Welcome to Timberlake Charles (Charley) F. Hurt, P.E.
Presented by Charles (Charley) F. Hurt, P.E. Charles (Chuck) K. Hurt, P.E. April 19, 2004 The Headforemost Co. Consultant Engineers 408 St. Andrews Circle Lynchburg, VA 24503 (434) Acknowledgements & Thanks Charles Falwell, Falwell Well Corp. The News & Daily Advance Hurt & Proffitt, Inc. Designed by: Betty Anne Hurt
3
History Timberlake “the gem of the Piedmont”
70 acres of lake and golf course Developed in the fall of 1926 Developers The Timberlake Corp. Edley Craighill, Engineer F. L. Showalter, Contractor The Dam was designed for the 100-year flood The Timberlake Corp. took bankruptcy in 1930 The Peaksview Corp. bought the property in 1945 The water system was given to CCUSA in 1970 The Homeowners Assn. (HOA) was set up in 1986 and continued until 1990
4
TIMBERLAKE As it was…
5
Timberlake aas it was
6
Sailing
7
Across the Water
8
DAM FAILURE June 22, 1995 Century’s hardest recorded Rainfall
9” in 4 to 5 hours DAM FAILURE
9
Break in Dam Washout from the Dam Failure 6/22/95
10
Break in Dam The Break
11
Southside of Road Over Dam
12
Lake Bed After Dam Break
13
Principle Spillway
14
Boat Caught in Principle Spillway
15
Looking Downstream Thru the Dam Break
16
Reconstruction of Timberlake
An emergency meeting of the Board of Directors of the HOA was called Reconstruction Committee Charlie Falwell, Chair Restoration Fund Bud Colbert, Chair Licensing and Permits George Shrader, Chair Land Assessments Shaeffer Oglesby
17
Rebuild Dam HOA hired Hurt & Proffitt on July11,1995, to design the reconstruction of Timberlake Bid opening for Dam repairs - May 23, 1996 Construction by Counts & Dobyns began on June 2, 1996 Clay core material was found on adjoining property of Bobby Montgomery Hurricane Fran brought heavy rains half-way through the construction Dam completed November 1, 1996 Refilling of Lake on February 17, 1997 Easter Sunday 1997, after 40 days and 40 nights FULL LAKE water flowed thru the primary spillway
18
Creek thru Timberlake Lake Bed a Year Later 1996
19
Dredging Silt From Lake Bottom 1996
20
Construction of New Dam June 1996 Cutting a Keyway to the Dam
21
Installation of Lake Drain Valve
22
Inspection of Drain Outlet by Hurt & Proffitt
23
Dam 50% Complete
24
Cut in Dam Prior to Storm Fran’s Rains
25
Fran Fills the Lake
26
Beginning of Repairs Due to Fran
27
Repairs to Cut Made for Fran
28
Construction of Emergency Spillway
200 ft. wide by 4.5 ft. deep
29
Dam Completion November 1, 1996
30
Dedication of Dam June 21, 1997
31
Memorial
32
Timberlake Again
38
Good Bye from Timberlake
Presented by Charles (Charley) F. Hurt, P.E. Charles (Chuck) K. Hurt, P.E. The Headforemost Co. Consultant Engineers 408 St. Andrews Circle Lynchburg, VA 24503 (434) Acknowledgements & Thanks Charles Falwell, Falwell Well Corp. The News & Daily Advance Hurt & Proffitt, Inc. Designed by: Betty Anne Hurt