Download presentation
Presentation is loading. Please wait.
1
ELC 347 project management
Day 17
2
Agenda Projects 3 & 4 in Project Essentials
Integrative Project Part 3 Not Corrected Yet Part 4 Due Nov 10 (page 276) Any of the first five sections can be resubmitted for rescoring prior to finals week. The recorded score will the average of the original score and the score on the resubmitted section. Assignment 6 Posted Problems 1-7 on Page 272 & 3 Due Nov 6, 1008 Projects 3 & 4 in Project Essentials Nov 6 will be group work for part 4 of IP project
3
Schedule for rest of semester
Nov 6 Group Work Assignment 6 due Nov 10 Chap 9 IP part 4 Due Nov 13 Chap 10 Nov 17 Chap 11 Assignment 7 due Nov 20 Group work Nov 24 Quiz 3 IP part 5 Due Dec 1 Project s 5 & 6 Dec 4 Group Work Assignment 8 due Dec 8 Chap 12 IP Part 6 due Dec 11 Chap 13 & 14 Dec 10 AM Quiz 4 IP Project’s due © 2007 Prentice-Hall, Inc
4
Essentials Microsoft Project 2003 Dawn Parrish Wood Mary E. Pascarella
Entering Tasks And Creating A Project Schedule
5
Objectives Enter tasks and specify duration Organize tasks
Create milestone and recurring tasks Link tasks by specifying task predecessors Use outline features and view Work Breakdown Structure (WBS) codes Apply a calendar to a task Set constraints
6
Copyright © 2004 Prentice-Hall. All rights reserved.
Pre-planning Collaboration Past projects Terminology Stakeholders Phase Deliverables Copyright © 2004 Prentice-Hall. All rights reserved.
7
Copyright © 2004 Prentice-Hall. All rights reserved.
Visual Summary Project 3 results Copyright © 2004 Prentice-Hall. All rights reserved.
8
Entering Tasks And Specifying Duration
Follows calendar setup Task entry Gantt chart Task table Import data Copyright © 2004 Prentice-Hall. All rights reserved.
9
Understanding The Fields
ID Automatically assigned Indicator Displays signal icons Task Name Duration Copyright © 2004 Prentice-Hall. All rights reserved.
10
Understanding The Fields (continued)
Start Finish Predecessors Resource Names Copyright © 2004 Prentice-Hall. All rights reserved.
11
To Enter Tasks And Specify Durations
Copyright © 2004 Prentice-Hall. All rights reserved.
12
Copyright © 2004 Prentice-Hall. All rights reserved.
Organizing Tasks Edit the input Phases Logic Output needs Copyright © 2004 Prentice-Hall. All rights reserved.
13
Copyright © 2004 Prentice-Hall. All rights reserved.
Screen Orientation Copyright © 2004 Prentice-Hall. All rights reserved.
14
Copyright © 2004 Prentice-Hall. All rights reserved.
Task Removal Row selection Task renumbering Copyright © 2004 Prentice-Hall. All rights reserved.
15
Multiple Task Selection
Click and drag Next action effects all selected tasks Copyright © 2004 Prentice-Hall. All rights reserved.
16
Creating Milestone And Recurring Tasks
Milestone task No duration, very significant Recurring task Status reviews Summary task Copyright © 2004 Prentice-Hall. All rights reserved.
17
Recurring Task Creation
Copyright © 2004 Prentice-Hall. All rights reserved.
18
Copyright © 2004 Prentice-Hall. All rights reserved.
Warning Box If tasks exist in current project Precaution against overlap Copyright © 2004 Prentice-Hall. All rights reserved.
19
Recurring Task Screen View
Copyright © 2004 Prentice-Hall. All rights reserved.
20
Milestone Task Creation
Copyright © 2004 Prentice-Hall. All rights reserved.
21
Copyright © 2004 Prentice-Hall. All rights reserved.
Smart Tag Information Copyright © 2004 Prentice-Hall. All rights reserved.
22
Linking Tasks By Specifying Task Predecessors
Task interdependency Predecessor Successor Timing differences Lag time Lead time Value of linking Project automatically resets timing Copyright © 2004 Prentice-Hall. All rights reserved.
23
Copyright © 2004 Prentice-Hall. All rights reserved.
