Download presentation
Presentation is loading. Please wait.
1
C75 Cryomodule Project Outline
G. Ciovati for the SRF Department 08/03/2017
2
Acknowledgments SRF R&D R. Rimmer, F. Marhauser, J. Guo Engineering
G. Cheng, E. Daly, F. Fors, C. Hovater SRF Cavity Fab. Group L. Turlington, B. Clemens, J. Henry, S. Williams Machine Shop D. Combs, R. Martin, J. Dail SRF Cavity Prod. Group A. Anderson, K. Davis, C. Dreyfuss, J. Follkie, D. Forehand, T. Harris, C. Johnson, R. Overton, T. Sessoms, A. Wildeson SRF Test and Meas. Group N. Brock, C. Wilson SRF CM Assembly Group J. Fischer, R. Legg, M. McCrea Accel. Div. Management A. Freyberger, A. Hutton, A. McEwen, G. Myneni
3
C75: a more efficient way to refurbish CMs
Minimal changes to current C50 module/process Change cells to increase gradient and Qo Preliminary Design Review on Jan 21st, 2016 endorsed the project
4
C75 draft specifications
Cavity Parameters Unit C75 Energy Gain MeV 75 Number of cavity cells 5 Cavity active length m 0.4912 R/Q (β = 1) Veff2/(ω*W) Ω 525.4 Eacc MV/m 19.07 ± 10%, spread 21 MV/m max. Maximum beam current μA 460 Beam loading kW 4.31 (4.74 max.) Design 2.07 K 8e9 Pcav W 20.9 (25.3 max.) Qext,opt – no microphonics 3.9e7 Peak-to-peak microphonics Hz ± 20 Qext,opt 2.8e7 Design Qext 1.8 – 4.3e7 Required forward RF power 6 (7.6 kW, ~ 1 dB added for klystron power) ~21 W/cavity, ~200 W cryomodule total heat load <Total HL>C50 ~190 W
5
C75 cavity design Cell shape is a “low-loss” type, designed for high-current FEL Distance end-cell-to-FPC optimized for Qext ~2×107 Stiffening rings added to obtain the same stiffness as C50 cavity
6
E.-M. parameters C20/C50 cavity C75 cavity Cavity Parameters Unit
Original CEBAF/ Cornell (OC) High Current (HC) Cavity active length m 0.500 0.4912 R/Q*G/cell Ω2 26441 28961 Epk/Eacc 2.83 2.45 Bpk/Eacc mT/(MV/m) 4.62 4.18 kcc % 3.15 + 10% - 13.6% - 9.4% = C20/C50 cavity C75 cavity
7
Cavity material Cells made from Nb discs sliced from an ingot
Technology pioneered in 2004 at JLab through a CRADA with CBMM, Brazil Medium purity (RRR= ) ingot is a good compromise between lower cost and performance Many single- and multi-cell cavities built, processed and tested at JLab quench field 1.5 GHz (OC shaped cavities) C75 spec. C75 spec.
8
Ingot Nb technology validation
Eleven 1.3 GHz 9-cell cavities built at RI, Germany. Processed and tested at DESY 7 cavities installed in Cryomodule XM-3 resulted in 45% lower RF heat load than standard fine-grain, high-RRR cavities Nb from W.C. Heraeus, Germany, RRR ~ C75 spec.
