Download presentation
Presentation is loading. Please wait.
Published bySara Río Sáez Modified over 6 years ago
1
Mississippi Riverbank Project (Final Presentation) May 14, 1999
Architect: Steve GEORGALIS Georgia Institute of Technology Structural Engineer: Tomo CEROVŠEK University of Ljubljana Construction Manager: . Jacky HO Stanford University Owner: Ali AL-ALI
2
Agenda Project Introduction Four Preliminary Design Alternatives
Final Design - A / E / C Solutions and Interactions Learning Experience
3
Introduction Building for Riverbank University in Sacramento
Virtual Project (Year 2010) Produce 4 Alternatives and 1 Final Design Practice A/E/C Interaction
4
Requirements Architectural Requirements Structural Requirements
Maintain Footprint & Transportation / Circulation Occupancy, Security, Environmental (3 stories, total height 35’) Structural Requirements Load: Earthquake and Total Height of 35’ Construction Requirements Budget : $5,500,000 (Structural $550,000) Time Budget : 12 months (ready in May 2012)
5
4 Alternatives 1 2 3 4 $4,500, $4,900, $4,700,000 $4,100,000
6
Building Site
7
Alternative 1
8
Alternative 1
9
Alternative 2
10
Alternative 2
11
Alternative 3 3rd floor
12
Alternative 3
13
Alternative 4
14
Reasons for choosing Alternative 2
Owner’s Decision Aesthetic and Challenging Design Team’s Preference Attracting Glass Atrium Challenging Structural Systems Feasible in Time and Cost
15
Further Iterations and Evaluations
Meeting with Owner Height Limit Faculty Lounge Atrium Design Structural Materials Revised design Feedback on cost Suggestions and changes Revised design material choice E C Revised design Feedback on cost and constructibility
16
Discussion on Faculty Lounge
17
Discussion on Structural Materials
Prefab Steel Frame for Atrium Cast-in-place Concrete Columns
18
Final Design
19
Final Design
20
Architecture: 1st Floor
21
Architecture: 2nd Floor
22
Architecture: 3rd Floor
23
Architecture: Section
24
Architecture: Footage Evaluation
25
Engineering: Structural Model
26
Engineering: Structural Model
27
Engineering: Loads Live Loads: Dead Loads:
Classrooms: 40 psf Offices: 50 psf Halls: 100 psf Dead Loads: Self weight, floor and partitions 30 psf MEP 10 psf Seismic Load: zone 3 (solid rock)
28
Engineering: SAP2000 Model
29
Engineering: Framing System
30
Engineering: Moments of the Plate
31
Engineering: Mode Shapes
32
Engineering: Moment Diagram
33
Typical members and connection
Beam spacing: 19’ Typical column: 18’’x18’’ Reinforcement: 3.5% Typical beam: 16’’x20’’ Foundations: 4’x4’
34
Construction: Cost
35
Construction: Cost Breakdown
36
Construction: Cost Breakdown
37
Construction: Schedule
Total Duration: 10 months Milestone 1: Start of Concrete Superstructure Milestone 2: Finish of Concrete Superstructure Milestone 3: Finish of Glass Atrium
38
Construction: Milestone 1
June 20, 2011 Completion of Foundation and Auditorium Start Concrete Frames
39
Construction: Milestone 2
Sept 20, 2011 Completion of Concrete Frame Start Atrium
40
Construction: Milestone 3
Dec 10, 2011 Completion of Atrium Continue Interior Construction
41
Construction: Site Layout
42
Construction: Equipment
Excavation 90,000 CF of soil Excavator Dump truck Cast-in-place Concrete 3,500 LF of Columns and Beams Pumper Truck Concrete Mixer Atrium Steel Frame Max height: 36 feet Crane Truck
43
PUT A FINAL MODEL HERE FOR WRAP UP
44
Learning from AEC A A C C E E Roles of A / E / C
New communication technology New team working environment Using 3D Model A E C A E C
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.