Lifting Operations on Construction Sites
A presentation to Merseyside & Cheshire Construction Safety Group on 12th March 2018 by: John Ellis BSc(Eng),CMIOSH,CMaPS
2
Most common ways of lifting:
Mobile Cranes Telehandler Excavator Hiab
3
Types of Mobile Crane Truck-mounted crane All-terrain crane
“City” crane Self-erecting tower crane
4
Truck-mounted crane
5
All terrain crane
6
“City” Crane
7
Self-erecting tower crane
8
Summary of suitability
Truck mounted-long wheelbase, large turning circle All terrain-more compact, all wheel steer, highly manoeuvrable City crane-compact, able to operate in limited headroom areas Tower crane-large working radius directly adjacent to structures
9
Use crane spec book to decide what size of crane required
11
What factors determine the size of crane needed ?
Maximum weight of load to be lifted (e.g m radius) Maximum working radius (e.g.37m lifting 1.2 tonnes) Angle of jib in restricted headroom locations
12
Find out and what room it will take up
13
Imposed Loadings Must be clearly shown on lifting plan as both point load and pressure(e.g. point load=25KN,pressure of 25KN/m2) Should indicate size of pads being used(typically 1m diameter pads have an area of 0.7m2) Tables can be used to get approx. loads, or crane hire company will be able to provide more precise detail
14
Ensure ground bearing pressures acceptable
Provided details of imposed loadings to the site (in writing) Obtain written confirmation from the site that the ground is capable of withstanding the loads May need CBR tests to be undertaken May need additional measures to reduce pressures to an acceptable level e.g. steel plates,sleepers,mats
15
Produce a detailed lifting plan
16
Lift plan should indicate:
Crane access and locations Crane size and lifting equipment Berthing study (rigger spread) Imposed loadings Position of delivery wagons Directions of slew Positions of new/existing buildings Location of any specific hazards
17
Set the crane up in accordance with the plan
18
Planning must be done by a competent person (appointed person)
19
Supervision Supervision done by the appointed person
Or, if not, then by a qualified crane supervisor Directing the crane is done by a qualified banksman who agrees a means of communication with the crane driver Slinging is undertaken by trained slingers Crane driven by suitably competent operator
20
Summary Select suitable type of crane
Select right size of crane for the job Understand how a crane works Ensure all involved in the planning and operation are competent
21
Don’t have the required Skills,Knowledge,Experience ?
You must arrange for a “Contract Lift” A reputable crane hire company will visit the site and do all the necessary planning They will provide relevant documentation for the lift including a lift plan On the day they will provide crane driver and crane supervisor/banksman They will also provide appropriate lifting tackle(chains,slings,etc.)
22
What can go wrong? Crane exceeds safe working capacity
SWL of lifting accessories exceeded Imposed rigger loadings exceed ground bearing capacity Structural failure of crane and/or lifting accessories (due to lack of maintenance) Operation in adverse weather conditions Communication failures
26
Waikato Crane Incident
27
Telehandlers
28
Requirements Driver must have appropriate skills, knowledge & experience(e.g. CPCS for type & size of telehandler) Operate on firm & level ground when placing/removing loads (e.g. designated stoned up area) Suitable reversing mirrors & cameras Use of stabilizers when required
29
Excavators
30
Types of excavator Back-hoe excavator Mini excavator Tracked excavator
31
Requirements Driver to have necessary skills, knowledge & experience for type & size of excavator Driver to have suitable knowledge & training in attachments (e.g. manual quick hitch, semi-automatic quick hitch, automatic quick hitch Suitable reversing mirrors and cameras to enable driver to see persons at rear
32
Hiabs
33
Requirements Driver with suitable skills, knowledge & experience
Set up on firm & level ground capable of withstanding rigger loadings All riggers to be fully extended
34
Statutory Requirements for Lifting Plant
LOLER Regulations require that all plant used for lifting has undergone thorough examination & inspection by a competent person within previous 12 months …..but if being used for lifting persons (e.g. man-rider cage attached to forklift) then must be within previous 6 months
35
Lifting tackle Chains (e.g. 2 legged 10mm chains,SWL 4.25 tonnes)
Web slings or wire slings Grabs of lifting booms Lifting clutches (e.g. modform lifters) All must be maintained in good condition and should be visually inspected each day before lifting operations commence
36
Using chains or slings in choked position
37
Requirements Capacity of the choked chains must be downrated by 20%
i.e. 2 legged Chains with SWL of 4.25 tonnes can only be used to lift a maximum load of 3.4 tonnes
38
Angle between chains/straps should not exceed 90 degrees
39
Statutory Requirements
All lifting accessories to have undergone thorough examination and inspection by competent person within the previous 6 months (as per LOLER Regulations)
40
Guidance BS7121 Part 3:Code of Practice for Safe use of Cranes
41
BS7121 Overview
42
Guidance on best practice for:
43
Lift Categories
44
Lift Categorisation
45
Contract Options
46
Construction Plant-hire Association www.cpa.uk.net
47
.
48
HSE Guidance L113 :Safe Use of Lifting Equipment ACOP
L22:Safe Use of Work Equipment INDG290:Lifting Equipment at Work-a Brief Guide INDG422:Thorough Examination of Lifting Equipment HSG144:Safe Use of Vehicles on Construction Sites HSG150:Health & Safety in Construction
49
Any questions ?