Birch bay community park
Project Update - March 7, 2017
2
Site location
4
Community Outreach Planning process Site Inventory and Analysis
Design Survey Cultural Resources Analysis Site Analysis Community Outreach 3 Steering Committee Meetings 3 Community Workshops Development of Master Plan Design Alternatives Development of the Preferred Master Plan Cost Estimate & Phasing Plan
9
Phase I - $3,530,000 On-Site Parking Public Restroom Beach Access
Annual Maintenance $91,000
10
Phase II - $610,000 Multi-purpose Pavilion Open Field Play
Picnic Areas Annual Maintenance $108,000
11
Phase III - $256,000 Nature Play Additional Picnic Areas
Annual Maintenance $110,000
13
Questions?