9
Material for C75 prototype cavities
Cavity Ingot SN Supplier RRR Ta content (wt. ppm) 5C75-001 2370-5 CBMM 118 1350 5C75-002 2667-5 114 670 5C75-003 NC-1654 Tokyo-Denkai 496 29 Prototype single-cell cavities test results 2370-5 2667-5 NC-1654 Medium purity Nb ingots Ingot Nb disc
10
C75 prototype cavities Standard fabrication techniques (deep-drawing, machining, electron beam welding) Improved cleaning of parts in preparation for welding Inside/outside equator welds 5C75-001 5C75-002 5C75-003 70 mm CBP 95 mm BCP 1:1:2 30 mm EP 35 mm EP 600 °C/ 3 h vacuum anneal 800 °C/ 3 h vacuum anneal 20 mm EP HPR RF Test Local grinding 30 mm BCP 1:1:2
11
Prototype cavity performance
Single-cavity test Cavity pair configuration (HOM elbows and load, dog-leg, RF window, top-hat) Losses due to metallization in RF window Cavity pair type C50 C75 Lorentz force detuning [Hz/(MV/m)2] ~ ‒3 ~ ‒5
12
HOM analysis No HOM issues
TE111 and TM110 Qs measured on cavity pair at 4 K Results are conservative since dog-leg + top-hat is not as broadband as in the cryomodule configuration to damp modes below 1.9 GHz = (R/Q)calc Qmeas No HOM issues
13
Weld defects The gradient performance of the prototype cavities was limited by weld defects Malfunctioning components in the EBW machine have been replaced 1 mm 1 mm 1 mm 5C75-001, cell 4 5C75-002, cell 4 5C75-003, cell 4
14
Tuner The original tuner will be used
Machining the profile of the cell holder clamps to fit new cell shape Replacement of some components with high remanent field Installation of new magnetic shield (Cryoperm 10®, 1 mm thick) Cell Holder Assy Swivel (Inside Yoke Assembly) Cell Holder Clamp New magnetic shield
15
Tuning sensitivity Tuning sensitivity measured with tuner and magnetic shield assembled both on a C20/C50 and a C75 cavity Linear stiffness of cavities also measured C50 C75 Tuning sensitivity (kHz/mm) 370 ± 40 470 ± 80 Stiffness (klbf/in) 24 ± 2 22 ± 3
16
Microphonics Simulations show the presence of mechanical modes of vibration of C50 cavities with swaying of HOM waveguides near 60 Hz Supports were designed to restrain the HOM waveguides to tuner cell holder Hammer tests performed on C75 pair showed higher mode damping with support brackets installed Accelerometer HOM support
17
FPC transition waveguide
Operation with up to 8 kW forward power Thermal performance demonstrated in FEL module FL02 Analysis required to confirm heat loads and thermal strap size to handle higher dynamic heat load than for C50 Re-use copper-plated SS FPC transition waveguide from existing CM and change heat station location Not done for C75 pair in C50-13
18
Reducing CWVF trips Low conductance Low H2 pumping
Courtesy of M. Drury
19
RF Power Identical to the operational R100 installation 8 kW Klystron
Upgraded HV Power Supply 8 kW Circulators New HPA controls Digital LLRF control for operation with higher Qext and LFD
20
unit cost (FY16 M$ Direct)
Presented at Director’s Review on Jan. 21st 2016 and JLab’s upper management on Feb. 5th 2016 All costs in FY16 DIRECT Dollars From Accelerator "STAY Treat" July2015) - see Slide 6 # Cav cells /cav cav length m Active Length m fill factor % MV volts /cav (MV) gradient (MV/m) klystron power unit cost (FY16 M$ Direct) RF Cost Total Cost FY16 Direct MV (gain) V(gain) /$ C50 8 5 0.5 4 48.1 50 6.25 12.5 6 1.51 20 13.3 C75† 75 9.4 18.8‡ 1.91 45 23.6 C100‡ 7 0.7 5.6 64.4 100 17.9‡ 13 4.77 70 14.7 Update - January 2016 *RF Cost 1.23 16.3 1.73 0.77 2.50 18.0 4.30 1.56 5.85 12.0 †New cells or new processing required to achieve higher Q’s and gradients ‡Digital LLRF required What changed from August 2015 to January 2016 ? Addition of RF to C100 & C75 (assumes C50 still usable) Updated Rates (Budget Office ) & change TDIII to TD II (match AWP) Improved estimate for Fabrication and other costs What is not included ? One time R&D costs Wave Guide Vendor Development + 8 Wave Guides Courtesy of A. McEwen
21
Issues and open questions
