Presentation is loading. Please wait.

Presentation is loading. Please wait.

Progress Report January 2016

Similar presentations


Presentation on theme: "Progress Report January 2016"— Presentation transcript:

1 Progress Report January 2016
Morris Close Burwash Progress Report January 2016 Prepared by Kim Randall Development Officer Hastoe House Association

2 Scheme Review RG Carters have been unable to secure air tightness due to failure in the membrane To achieve air tightness all units need to be stripped back to timber stud and new membrane installed All kitchens are in the process of being removed and stored in a secure unit until remedial works are completed Roof lights have been leaking, inspection highlighted they have not been fitted correctly Removal of roof tiles and exposure to gables and roof lights for repair has commenced Plots 1,2 & 3 plasterboard has been removed and the versaliner exposed ready for installation of new membrane Electrical first fix services have been removed New front doors have been installed to all units Scaffolding erected for external repairs to commence.

3 Remedial Works New doors installed, rear wall has been stripped back to timber battens Plasterboard has been removed to expose the versaliner New membrane to be installed over the versaliner and floor area

4 Key Project Dates Description Date Contract commencement date 29.06.14
Structural investigation & repair Roofing light repairs Remedial works finalised Snagging & desnagging Fit out of units Estimated handover date

5 Scheme Details 8 x affordable units 2 x shared ownership
10 units in total 1 x 1 bedroom bungalow 2 x 1 bedroom flats 2 x 2 bedroom flats 4 x 2 bedroom houses 1 x 3 bedroom house Site possession

6 Hastoe Housing Team - Brede

7 Contact List Hastoe RG Carter Rother Council
Kim Randall - Development Officer Responsible for managing the development of the scheme RG Carter Nick Pitcher- Site Manager Contact details T.B.C Responsible for site management Rother Council Amy Fearn – Housing and Asset Development Officer – Responsible for allocation queries and Rother Council waiting lists for local residents

8 Summary Uncovering sections of previously completed work has revealed additional areas of concern therefore delaying site progress. Although this is a major disappointment we had anticipated additional problems and had added extra time within the program to action any unforeseen issues. We have commenced remedial works on these areas and finalised the detail to secure air tightness which is required to achieve Passivhaus standards. We are still looking to handover on , but this still remains a provisional date Hastoe would like to apologise for any inconvenience caused due to the delay for this scheme and we want to thank the Parish Council & Local Authority for their continued support.


Download ppt "Progress Report January 2016"

Similar presentations


Ads by Google