1
Improvements for 2016 & 2017 Todd Harris Maintenance Manager
Status of the Property Improvements for 2016 & 2017 Todd Harris Maintenance Manager Buildings 1,2,3 Elevator Cab Remodels
2
2016 HOA Improvements New Roofs B4 Walkway B1 Ramp 5 Stair Towers
3
2016 HOA Improvements B3 Pool Exterior Deck Tile
4
2016 HOA Improvements B3 Pool Men's Room B3 Sauna
5
B3 Exercise Room Flooring
2016 HOA Improvements B3 Exercise Room Flooring
6
2016 HOA Improvements B4 Pool & Spa Resurface
7
2016 HOA Improvements B4 Snow Retention
8
2016 HOA Improvements Window Replacements – Both Pool Areas Spandrel Repairs – B1, B2, B3 Carpet Replacement – B1 Halls Hedges – Front of B4
9
2016 HOA Improvements New Vehicles Plow Truck Bobcat Minivan
10
2016 HOA Improvements Landscaping
11
2016 HOA Improvements The Hub Bathrooms
12
Bathrooms 2nd & 3rd Floors New Doors & Wood Trim on 2nd Floor
2016 CC & FB Improvements Conference Center Bathrooms 2nd & 3rd Floors New Doors & Wood Trim on 2nd Floor New Sound System
13
Hub Bar & Service Window
2016 CC & FB Improvements Hub Bar & Service Window Spencer's New Buffet
14
2017 CC & FB Improvements New Tent Painting – 3rd Floor Sunshades – 3rd Floor New Kitchen Floor
15
2017 HOA Projects Resurface B4 Pool & Hot Tub Deck Emergency Power – B1 Continue Energy Savings Program Total Boiler Rebuild – B2 & B3
16
2017 Landscaping – Phase 2
17
B1 Walkway
18
B1 Walkway Apr 24 – Construction Begins Jun 15 – Set Vertical Steel
Sep 7 – Timber Frame Oct 10 – Windows & Doors Dec 1 – Final Inspection