Presentation is loading. Please wait.

Presentation is loading. Please wait.

Mississippi Riverbank Project (Final Presentation) May 14, 1999

Similar presentations


Presentation on theme: "Mississippi Riverbank Project (Final Presentation) May 14, 1999"— Presentation transcript:

1 Mississippi Riverbank Project (Final Presentation) May 14, 1999
Architect: Steve GEORGALIS Georgia Institute of Technology Structural Engineer: Tomo CEROVŠEK University of Ljubljana Construction Manager: . Jacky HO Stanford University Owner: Ali AL-ALI

2 Agenda Project Introduction Four Preliminary Design Alternatives
Final Design - A / E / C Solutions and Interactions Learning Experience

3 Introduction Building for Riverbank University in Sacramento
Virtual Project (Year 2010) Produce 4 Alternatives and 1 Final Design Practice A/E/C Interaction

4 Requirements Architectural Requirements Structural Requirements
Maintain Footprint & Transportation / Circulation Occupancy, Security, Environmental (3 stories, total height 35’) Structural Requirements Load: Earthquake and Total Height of 35’ Construction Requirements Budget : $5,500,000 (Structural $550,000) Time Budget : 12 months (ready in May 2012)

5 4 Alternatives 1 2 3 4 $4,500, $4,900, $4,700,000 $4,100,000

6 Building Site

7 Alternative 1

8 Alternative 1

9 Alternative 2

10 Alternative 2

11 Alternative 3 3rd floor

12 Alternative 3

13 Alternative 4

14 Reasons for choosing Alternative 2
Owner’s Decision Aesthetic and Challenging Design Team’s Preference Attracting Glass Atrium Challenging Structural Systems Feasible in Time and Cost

15 Further Iterations and Evaluations
Meeting with Owner Height Limit Faculty Lounge Atrium Design Structural Materials Revised design Feedback on cost Suggestions and changes Revised design material choice E C Revised design Feedback on cost and constructibility

16 Discussion on Faculty Lounge

17 Discussion on Structural Materials
Prefab Steel Frame for Atrium Cast-in-place Concrete Columns

18 Final Design

19 Final Design

20 Architecture: 1st Floor

21 Architecture: 2nd Floor

22 Architecture: 3rd Floor

23 Architecture: Section

24 Architecture: Footage Evaluation

25 Engineering: Structural Model

26 Engineering: Structural Model

27 Engineering: Loads Live Loads: Dead Loads:
Classrooms: 40 psf Offices: 50 psf Halls: 100 psf Dead Loads: Self weight, floor and partitions 30 psf MEP 10 psf Seismic Load: zone 3 (solid rock)

28 Engineering: SAP2000 Model

29 Engineering: Framing System

30 Engineering: Moments of the Plate

31 Engineering: Mode Shapes

32 Engineering: Moment Diagram

33 Typical members and connection
Beam spacing: 19’ Typical column: 18’’x18’’ Reinforcement: 3.5% Typical beam: 16’’x20’’ Foundations: 4’x4’

34 Construction: Cost

35 Construction: Cost Breakdown

36 Construction: Cost Breakdown

37 Construction: Schedule
Total Duration: 10 months Milestone 1: Start of Concrete Superstructure Milestone 2: Finish of Concrete Superstructure Milestone 3: Finish of Glass Atrium

38 Construction: Milestone 1
June 20, 2011 Completion of Foundation and Auditorium Start Concrete Frames

39 Construction: Milestone 2
Sept 20, 2011 Completion of Concrete Frame Start Atrium

40 Construction: Milestone 3
Dec 10, 2011 Completion of Atrium Continue Interior Construction

41 Construction: Site Layout

42 Construction: Equipment
Excavation 90,000 CF of soil Excavator Dump truck Cast-in-place Concrete 3,500 LF of Columns and Beams Pumper Truck Concrete Mixer Atrium Steel Frame Max height: 36 feet Crane Truck

43 PUT A FINAL MODEL HERE FOR WRAP UP

44 Learning from AEC A A C C E E Roles of A / E / C
New communication technology New team working environment Using 3D Model A E C A E C


Download ppt "Mississippi Riverbank Project (Final Presentation) May 14, 1999"

Similar presentations


Ads by Google