Software Requirements
Michael P. Rupen EVLA Project Scientist for Software Rupen EVLA Advisory Committee Meeting May 8-9, 2006
2
EVLA Advisory Committee Meeting
General Approach Requirements developed in , re-prioritized in 2005 Each is assigned a priority… 1: essential; 2: important; 3: desirable …and timescale Z: test antennas (now) A: Prototype Correlator (2007 Q2) B: Limited Production Correlator (2007 Q4) C: Science commissioning (2008) D: Shared-risk observing (end of 2009) E: Full science operations (2012) Transition issues embedded in main documents QUESTION: are the timescales correct??? This is from the latest (31dec05) e2e requirements doc. Rupen EVLA Advisory Committee Meeting May 8-9, 2006
3
EVLA Advisory Committee Meeting
General Approach “Living” documents Much direct interaction between responsible parties and programmers (e.g., Subsystem Scientists) (mostly) single-site project much on-going VLA expertise transition issues react to schedule and staffing changes Rupen EVLA Advisory Committee Meeting May 8-9, 2006
4
On-line and Science Domains
Proposal Submission ObsPrep Scheduler Archive (science and monitor) Quicklook Pipeline ObsMon Would like common block diagram with others, highlighting which bits we’re talking about Rupen EVLA Advisory Committee Meeting May 8-9, 2006
5
On-line and Science Domains
Requirements documents: Timescales and Deliverables (Dec 05) Science Software Requirements (Dec 05) Engineering Software Requirements (Aug 03) Operations Software Requirements (Jun 03) WIDAR/CBE Requirements ( ) Recent efforts re-organize by time comare priorites with resources Rupen EVLA Advisory Committee Meeting May 8-9, 2006
6
On-line and Science Domains
Status in reasonably good shape – not holding back development need to prioritize within “priority 1”, given staffing prognosis timescale: late summer/early fall Rupen EVLA Advisory Committee Meeting May 8-9, 2006
7
Post-Processing (CASA)
Pipelines Interactive processing Rupen EVLA Advisory Committee Meeting May 8-9, 2006
8
EVLA Advisory Committee Meeting
Post-Processing Requirements documents: Science Software Requirements (Jul 03) Recent efforts re-visiting priorities and timescales new WIDAR schedule ramping up EVLA involvement in CASA moving CASA from development to user domain Rupen EVLA Advisory Committee Meeting May 8-9, 2006
9
EVLA Advisory Committee Meeting
Post-Processing Status should be re-visited, now that we have a better idea of EVLA capabilities vs. time connecting now to 2012 “delta” requirements (vs. ALMA) tricky since we are moving faster than they in some areas Rupen EVLA Advisory Committee Meeting May 8-9, 2006