ColumbiaGrid Planning Meeting FERC Order 1000 Activities June 7, 2018
2
In This Presentation ITP Submittal Summary Status
Overview of ITPs – based on public information provided by project sponsors Status Ongoing activities Milestones/Timeline
3
Interregional Transmission Project (ITP) Submittals
4
ITP: Six (6) Projects For more information regarding these projects, please refer to: overview.cfm
5
TransWest Express Transmission DC Project
Project sponsor: TransWest Express LLC Technology: Two-Terminal, 600kV, Bipole HVDC Connections: Northern terminal: Wyoming (NTTG & potential WestConnect) Southern terminal: Nevada (CAISO, WestConnect) Capacity: Phased 1,500/3,000 MW In-Service Date: 2022 Cost Estimate: $2.11B (initial phase), $0.87B (increase the capacity to 3,000 MW)
6
TransWest Express Transmission DC Project*
*Based on a presentation from TransWest Express LLC , March 31, 2018
7
TransWest Express Transmission DC Project*
*Based on a presentation from TransWest Express LLC, March 31, 2018
8
TransWest Express Transmission AC&DC Project
Project sponsor: TransWest Express LLC Technology: Two-Terminal, 500kV, Bipole HVDC and 500 kV AC Connections: Northern terminal: Wyoming (NTTG & potential WestConnect) Southern terminal: Nevada (CAISO, WestConnect) DC segment connects with the AC segment in Utah Capacity: Phased 1,500/3,000 MW In-Service Date: 2022 Cost Estimate DC segment: $1.62B (1,500 MW), $0.87B (increase to 3,000 MW) AC segment: $600M
9
TransWest Express Transmission AC &DC Project*
*Based on a presentation from TransWest Express LLC, March 31, 2018
10
TransWest Express Transmission AC&DC Project*
*Based on a presentation from TransWest Express LLC , March 31, 2018
11
Cross-Tie Transmission Project
Project sponsor: TRANSCANYON Technology: 213 mile, 500 kV AC Transmission line Connections: Clover (NTTG) & Robinson Summit (WestConnect) 500 kV substations Anticipated Project rating: 1,500 MW In-Service Date: Q4 2024 Cost Estimate: $667M
12
Cross-Tie Transmission Line*
*Based on a presentation from Transcanyon , May 18, 2018
13
Cross-Tie Transmission Line*
*Based on a presentation from Transcanyon, May 18, 2018
14
Southwest Intertie Project (SWIP) - North
Project sponsor: Great Basin Transmission (LS POWER) Technology: 275 mile, 500 kV AC Transmission line Connections: Midpoint (NTTG) & Robinson Summit (WestConnect) 500 kV substations In-Service Date: As early as 2021 Cost Estimate: $525M
15
SWIP - North* *Based on a presentation from LSPOWER , Great Basin Transmission, May, 2018
16
Southwest Intertie Project (SWIP) - North*
*Based on a presentation from LSPOWER , Great Basin Transmission, May, 2018
17
North Gila – Imperial Valley #2 Project
Development team: ITC Grid Development, LLC & Southwest Transmission Partners, LLC Technology: 97-mile, 500 kV AC Transmission line Connections: North Gila (WestConnect) & Imperial Valley (CAISO) 500 kV substations Also interconnect with a new Highline substation (WestConnect) In-Service Date: Q4 2022 Cost Estimate: $250M-$400M
18
North Gila – Imperial Valley #2*
*Based on a presentation from ITC Grid Development, LLC and Southwest Transmission Partners, LLC, May 18, 2018
19
North Gila – Imperial Valley #2*
*Based on a presentation from ITC Grid Development, LLC and Southwest Transmission Partners, LLC, May 18, 2018
20
Renewable Energy Express HVDC Conversion Project
Project sponsor: San Diego Gas and Electric (SDG&E) Technology: Conversion of a portion of existing 500 kV AC Transmission line to a three-terminal HVDC system Anticipated Project rating: 3,000 MW In-Service Date: 2026 Cost Estimate: $900M – $1B
21
Renewable Energy Express HVDC Conversion Project*
*Based on a presentation from SDG&E
22
Renewable Energy Express HVDC Conversion Project*
*Based on a presentation from SDG&E
23
ITP Evaluation: Status
Evaluation plans are being drafted For each ITP Primarily, describe the scope, and methodology will be used by the Relevant Planning Regions to evaluate each project Anticipated completion: End of 2019
24
Question: Paul Didsayabutra, paul@columbiagrid.org