1
A r d m o r e T r a n s i t C e n t e r
March 10, 2015
2
VIDEO PLACEHOLDER: https://youtu.be/57rvylN_EXM
3
Existing Station SUBURBAN SQUARE ANDERSON AVE RUBY’S LOT
COULTER AVE LOT ARDMORE WEST MUNICIPAL LOT STATION SEPTA LOT MUNICIPAL LOT RITTENHOUSE PL STATION AVE STATION PLACE LANCASTER AVE
4
Phase 1 – Station Facilities: Scope
ADA Accessible Station – Ramps, Elevators High & Low Level Platforms Station Building/Shelter and Canopies Site Utilities and Stormwater Management Garage Foundations Catenary Structures Streetscape
5
Phase 2 – Parking Garage : Scope
500 Space Parking Garage 5 Stories Bus / Intermodal Connections Limited Commercial Space
6
Phase 1 – Station Facilities: Site Plan
COULTER AVE RUBY’S LOT COULTER LOT (AMTRAK) ARDMORE WEST MUNICIPAL LOT Future Parking Garage STATION AVE SEPTA LOT MUNICIPAL LOT ANDERSON AVE STATION AVE LANCASTER AVE
7
Phase 1 – Station Facilities: South Inbound Elevation
8
Phase 1 – Station Facilities: Station Building Plan
9
Phase 1 – Station Facilities: Tunnel Cross Section
10
Phase 1 – Station Facilities: North Outbound Elevation
11
Phase 2 – Parking Garage: Site Plan
12
Phase 2 – Parking Garage: View Looking Down Station Place
13
Phase 2 – Parking Garage: North Elevation
14
Phase 2 – Parking Garage: Ground Tier Plan
BUS STOP / LOADING BUS TRAVEL
15
Amtrak Work: Prior to Station Construction
16
Project Schedule Design complete by July 1, 2016
Finalize agreements and easements Amtrak to advance catenary work: 6-12 month anticipated duration SEPTA bid cycle – 6 months Construction – 2-3 year duration Station remains in operation Parking closed during construction 16
17
THANK YOU