Window Orientation Copyright © 2004 Prentice-Hall. All rights reserved.
24
Copyright © 2004 Prentice-Hall. All rights reserved.
Predecessor Link Copyright © 2004 Prentice-Hall. All rights reserved.
25
Copyright © 2004 Prentice-Hall. All rights reserved.
Link Established Assigned task #22 Copyright © 2004 Prentice-Hall. All rights reserved.
26
Task Information Window
Copyright © 2004 Prentice-Hall. All rights reserved.
27
Copyright © 2004 Prentice-Hall. All rights reserved.
Showing The Linkage FF (Finish-to-Finish) The Predecessors column shows 1FF, indicating the Finish-to-Finish link with Task 1. A join line has been added from the end of the Task 1 Gantt bar to the end of the Task 2 Gantt bar (see Figure 3.17). Notice also that this type of relationship does not affect the finish date for Task 2. Copyright © 2004 Prentice-Hall. All rights reserved.
28
Showing The Linkage (continued)
SS (Start-to-Start) Copyright © 2004 Prentice-Hall. All rights reserved.
29
Copyright © 2004 Prentice-Hall. All rights reserved.
Using Outline Features And Viewing Work Breakdown Structure (WBS) Codes Visually identify phases Group related tasks Summary task Subtask WBS codes Default outline numbers Copyright © 2004 Prentice-Hall. All rights reserved.
30
Copyright © 2004 Prentice-Hall. All rights reserved.
Establish Hierarchy Indenting Copyright © 2004 Prentice-Hall. All rights reserved.
31
Copyright © 2004 Prentice-Hall. All rights reserved.
Summary Tasks Copyright © 2004 Prentice-Hall. All rights reserved.
32
Copyright © 2004 Prentice-Hall. All rights reserved.
Outline Level One View Copyright © 2004 Prentice-Hall. All rights reserved.
33
Copyright © 2004 Prentice-Hall. All rights reserved.
View The WBS Code Copyright © 2004 Prentice-Hall. All rights reserved.
34
WBS Code Showing Phases
Numbering convention Copyright © 2004 Prentice-Hall. All rights reserved.
35
Alternate Outlining Methods
Formatting toolbar Project guide Drag and drop Menu bar Copyright © 2004 Prentice-Hall. All rights reserved.
36
Applying A Calendar To A Task
Independent from base project calendar Task-level control Copyright © 2004 Prentice-Hall. All rights reserved.
37
Copyright © 2004 Prentice-Hall. All rights reserved.
Task Dialog Screen Copyright © 2004 Prentice-Hall. All rights reserved.
38
Showing Constraints And Task Calendars
Copyright © 2004 Prentice-Hall. All rights reserved.
39
Copyright © 2004 Prentice-Hall. All rights reserved.
Setting Constraints Constraint types Flexible Not tied to a specific date Inflexible Date-specific, usually tied to external forces Copyright © 2004 Prentice-Hall. All rights reserved.
40
Copyright © 2004 Prentice-Hall. All rights reserved.
Flexible Constraints As Soon As Possible (ASAP) As Late As Possible (ALAP) Finish No Earlier Than (FNET) Finish No Later Than (FNLT) Copyright © 2004 Prentice-Hall. All rights reserved.
41
Inflexible Constraints
Must Finish On (MFO) Must Start On (MSO) Start No Earlier Than (SNET) Start No Later Than (SNLT) Copyright © 2004 Prentice-Hall. All rights reserved.
42
Copyright © 2004 Prentice-Hall. All rights reserved.
Setting Constraints Copyright © 2004 Prentice-Hall. All rights reserved.
43
Summary Enter tasks and specify duration Organize tasks
Create milestone and recurring tasks Link tasks by specifying task predecessors Use outline features and view Work Breakdown Structure (WBS) codes Apply a calendar to a task Set constraints
44
Review Options Key terms Checking concepts and terms Discussion
Skill drill Challenge
45
What are your questions?
Copyright © 2004 Prentice-Hall. All rights reserved.
46
Essentials Microsoft Project 2003 Dawn Parrish Wood Mary E. Pascarella
Scheduling Resources And Assigning Costs
47
Objectives Enter resource information Enter fixed costs
Assign resources to tasks View and modify resource assignments Print resource allocations and project costs
48
Copyright © 2004 Prentice-Hall. All rights reserved.