Achieving Q0-spec in cryomodule Not successful in C50 program Main issues: Shielding from or eliminating remanent magnetic field close to the cavity Reduce/eliminate losses from metallization of cold window Degaussing equipment for components, up to 66 kA/m Will try degaussing of fully assembled cryounit in FEL04 New magnetic shield close to the cavities added in C50-7B (aka C50-13)
22
Issues and open questions
Cavity manufacturing New electronics and updated controls for EBW machine Sent RFQs to cavity manufacturers Critical spares: there are no spares HOM loads New HOM prototype successfully designed and built Need to build small inventory Applies to C50 rework
23
Issues and open questions
Critical spares: FPC transition waveguide Very limited number of spare FPCs in inventory, none released for production Forced to re-use FPCs that are of fair or poor quality contributes to 2 K dynamic heat load Currently no suppliers available that can produce new copies of this assembly Applies to C50 rework Need to develop new suppliers Vendor development + 8 WGs: $360k (direct, FY16)
24
Issues and open questions
Cryogenic operation If Q0-spec will be met, the heat load of C75 CM will be within ~10% of that of a current C50 CM No changes expected in terms of hardware (heaters) or controls (CHL heat management software)
25
Issues and open questions
Expectations for C75 pair from commissioning of C50-7B (aka C50-13): Operation of one cavity at 19 MV/m Verification of tuner operation Verification of new magnetic shields (all cavities) A decision is missing on next module rework Disassembly of old module and fabrication of 8 cavities should start NOW to be able to deliver a C75 module in August 2018
26
References Cavity Shape Cavity Material
H. Wang, R. Rimmer and G. Wu, “Elliptical Cavity Shape Optimization for Acceleration and HOM Damping”, Proc. PAC’05, Knoxville, TN, 2005, p Cavity Material P. Kneisel et al., Nucl. Inst. Meth. Phys. Res. A 774 (2015) 133–150. G. Ciovati, P. Dhakal and G. R. Myneni, Supercond. Sci. Technol. 29 (2016) P. Kneisel, “Progress on large grain and single grain niobium - ingots and sheet and review of progress on large grain and single grain niobium cavities”, Proc. SRF’07, Beijing, China (2007) p. 728. G. Ciovati, P. Kneisel and G. R. Myneni, “America’s overview of superconducting science and technology of ingot niobium”, in Proc. of the Symposium on the Supercond. Sci. and Technol. of Ingot Niobium, AIP Conf. Proc (2011) p. 25. G. Ciovati, P. Dhakal, P. Kneisel and G. R. Myneni, “Summary of performance of superconducting radio-frequency cavities built from CBMM niobium ingots”, in Science and Technology of Ingot Niobium for Superconducting Radiofrequency Applications, AIP Conf. Proc (2015) W. Singer et al., Phys. Rev. ST Accel. Beams 16, (2013). J. Sekutowicz et al., Phys. Rev. ST Accel. Beams 18, (2015).
27
References Cavity Fabrication and Tests
G. Ciovati et al., “Experience with the fabrication, processing and testing of the prototype “C75” 5-cell cavities”, JLab Tech Note TN (2017). R. Rimmer et al., “Upgraded cavities for the CEBAF cryomodule rework program”, presented at SRF’17, Lanzhou, China (2017). Microphonics, tuning sensitivity K. Davis and T. Powers, “Microphonics Evaluation for the CEBAF Energy Upgrade”, JLab Tech Note TN-05-40, 2005. G. Ciovati et al., “Tuning sensitivity and stiffness of C20/C50 and C75 cavities”, JLab Tech Note TN (2017). Low Q issue M. Drury et al., “Summary report for the C50 cryomodule project”, PAC 11 Proc., pp (2011). R. L. Geng et al., “Pursuing the origin and remediation of low Q0 observed in the original CEBAF cryomodules”, Proc. IPAC’14, Dresden, Germany (2014) p G. Ciovati et al., IEEE Trans. Appl. Supercond. 27 (4) (2017)
28
Backup slides
29
RF Power Imax = 460 µA (max, beam loading), target Q0 = 8e9, HC 5-cell cavity R/Q= Ω Eacc = MV/m for 75 MeV Existing klystrons work at 8 kW just as for R100 Allow waveguide losses and linear working regime (-1dB) = 6.4 kW 8 kW 6.4 kW min. Measured peak microphonics for SL20 in CEBAF ( Hz, avg Hz) Qext,opt = 20 Hz Qext,opt = 25 Hz Qext,opt = 20 Hz range: e7
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.