1 Capital and Tenant Improvements FY-2019
May 9 ,2018 CJ Jones Maricopa County Capital Project Manager

2 Maricopa County Central Animal Care & Control Improvements
Consolidate Mesa Facility into Durango campus Approximately 60,000SF New & 60,000SF Renovation Design Bid Build   

3 Southport Adult Probation Addition and Renovation
10,000SF Addition 5,000SF Renovation Design complete Construction to start July/August Design Bid Build   

4 Shooting Range at Buckeye Hills – Permanent Electric Service
Design and Construction Facility Currently on 100% generator power $1.3 Million in FY19   

5 Superior Court – Grand Jury at West Courts
Design and Construction $3.4 Million in FY 19   

6 Equipment Services – Fuel Stations
Design and Construction - New Station at the Durango Campus - (35th Ave and Lower Buckeye) Replacement at SE Campus - (Mesa)    $4.5 Million $277,000

7 SE Regional Justice Courts
Design (2019) $3.1 Million Construction (2020) $32.4 Million Consolidate 4 outlying justice court facilities into one facility   

8 Current Projects – 225 W. Madison Adaptive Reuse of Madison St. Jail
  

9 Current Projects – 225 W. Madison Adaptive Reuse of Madison St. Jail
  

10 Current Projects – Intake, Transfer, and Release Facility
  

11 Current Projects – Intake, Transfer, and Release Facility
  

12 Future Projects Central Courts Remodel (FY19 spanning several years)
Central Courts Remodel (FY19 spanning several years) Demolition of 1st Ave Jail (FY20) Renovation of Central Courts Plaza (FY20/21) Reorganization and Renovation of Administration Building (FY20/21) Demolition of Durango Jail (FY21) Security Fence at Durango Campus (FY21)   