Project Scheduling – Critical Path Method (CPM)
Bus Shelter Construction Example Job Name Duration Resources Predecessor(s) 1 Shelter Slab 2 2 5 2 Shelter Walls 1 1 1 3 Shelter Roof 2 2 2,4 4 Roof Beam 3 2 2 5 Excavation 2 3 6 Curb and Gutter 2 3 5 7 Shelter Seat 1 2 4,6 8 Paint 1 1 7 9 Signwork 1 2 2,6
4
Bus Shelter Construction
Critical Path Method Results ACT NAME DUR RES EARLY LATE FLOAT CUR CRIT start PATH ST FN ST FN TOT FREE 1 Shelter Slab 2 2 2 4 2 4 2 YES 2 Shelter Walls 1 1 4 5 4 5 4 YES 3 Shelter Roof 2 2 8 10 8 10 8 YES 4 Roof Beam 3 2 5 8 5 8 5 YES 5 Excavation 2 3 2 2 YES 6 Curb and 2 3 2 4 6 8 4 1 2 NO Gutter 7 Shelter Seat 1 2 8 9 8 9 8 YES 8 Paint 1 1 9 10 9 10 9 YES 9 Signwork 1 2 5 6 9 10 4 4 5 NO