Why would I Do This? Resource identification Exception handling Cost allocations Copyright © 2004 Prentice-Hall. All rights reserved.
49
Copyright © 2004 Prentice-Hall. All rights reserved.
Visual Summary Project 4 results Copyright © 2004 Prentice-Hall. All rights reserved.
50
Viewing and Setting Up Resources
Resource pool Work resources People Equipment Material resource Consumable Copyright © 2004 Prentice-Hall. All rights reserved.
51
Copyright © 2004 Prentice-Hall. All rights reserved.
Resource Attribute Individual Consolidated Group Interchangeable Copyright © 2004 Prentice-Hall. All rights reserved.
52
Copyright © 2004 Prentice-Hall. All rights reserved.
Resource Sheet View Easiest to use Default values Copyright © 2004 Prentice-Hall. All rights reserved.
53
Resource Sheet View – Key Information
Copyright © 2004 Prentice-Hall. All rights reserved.
54
Indicator Column Icons
Overallocation Note Hyperlink Response pending Copyright © 2004 Prentice-Hall. All rights reserved.
55
Copyright © 2004 Prentice-Hall. All rights reserved.
Icon Information Overallocation Too much work assigned Note About the resource Hyperlink Associates to a file Response pending Copyright © 2004 Prentice-Hall. All rights reserved.
56
Entering A New Resource
Copyright © 2004 Prentice-Hall. All rights reserved.
57
Copyright © 2004 Prentice-Hall. All rights reserved.
Resource List Sort Copyright © 2004 Prentice-Hall. All rights reserved.
58
Entering Resource Information
Associated costs computed by Microsoft Project Copyright © 2004 Prentice-Hall. All rights reserved.
59
Resource Information Dialog Box
Accessed by double-clicking resource Copyright © 2004 Prentice-Hall. All rights reserved.
60
Copyright © 2004 Prentice-Hall. All rights reserved.
Entering Fixed Costs Task-related Copyright © 2004 Prentice-Hall. All rights reserved.
61
Assigning Resources To Tasks
Scheduling formula Duration = Work / Units Calculated automatically Copyright © 2004 Prentice-Hall. All rights reserved.
62
Copyright © 2004 Prentice-Hall. All rights reserved.
Duplication Error Fix Copyright © 2004 Prentice-Hall. All rights reserved.
63
Create Work Resource Assignments
Copyright © 2004 Prentice-Hall. All rights reserved.
64
Adding Second Resource
Copyright © 2004 Prentice-Hall. All rights reserved.
65
Multiple Resources Assigned To One Task
Copyright © 2004 Prentice-Hall. All rights reserved.
66
Viewing and Modifying Resource Assignments
Copyright © 2004 Prentice-Hall. All rights reserved.
67
To Fix Resource Assignment Errors
Overallocation Leveling Assignment units Copyright © 2004 Prentice-Hall. All rights reserved.
68
Copyright © 2004 Prentice-Hall. All rights reserved.
Resource Adjustments Smart Tag Copyright © 2004 Prentice-Hall. All rights reserved.
69
Assignment Information Fixes
Task Copyright © 2004 Prentice-Hall. All rights reserved.
70
Copyright © 2004 Prentice-Hall. All rights reserved.
Results Of Fixes Copyright © 2004 Prentice-Hall. All rights reserved.
71
Assignment Information Changes
Copyright © 2004 Prentice-Hall. All rights reserved.
72
Copyright © 2004 Prentice-Hall. All rights reserved.
Using the Smart Tag Task assignment is now split Copyright © 2004 Prentice-Hall. All rights reserved.
73
Printing Resource Allocations and Project Costs
Resource Usage report To-do List report Budget report Copyright © 2004 Prentice-Hall. All rights reserved.
74
Copyright © 2004 Prentice-Hall. All rights reserved.
Report Includes Copyright © 2004 Prentice-Hall. All rights reserved.
75
Summary Enter resource information Enter fixed costs
Assign resources to tasks View and modify resource assignments Print resource allocations and project costs
76
Review Options Key terms Checking concepts and terms Discussion
Skill drill Challenge
77
What are your questions?
Copyright © 2004 Prentice-Hall. All rights reserved.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.