Download presentation
Presentation is loading. Please wait.
1
Specifications Updates and Approval
Distrelay model Specifications Updates and Approval Megan Cammarano | MVWG Meeting | June 15, 2016
2
Updates to WECC Model Specifications
overview Drivers and Need Updates to WECC Model Specifications The Generic Distance Relay Model was approved January 23, 2014 Model Approval Including examples of proper operation
3
Drivers and need
4
2011 Southwest blackout event
FERC & NERC report called for improved planning Modeling of automatic actions Reduce assumptions made on timing of actions Expand entities’ external visibility More complete data sharing WECC response agreed to model relays TSS created the Modeling SPS and Relays Ad-Hoc Task Force (MSRATF) to develop and/or implement relay models WECC developed DISTRELAY model specs
5
Tpl-001-4 Accurate representation of system elements Protection will have significant impact on system performance As stated in TPL-001-4, R4, Part analysis should include: “Tripping of Transmission lines and transformers where transient swings cause Protection System operation based on generic or actual relay models.”
6
PRC-026 Ensuring load-responsive protective relays do not trip in response to stable power swings during non-Fault conditions Relay models as a part of the system model allow for PRC-026 testing as a part of the annual TPL assessment Requirement R1 criterion 4 references TPL and states relay tripping must be assessed within the annual TPL assessment
7
Updates to wecc model specifications
8
Add language If the fault persists, both ends should reopen, following the same timeline as their initial opening. If the input parameter RecloseWithFault is set to 0, when the fault persists, the second end to reclose will not reclose.
9
Include parameter “reclosewithfault”
Allows for line “testing” Set parameter to 0 to enable If the first end of the line to reclose recloses on a fault, the second end of the line will not reclose
10
Motion Change model specifications to those outlined: Include clarification that relays should be able to trigger breakers to reopen after reclosing if the fault persists Add parameter “RecloseWithFault” to allow for line testing
11
Model approval
12
Seattle City light system overview
Service area population: ~800,000 ~1,900 MVA system load peak 15 major substations 50 transmission lines (656 miles) 92 distance relays
13
Model examples Using PowerWorld Version 19 Without transfer trip Direct Underreaching Transfer Trip (DUTT) Permissive Overreaching Transfer Trip (POTT)
14
Example W/O Transfer Trip
Contingency: Three-phase fault applied at 1 second on Shoreline to Bothell Ckt 2 at 10% of the line
15
Example W/O Transfer Trip
Bus 1 should open 6 cycles after the fault is applied (Zone 1 Protection) Bus 2 should open 26 cycles after the fault is applied (Zone 2 Protection) Bothell Shoreline
16
Simulation results correct!
Example w/o transfer trip Transient Stability Started at 5/18/2017 3:06:00 PM Time: Event: Apply Solid Fault (3PB) Line BOTHELL TO SHORELIN CKT 2 Time: Event: Relay A Zone 1 tripped Line BOTHELL TO SHORELIN CKT 2 Time: Event: Line Relay DISTRELAYRF,Direct Trip action: Open From End Line BOTHELL TO SHORELIN CKT 2 Time: Event: Relay A Zone 2 tripped Line BOTHELL TO SHORELIN CKT 2 Time: Event: Line Relay DISTRELAYRF,Direct Trip action: Open To End (Both ends now Open) Line BOTHELL TO SHORELIN CKT 2 Transient Stability Solution Finished at 5/18/2017 3:11:01 PM
17
Simulation results Example W/O Transfer Trip
18
Simulation Results Example W/O Transfer Trip
19
Simulation Results Example W/O Transfer Trip
20
Example W/ Transfer Trip (DUTT)
Contingency: Three-phase fault applied at 1 second on Bothell to Diablo Ckt 1 at 10% of the line
21
Example W/ Transfer Trip (DUTT)
Bothell should open 6 cycles after the fault is applied (Zone 1 Protection) Diablo should open 1 cycle after that (TT communication time) Bothell Diablo
22
Simulation results correct!
Example w/ transfer trip (DUTT) Transient Stability Started at 5/15/2017 1:19:29 PM Time: Event: Apply Solid Fault (3PB) Line BOTHELL TO DIABLO CKT 1 Time: Event: Relay A Zone 1 Entered (pickup) Line BOTHELL TO DIABLO CKT 1 Time: Event: Line Relay DISTRELAYRF,Direct Trip action: Open From End Line BOTHELL TO DIABLO CKT 1 Time: Event: Line Relay DISTRELAYRF,Transfer Trip action: Open To End (Both ends now Open) Line BOTHELL TO DIABLO CKT 1 Transient Stability Solution Finished at 5/15/2017 1:24:25 PM
23
Simulation results Example W/ Transfer Trip (DUTT)
24
Simulation results Example W/ Transfer Trip (DUTT)
25
Simulation results Example W/ Transfer Trip (DUTT)
26
Example W/ Transfer Trip (pott)
Contingency: Three-phase fault applied at 1 second on Delridge to Duwamish Ckt 1 at 10% of the line
27
Example W/ Transfer Trip (pott)
Delridge should open 6 cycles after the fault is applied (Zone 1 Protection) Duwamish should open 1 cycle after that (TT communication time) Delridge Duwamish
28
Simulation results correct!
Example w/ transfer trip (POTT) Transient Stability Started at 5/15/2017 2:06:46 PM Time: Event: Apply Solid Fault (3PB) Line DELRIDGE TO DUWAMISH CKT 1 Time: Event: Relay A Zone 1 Entered (pickup) Line DELRIDGE TO DUWAMISH CKT 1 Time: Event: Line Relay DISTRELAYRF,Direct Trip action: Open From End Line DELRIDGE TO DUWAMISH CKT 1 Time: Event: Line Relay DISTRELAYRF,Transfer Trip action: Open To End (Both ends now Open) Line DELRIDGE TO DUWAMISH CKT 1 Transient Stability Solution Finished at 5/15/2017 2:11:56 PM
29
Simulation results Example W/ Transfer Trip (POTT)
30
Simulation results Example W/ Transfer Trip (POTT)
31
Simulation results Example W/ Transfer Trip (POTT)
32
DISTRELAY is functioning properly for multiple contingencies
Conclusion DISTRELAY is functioning properly for multiple contingencies No significant increase in computation time With 92 DISTRELAY models
33
motion Approve DISTRELAYRF model and add to WECC Approved Dynamic Model Library Note: Please do not use on series compensated lines until further testing is completed
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.