Personal Software Process Software Estimation
CIS 376 Bruce R. Maxim UM-Dearborn 11/29/2018
2
Product Size Measures Must be:
Precise – gives an exact value for product size and is defined by the product content Specific – based on defined product properties. Countable – automated counting is far less tedious than manual counting and more accurate 11/29/2018
3
Establishing Satandards
Database Projects fields, tables GUI elements, queries, code lines GUI Creation buttons, boxes, labels Programming LOC, FP 11/29/2018
4
Expert Guessing A = The most pessimistic estimate.
B = The most likely estimate. C = The most optimistic estimate. Ê = (A + 4B + C) 6 (Weighted average; where Ê = estimate). 11/29/2018
5
Function Points 11/29/2018 Parameter Simple + Average Complex = Fi
Distinct input items 3( ) 4( ) 6( ) ? Output screens/reports 5( ) 7( ) Types of user queries Number of files 10( ) 15( ) External interface Total 11/29/2018
6
Function Point Equation
F.P.’s = T * ( * Q) T = unadjusted table total Q = score from questionnaire (14 items with values 0 to 5) Cost of producing one function point? May be organization specific. 11/29/2018
7
Function Point Questionnaire
Backup. Data communication. Distributed processes. Optimal performance. Heavily used operating system. On-line data security. Multiple screens. On-line master file update. Complex inputs, queries, outputs. Complex internal processing. Reusable code. Conversion or installation. Multiple user sites. Ease of use. 11/29/2018
8
COCOMO - I Model E = a Sb * m(x) 11/29/2018 BASIC INTERMEDIATE MODE a
BASIC INTERMEDIATE MODE a b Organic 2.4 1.05 3.2 Semidetached 3.0 1.12 Embedded 3.6 1.20 2.8 11/29/2018
9
Basic COCOMO Computes software development effort (and cost) as a function of program size, expressed in estimated lines of code. m(x) = 1 11/29/2018
10
Intermediate COCOMO Computes software development effort as a function of program size and a set of "cost drivers" that include subjective assessments of product, hardware, personnel, and project attributes. m(x) = m(xi) 11/29/2018
11
11/29/2018
12
Detailed COCOMO Includes all characteristics of the intermediate version with an assessment of the cost driver’s impact on each step (analysis, design, ect.) of the software engineering process m(x) based on similar questionnaire 11/29/2018
13
Size Accounting Base – initial unmodified original program
Added – new lines not in base always increases LOC in base count Modified – lines changed in base, does not increase LOC (includes adapted reused code) Deleted – lines removed from base always decreases LOC Reused – unmodified existing code increases LOC Total – net sum of changes in base LOC 11/29/2018
14
Example Base code 500 LOC Added 60 LOC Deleted 40 LOC Modified 30 LOC
Reused 50 LOC Total = – = 570 11/29/2018
15
Using Size Data Planning and tracking Assessing program quality
historical size and time data are necessary to estimate future project Assessing program quality useful in computing defect density and service costs Assessing personal work reused, added, deleted, modified code 11/29/2018
16
Productivity Computed in terms of units produced divided by the time units required to create it Total/time = 570 LOC / 50 hours = 11.2 LOC/hours 11/29/2018
17
Size Counters Manual counting works for small programs not large programs Physical LOC Counters count all text lines except counters Logical LOC Counters only count logical program lines defined by program control structures Counting Program Elements measure sizes of procedures or classes in large programs 11/29/2018
18
Proxy-Based Estimation
Estimates made by comparing new project to previously completed project Requires that you have saved historical data from previous projects May have to do estimation based on similar pieces from multiple projects 11/29/2018
19
Proxy Selection Criteria
Proxy size measure closely related to required development effort Proxy content or product should be automatically countable Proxy should be easy to visualize at project beginning Proxy customizable to needs of each project and developer Proxy sensitive to implementation variations affecting development cost or effort 11/29/2018
20
Possible Proxies Function points Classes Database elements Forms
Scripts Document chapters 11/29/2018
21
Estimation Considerations - 1
Improving Estimation Accuracy break up product in to several parts and compute average of several independent estimates for each Estimating Bias use historical data techniques to minimize impact of subjective judgment Incomplete Knowledge Bias reestimate product size several times during development 11/29/2018
22
Estimation Considerations - 2
Overcompensation caused by making too small an estimate after being too large or the reverse Selecting Abstraction Level get the right grain size Large Systems divide in to separately estimated subsystems Unprecedented Systems build prototypes and extrapolate 11/29/2018
23
PROBE Estimation Method - 1
Step 1: Conceptual Design identify parts of product after conceptual design is finished Step 2: Estimate Parts Size use relative size table to get estimate for each part based on expected size (VS, S, M, L, VL) Step 3: Estimate Sizes of Reused Parts and Base Additions estimate sizes of any additional parts needed 11/29/2018
24
PROBE Estimation Method - 2
Step 4: Size Estimating Procedure select which PROBE method to use (A, B, C, D, E) the default is A Step 5: Time Estimating Procedure check your data to see whether or not you can use method A Step 6: Prediction Interval determine prediction interval surrounding the size or time estimate 11/29/2018
25
PROBE Use - 1 Estimating practice Estimating judgment Outliers
once regression parameters stabilize they do not need to be recomputed for every new program Estimating judgment poor proxy estimates will ruin PROBE estimate Outliers discard obvious outliers from regression data 11/29/2018
26
PROBE Use - 2 Using limited data
you need at least 3 historical data points for regression to work (30 is better) Overcompensation and Undercompensation only make changes when you change processes or discover ineffective practices (normal statistical fluctuations are common) 11/29/2018