Central Tailings Access Protocol
11/28/2018
2
All projects have a Vale Contact
For the PMO the Vale Contact is: Vale Contact = Vale Construction Coordinator (Supervisor of Services) 11/28/2018
3
Central Tailings Access Forms
Step 1: Make an appointment with CTA Supervisor for a site visit Awarded Contractor is to draft the following forms and submit to Vale Construction Coordinator: Formal Risk Assessment-PHR CTA Contractor Work Permit (completed weekly) Routed Map Adverse Weather Guidelines Road Use Authorization Form (Mon to Fri Dayshift) 11/28/2018
4
Included in PHR Scope of work
Add haulage route to Landfill or PQ Ditch Identify the hazards (road conditions, weather) -will you need an escort? -will you need extra lighting? -will you need a sander/plow/grader? -are the roads slippery? -will weather get worse?(refer to Adverse Weather Guidelines) Tailings Orientation (Tier 3) Tailings access ( Lenel swipe card) Vale Contact or Contractor Haulage Supervisor to sit at the morning safety meeting at Hill Station. 7:00am Discuss hazards mentioned at the morning meeting Supervisor signs in at Hill Station for entire crew and highlight your name on the Sign in Sheet Hazards at the Landfill or PQ Ditch Off shift notification Form sent to Clarabelle Mill Ensure that the “Adverse Weather Guideline” is included in the Risk Assessment as an action to review with all workers 11/28/2018
5
Contractor Work Permit (filled out weekly)
Vale Contact signature
6
Example of Map route (gate #9 to Landfill)
11/28/2018
7
Adverse Weather Guidelines
CTA Forum – 27/10/2015
8
Road Use Authorization Form
9
Central Tailings Access Forms
All CTA forms are available via the external website at extportal.vale.com under the Contractor Portal in the Policies & Programs section 11/28/2018
10
Central Tailings Access Forms
All CTA forms are available via the external website at extportal.vale.com under the Contractor Portal in the Policies & Programs section Central Tailings Area CTA Road Use Authorization Form (Monday to Friday Dayshift only) CTA Control Work Permit Central Tailings Roads Map Adverse Weather Conditions (P42000C) (Adverse Weather Guidelines - Memo rev 3 Oct 20/15) Tailings Access Form (completed form must be sent with Lenel Gate/Swipe Station Access Form) Tailings Access Procedure (P42003) (Changes to Tailings Access - Memo Mar 24/16) CTA Road Use Authorization Form (All Shifts) (with access required after hours, 5pm-7am) Off-Shift Notification Template 11/28/2018
11
Central Tailings Access Forms
Step 2: Vale Construction Coordinator to arrange Risk Assessment Meeting. -in addition to the PHR Attendee Requirements, the CTA Supervisor and worker Rep must be invited to review the PHR. 11/28/2018
12
Central Tailings Access Forms
Step 3: After the Risk Assessment Meeting: The Vale Construction Coordinator will sign the CTA Contractor Work Permit. The Vale Construction Coordinator & Vale CTA Supervisor will sign the Road Use Authorization Form. Contractor Supervisor to review PHR with all workers accessing the CTA and sign the PHR Worker Sign Off Sheet. 11/28/2018
13
Central Tailings Access Forms
Step 4: Vale Construction Coordinator to all of the following approved documents to and cc Jay Mills and Denise Lemieux. PHR Contractor Work Permit (completed weekly)and send to Routed Map Adverse Weather Guidelines Road Use Authorization Form 11/28/2018
14
Central Tailings Access Forms
Step 5: Each Contractor Driver must have a copy of all forms in a binder in their vehicle: PHR Contractor Work Permit (updated weekly at the morning meeting) Route Map Adverse Weather Guidelines Road Use Authorization Form 11/28/2018
15
Central Tailings Access Forms
Step 6: The Vale Construction Coordinator or Contractor Haulage Supervisor must attend the morning Central Tailings 7:00 am meeting in the Hill Station lunchroom each day the Contractors will be accessing the Central Tailings Area. -To review potential hazards , high risk tasks and interferences 11/28/2018
16
After Hours (5:00 pm-7:00 am and weekends) 11/28/2018
17
Lenel Gate/Swipe Station Access Form to be attached to Tailings Access Form and sent to for approval CTA Forum – 27/10/2015
18
Central Tailings Access Forms
If access to the CTA is required for after daylight hours the Vale Construction Coordinator must contact Gary Remington to arrange after hours access for Contractors hauling to the Landfill Site 11/28/2018
19
Revise the PHR Or Create a JHA To Include: 11/28/2018 Scope of work
Add haulage route to Landfill or PQ Ditch . Identify the hazards (road conditions, weather) -will you need an escort? -will you need extra lighting? -will you need a sander/plow/grader? -are the roads slippery? -will weather get worse?(refer to Adverse Weather Guidelines) Site Indoc Tailings access ( Lenel swipe card) Contractor Supervisor to sit at the morning safety meeting at Hill Station. 7:00am Any new hazards mentioned at the morning meeting Supervisor signs in at Hill Station for entire crew and highlight your name on the Sign in Sheet Hazards at the Landfill or PQ Ditch Off shift notification Form sent to Clarabelle Mill Ensure that the “Adverse Weather Guideline” is included in the Risk Assessment as an action to review with all workers 11/28/2018
20
11/28/2018
21
Central Tailings Access Forms
11/28/2018
22
If anyone is requesting access for other drivers
11/28/2018
23
Lenel Gate/Swipe Station Access Form to be attached to Tailings Access Form and sent to for approval CTA Forum – 27/10/2015
24
Guy Shank_________705-897-6710 Worker Rep (Clarabelle Mill)
Any questions contact : Jerry Brouse_______ Operations Supervisor CTA (projects) Jay Mills __________ Operations Supervisor CTA Denise Lemieux____ Superintendent-Water Plants,Tailings Guy Shank_________ Worker Rep (Clarabelle Mill) 11/28/2018