12 Address Amendment Examples
This example reflects no address change, but still accepted and entered by the supplier. 12

13 Address Amendment Examples
This address was rejected as there is already a unit six existing at the same address 13

14 Address Amendment Examples
This example illustrates the varying spelling differences between supplier requests and what is in the Regional Structure. 14

15 Address Amendment Examples
This was rejected as there is already a no 1 in the system 15

16 Address Amendment Examples
This example shows a second request to alter addresses as the original change was made on the 7/7/08. How often do we change the same address. 16

17 Site Address Interactions / Dependencies
Management Company Engineering Officer Developer Address Setup Legal Documents Management Agreement Supplier Wiring Cert Planning Authority Developers Agreement Supply Agreement Customer Connection Agreement ESB Networks Electricity Bill Wiring Cert address has to match exactly the Connection Agreement address Bank 17

18 Address Bureau Concerns
Developers are looking to change addresses after they have been agreed with the Planning Authority and after customers have moved in. There is nothing to stop the Developer from making address change requests. Huge cost in readdressing a whole development. Planning authorities are not being consulted about the Developer address changes. ESB Networks now have concerns over the legality of documentation. 18

19 Discussion Requests & Market Change Requests
Cormac Madden, RMDS 19

20 Discussion Request Discussed at the August 28th Conference call.
DR Addition of Vulnerable Customer data deletion flag on 102 V.2 Discussed at the August 28th Conference call. All were in favour of the flag being included on the 102 message All agreed that medical institution could be added. It was agreed that there was no need to display the delete flag on the 102P. Approval to progress to MCR 20

21 Market Change Request MCR 0080 – Remove Meter Point Status Field from 017 Message Dates back to early 2006 Approved but not Implemented Not on Current Outstanding List Should this MCR be included on the MCR prioritisation list? 21

22 Market Change Request MCR 0165 – Recalculation of Estimates
Released Tuesday 16th September at 14h00. Release note issued Design is somewhat different to MCR Amendments to MCR will be proposed Recalculation due to meter removal readings is not yet operational. A supplementary release is planned. 22

23 Discussion Request MCR 0167 - Delivery of 106d message to EirGrid
Approval requested 23

24 Discussion Request Circulated to the market Approval Requested
MCR 0168 – Addition of 331MM to notify of QH meter removal during QH de-energisation with meter removal process Circulated to the market Approval Requested 24

25 SoLR Working Practice 17 Purpose of Working Practice 17
Provide Alternate Suppliers with an opportunity to acquire the Defaulting Supplier’s Customers Provide a clear mechanism by which ESB Networks MRSO and MO can hand over clean data to the SoLR at the end of day 19 (5 day communication period + 14 day CoS period). Provide guidelines on how to handle the following scenarios: Present Reading < Previous Reading Large Debits 25

26 SoLR Working Practice 17 26

27 SoLR Working Practice 17 27

28 SoLR Working Practice 17 28

29 SoLR Working Practice 17 Issues
How does the SoLR and Alternate Suppliers recover SoLR costs A customer cannot query an SoLR reading 10 months after the SoLR Direction date How does the SoLR / Alternate Supplier identify SoLR readings 29

30 Action 367: MPRN/Name & Address Web Service
Investigated using existing web service for this purpose. Finding: a new web service is required. Reasons: Existing web service is not designed for CoS volume Modification to information content required RMDS will develop a DR for a new web service 30

31 Release Planning - Outstanding MCRs
MCR Number MCR Description MCR 0033 Sending 306 for all NQH De-energisations MCR 0034 Sending 307 for all NQH Re-energisations MCR 0060 New Message to contain customer details on conversion from NQH to QH 1.1 MCR 0062 New rules for MPD 1 - CoS MCR 0069 Irish language character set MCR 0078 Add Validation to use of Registered Company Number MCR 0081 Suppliers Extranet shows Non billable devices where installed MCR 0087 Exchanged Meter Ref amendment to provide only for like for like exchanges MCR 0126 Rejection of change of usage requests DG5 to 1 or 2 where MIC is greater than 30 v1.0 MCR 0127 Decouple Connection Agreement and CoS where no COLE MCR 0130 Extra validation check required at creation of 306 and 307 messages v2.0 MCR 0152 Vulnerable Customers - Phase 3 MCR 0154 Versioning of 341 message MCR 0157 Proposal to add Acceptance / Completion / Cancellation message to Meter Works Design Completing Design For TUoS New market rule Irish Language Act Reduce residual CA on CoS issue Better mkt function Speed up response Automation Automation + better function (Impose 20 day time limit on replacement of CoS reads) 31

32 Release Planning - Outstanding MCRs
MCR Number MCR Description MCR Number MCR Description MCR 0161 Increasing the threshold for connection agreements in CoS process MCR 0162 SoLR process MCR 0163 Increase in tolerance levels for NQH Meter Reading Validation 32

33 Next Steps Proposed Diary dates for IGG meetings in 2008: 30.10.2008
Proposed dates are on Calendar of Events on RMDS website 33

34 Next Steps Propose to continue with conference call every two weeks:
Call details have new contingency PIN No: Number: PIN : Contingency number remains: New PIN: 80490 34

35 Thank You 35


Download ppt "IGG Agenda – 18th September 2008"

Similar presentations


Ads by Google